👉በኮንስትራክሽን ጨረታ ተርንኪ ምንድነው?

‎🚧በኮንስትራክሽን ጨረታ ሰነድ ላይ "ተርንኪ"/"turnkey" ማለት አንድ ነጠላ ተቋራጭ ለእያንዳንዱ የፕሮጀክት ደረጃ ከመነሻ ዲዛይን ጀምሮ እስከ መጨረሻው ግንባታ እና ስራ ድረስ በብቸኝነት የሚወስድበትን የፕሮጀክት ማቅረቢያ ዘዴን ያመለክታል።

⭐️ዋና ግቡ/main goal ለባለቤቱ ሲሰጥ ሙሉ በሙሉ equipped፣ የሚሰራ እና "ለአገልግሎት ዝግጁ" የሆነ የተጠናቀቀ ተቋም ማቅረብ ነው።
‎
🎲 "ተርንኪ"/ "turnkey"የሚለው ቃል የሚያመለክተው ባለቤቱ ሥራውን ለመጀመር ቃል በቃል "ቁልፉን ማዞር" ብቻ ነው፣ ይህም በአፈጻጸም ደረጃ አነስተኛ ተሳትፎ ያስፈልገዋል።
‎
💫በጨረታ ሰነዱ ውስጥ ያሉ ቁልፍ ገጽታዎች/Key Aspects in Bid Documents
‎
‎1. ነጠላ የኃላፊነት ቦታ/Single Point of Responsibility፡- የጨረታ ሰነዱ አንድ ተቋራጭ ለጠቅላላው የፕሮጀክት የሕይወት ዑደት ተጠሪ መሆኑን በግልጽ ያስቀምጣል። ይህም የባለቤቱን በርካታ ውሎችን የማስተዳደር አስተዳደራዊ ሸክም (ለምሳሌ የተለየ ዲዛይነሮች፣ አቅራቢዎች እና ግንበኞች) ይሆናል።
‎
‎2. ሁሉን አቀፍ የስራ ወሰን/Comprehensive Scope of Work፡ ኮንትራክተሩ የዲዛይን፣ የምህንድስና፣ የቁሳቁስ ግዥ፣ ግንባታ፣ ተከላ፣ ሙከራ እና የኮሚሽን ሃላፊነት አለበት።
‎
‎3. የተወሰነ የዋጋ ውል/Fixed Price Contract፡-የተርንኪ ፕሮጄክቶች በጅምር ላይ በተስማሙት በአንድ ጊዜ ድምር ላይ የተመሰረቱ ናቸው፣ይህም ለደንበኛው የወጪ እርግጠኝነትን የሚሰጥ እና የበጀት መብዛትን አደጋን የሚቀንስ ነው (ምንም እንኳን ይህ ብዙውን ጊዜ በመነሻ ዋጋ ላይ የተገነባ የአረቦን ወይም የአደጋ ጊዜ/premium or contingency fee ክፍያን ይጨምራል)።
‎
‎4. አደጋ ማስተላለፍ/Risk Transfer፡- አብዛኛው የፕሮጀክት አደጋዎች፣የዋጋ ጭማሪ፣ የጊዜ ሰሌዳ መዘግየት እና የአፈጻጸም ጉዳዮችን ጨምሮ ከባለቤቱ ወደ ኮንትራክተሩ ይተላለፋሉ።
‎
‎5. የአፈጻጸም ዋስትና/Performance Guarantees፡- የጨረታ ሰነዱ የተጠናቀቀው ፕሮጀክት መደበኛ ተቀባይነት እና የመጨረሻ ክፍያ ከመፈጸሙ በፊት ማሟላት ያለባቸውን ልዩ የሥራ አፈጻጸም መስፈርቶች እና ደረጃዎችን ይዘረዝራል።

‎⭐️የ YouTube ገፃችን ለመቀላቀል ከታች ባለው ሊንክ በመግባት SubScribe አርገው ቤተሰብ ይሁኑ👇

https://youtube.com/@ethiopianconstruction7?si=ils307xXQQpIdCwG

@etconp
❤5👍4
👉 INTERCON Construction Chemicals 

● Concrete Admixtures
● Bonding Agents
● Waterproofings
● Wall Putty, Prime Coat
● Concrete Repair Mortar
● Floor hardener, Epoxy
● Grout, Self-level mortar
● Quartz paint, Contextra
● Tile Adhesive & Tile Joint Fillers 
● Geotextiles and other construction chemicals and materials

☎️ Tel: 0961955555

🔹 Address 1: Signal road, around
Dinberwa Hospital

🔹 Addres 2: Wellosefer, Infront of
Dani Plaza
❤3
👉PILE FOUNDATION – MAIN COMPONENTS

💫A pile foundation is a type of deep foundation used when the near-surface soil is weak and cannot safely carry the load of a structure.

The loads are transferred to deeper, stronger soil layers or rock through piles.

1. PILE (Primary Load-Carrying Element)

What is a Pile?

A pile is a long, slender structural member installed deep into the ground to transfer loads from the structure to competent soil or rock.

Functions of a Pile

Transfer vertical loads (dead + live loads)
Resist lateral loads (wind, earthquake)
Control settlement
Provide stability in weak, expansive, or water-logged soil

Load Transfer Mechanism

Piles carry load in three ways:

End Bearing
Load transferred to hard soil or rock at pile tip
Skin Friction
Load transferred by friction between pile surface and surrounding soil
Combined Action
Both end bearing + skin friction

Types of Piles by Material
Concrete piles

Precast reinforced concrete piles
Cast-in-situ (bored) piles
Steel piles
H-section, pipe piles
Timber piles
Used for light structures (rare today)

2. PILE CAP (Load Distribution Element)

What is a Pile Cap?

A pile cap is a thick reinforced concrete slab or block constructed at the top of piles.
Functions of a Pile Cap
Connects multiple piles into one foundation unit
Distributes column or wall loads uniformly
Ensures equal load sharing among piles
Provides structural integrity and stiffness
Structural Behavior
Acts as a rigid element
Transfers load by bending and shear
Designed as a deep beam or strut-and-tie system
Construction Details
Made of reinforced concrete
Minimum cover provided to resist corrosion
Thickness depends on:
Number of piles
Column load
Pile spacing

3. COLUMN / PIER (Vertical Load Transfer Member)

Role of Column

Transfers load from:
Slabs
Beams
Superstructure
Delivers the load directly to the

pile cap
Connection
Column reinforcement is anchored into the pile cap
Proper development length is required
Ensures monolithic action

4. GROUND BEAM / TIE BEAM
What is a Ground Beam?

A ground beam (also called tie beam) is a reinforced concrete beam connecting two or more pile caps.

Functions

Resists lateral forces (wind, seismic)
Prevents differential settlement
Improves overall foundation stiffness
Helps in load redistribution
Importance in Seismic Areas
Extremely important in earthquake-prone regions
Maintains integrity of foundation system
Often mandatory by structural codes

5. PILE SHOE / PILE TIP (Optional Component)

What is a Pile Shoe?

A pile shoe is a steel or cast-iron attachment fixed at the bottom of some piles.

Purpose

Helps penetration into hard soil or rock
Protects pile end during driving
Improves end bearing capacity
Usage
Common in driven piles
Not always used in bored piles

6. REINFORCEMENT (Structural Steel)
Reinforcement in Piles

Longitudinal bars:
Resist bending and tension
Lateral ties / spirals:
Prevent buckling
Improve confinement

Reinforcement in Pile Cap
Top and bottom reinforcement:
Resist bending
Shear reinforcement:
Prevent punching and shear failure

7. SOIL / BEARING STRATUM (Supporting Medium)

Role of Soil

Final load-receiving element
Must have sufficient:
Bearing capacity
Shear strength
Low compressibility
Soil Investigation
Borehole drilling
SPT / CPT tests
Determines:
Pile type
Pile length
Load capacity

8. DRAINAGE & PROTECTION (Supporting Elements)
Drainage

Prevents water accumulation around pile cap
Reduces corrosion risk
Protection
Concrete cover
Waterproofing (where required)
Anti-corrosion treatment for steel piles

@etconp
❤10👍4
👉የ ከባድ ማሽነሬዎች ኪራይ እንፈልጋለን

እነዚህ ማሽኖች ማለትም ኤክስካቨተር እና ዳምፕ ትራክ ካሎት በ 0924918447 ይደውሉ ወይም @Engkdt ይፃፉልን
👏3❤1
3145. For a simply supported beam with a span of 4 metres, what is the maximum permissible final deflection as per IS: 456 – 2000 including all loads?
Anonymous Quiz
25%
(a) 11.4 mm
23%
(b) 10 mm
39%
(c) 16 mm
14%
(d) 20 mm
👍4❤1
3142. If a soil sample experiences unloading such that σ1 decreases and σ3 is constant, the stress path on the p-q plane will generally move:
Anonymous Quiz
32%
(a) downward and leftward
34%
(b) horizontally to the right
23%
(c) upward and rightward
11%
(d) vertically upward
👍3❤1
3140. Which angle is measured in the 'direct observation of angle method' of theodolite traversing?
Anonymous Quiz
29%
(a) Included angle between survey lines
31%
(b) Vertical angle of slope
35%
(c) Azimuth from north
6%
(d) Magnetic bearing
👍2
3137. Two forces act at a point with an included angle of 90°. The magnitude of their resultant equals either force when:
Anonymous Quiz
20%
(a) forces are unequal but opposite
33%
(b) one force is zero
35%
(c) both forces are equal
12%
(d) angle between forces is 180°
❤3
3136. Which material from municipal solid waste is most effectively reused without significant processing for applications like construction fill?
Anonymous Quiz
14%
(a) Glass bottles
11%
(b) Food waste
23%
(c) Plastic bags
53%
(d) Construction debris
❤6
3135. A soil has a Poisson's ratio of 0.20. Find the coefficient of earth pressure at rest.
Anonymous Quiz
30%
(a) 0.80
25%
(b) 0.20
29%
(c) 0.25
16%
(d) 1.00
❤7
3131. What is the initial process by which a cyclone separator removes particulates from air emissions?
Anonymous Quiz
23%
(a) Electrostatic attraction
34%
(b) Centrifugal force
26%
(c) Chemical absorption
17%
(d) Gravitational settling
👍3❤1
3113. In a horizontal pipe of diameter d mm and length l m carrying oil, whose friction factor is f. If the acceleration due to gravity is g m/s^2 and fluid velocity v m/s, then the head loss due to friction is given by
Anonymous Quiz
33%
(a) flv^2/8gd
28%
(b) flv^2/6gd
27%
(c) flv^2/2gd
12%
(d) flv^2/4gd
❤4
3103. What is called the operation of applying corrections to latitudes and departures in the closed traverse?
Anonymous Quiz
28%
(a) Balancing
18%
(b) Prolonging a line
22%
(c) Offsetting
32%
(d) Traversing
❤8
👉 INTERCON Construction Chemicals 

● Concrete Admixtures
● Bonding Agents
● Waterproofings
● Wall Putty, Prime Coat
● Concrete Repair Mortar
● Floor hardener, Epoxy
● Grout, Self-level mortar
● Quartz paint, Contextra
● Tile Adhesive & Tile Joint Fillers 
● Geotextiles and other construction chemicals and materials

☎️ Tel: 0961955555

🔹 Address 1: Signal road, around
Dinberwa Hospital

🔹 Addres 2: Wellosefer, Infront of
Dani Plaza
❤1
👉የመዲናዋ የመሬት ልማትና አስተዳደር ቢሮ ም/ኃላፊን ጨምሮ 11 አመራርና ሰራተኞች በፖሊስ ተይዘው ፍርድ ቤት ቀረቡ

የአዲስ አበባ ከተማ አስተዳዳር የመሬት ልማት እና አስተዳደር ቢሮ ም/ኃላፊን ጨምሮ 11 አመራር እና ሰራተኞች በፖሊስ ተይዘው ፍርድ ቤት ቀረቡ።

1. አቶ ሞሊቶ አባይነህ ኤርቃሎ የአዲስ አበባ ከተማ አስተዳደር መሬት ልማትና አስተዳዳር ቢሮ የቀድሞ ም/ኃላፊ፣

2. ኢ/ር ቸርነት አበበ የአደቴ የቦሌ ክ/ከተማ መሬት ልማትና አስተዳደር ጽ/ቤት የቀድሞ ኃላፊ፣

3. ሰለሞን በላይ መኮንን የአዲስ አበባ ከተማ አስተዳደር መሬት ልማትና አስተዳዳር ቢሮ የቴክኒክ ጉዳይ ወሳኝ ባለሙያ፣

4. አድማሱ አዳነ ወንድሙ የአዲስ አበባ ከተማ አስተዳደር መሬት ልማትና አስተዳዳር ቢሮ የቅሬታ እና አቤቱታ ባለሙያ፣

5. ግዛቸው ሙሉጌታ ደሴ የአዲስ አበባ ከተማ አስተዳደር መሬት ልማትና አስተዳዳር ቢሮ ይዞታ ማስተካከል ቡድን መሪ፣

6. ደረጀ ጎሹ ሀይሌ የቦሌ ክ/ከተማ ወረዳ 13 የቀድሞ ዋና ሥራ አስፈፃሚ፣

7. አለምፀሃይ ለማ ኪ/ማርያም የቦሌ ክ/ከተማ ወረዳ 13 መሬት ልማትና አስተዳደር የሰነድ አጣሪ ባለሙያ፣

8. ግርማ ተፈራ አያና የአዲስ አበባ ከተማ አስተዳደር መሬት ልማትና አስተዳዳር ቢሮ ህግ/ቴክኒክ ጉዳይ ክትትል ዳይሬክተር፣

9. አማኑኤል አለማየሁ ማሞ የቦሌ ክ/ከተማ ወረዳ 13 የቴክኒክ ባለሙያ፣

10. ቢኒያም ሀይሉ ገብሬ የቦሌ ክ/ከተማ ወረዳ 13  የቴክኒክ ባለሙያ እና 11. አቢዮት ጁፋሬ ባይሳ በአዲስ አበበ ከተማ አስተዳደር ፍትህ ቢሮ የወንጀል ጉዳዮች ዳይሬክተር የነበሩ በቁጥጥር ስር ውለው በፍርድ ቤት ለተጨማሪ ምርመራ የጊዜ ቀጠሮ ተጠይቆ ምርመራው ቀጥሏል።

ግለሰቦቹ ከግበረ አበሮቻቸው ጋር በጥቅም ተመሳጥረው በህዝብና በመንግስት የተሰጣቸውን ኃላፊነት ያለአግባብ በመጠቀም ተጠርጥረዋል።

በዚህም በ2016 ዓ.ም በቦሌ ክ/ከተማ ወረዳ 13 ልዩ ቦታው አየር መንገድ አከባቢ የህዝብ እና የመንግስት ይዞታ የሆነውን በ9ኛው መዋቅራዊ ፕላን በዓድዋ ፓርክነት ተይዞ የነበረውን እና በ10ኛ መዋቅራዊ ፕላን በዊንዶው ኦፍ አፍሪካ ልዩ ልዩ የከተማዉ መተንፈሻ አረንጓዴ ስፍራ ፕሮጀክት በከተማ ደረጃ በመናፈሻነት ለህዝብ አገልግሎት የተያዘ እና በመሬት ባንክ ውስጥ ያለን ይዞታ ያለ ህጋዊ ምክንያት ሰነድ አልባ ይዞታ ነው በማለት ለዮርዳኖስ፣ ዘውዲቱ እና ጓደኞቻቸው የሲሚንቶ አከፋፋይ ህብረት ሽርክና ማህበር ለሚባሉት የቦታው ስፋት 2 ሺህ 905 ካ.ሜ ይዞታ ማረጋገጫ ካርታ የቦታው ሊዝ ዋጋ 168 ሚሊየን 724 ሺህ 405 ብር የሚገመትን ጉዳት በማድረስ ከወረዳ፣ ክ/ከተማ እና መሬት ልማትና አስተዳደር ቢሮ ድረስ በጥቅም ተሳስረዉ ስልጣንን ያለ አግባብ በመገልገል ከባድ የሙስና ወንጀል ተጠርጥረዋል።

በዚህም በፖሊስ ቁጥጥር ስር ውለው በፌደራል ከፍተኛ ፍርድ ቤት ልደታ ምድብ ችሎት ቀርበው ተጨማሪ ጊዜ ቀጠሮ ተጠይቆባቸው ምርመራው መቀጠሉን ኤፍቢሲ ዘግቧል።

@etconp
❤4😱1
👉የ ከባድ ማሽነሬዎች ኪራይ እንፈልጋለን

እነዚህ ማሽኖች ማለትም ኤክስካቨተር እና ዳምፕ ትራክ ካሎት በ 0924918447 ይደውሉ ወይም @Engkdt ይፃፉልን
❤3
👉ደረጃዎችን ለማስላት የወገብ ንጣፍ ቅርጽ የሥራ ትሬድ/Waist slab form work tread ወይም መወጣጫ ቅጽ የሥራ መወጣጫ ከፍታ/riser form work riser height 15 ሴ.ሜ +15 ሴሜ = 30 ሴ.ሜ ነው፤ለምን 15 ሴ.ሜ አይሆንም?
‎
🔰የ15 ሴሜ (ወይም 150 ሚሜ) መወጣጫ ቁመት በደረጃ ዲዛይን እንደ መደበኛ ፣ ergonomic እና ደህንነትን ያከብራል፣ ይህም ደረጃዎቹ ለመውጣት ምቹ መሆናቸውንና fatigue እንደማይፈጥሩ ለማረጋገጥ ነው ።
‎
‎🔰ምሳሌ "15 ሴሜ + 15 ሴሜ = 30 ሴ.ሜ" አጠቃላይ ቁመታዊ ከፍታ በሁለት እርከኖች ላይ በማስላት ወይም አጠቃላይ የከፍታ ቁመትን ምቹ በሆነ ክልል (15-17 ሴ.ሜ) በማስቀመጥ የተለመደ ሁኔታን ይወክላል።
‎
⏺‎በደረጃ ስሌቶች ውስጥ 15 ሴ.ሜ (150 ሚሜ) በተደጋጋሚ ጥቅም ላይ የሚውለው ለዚህ ነው።
‎
🏷‎ስነ ምቾት እና ደህንነት/Ergonomics and Safety፡ ከ15-17 ሴ.ሜ የሚደርስ ከፍታ ያለው 
‎
‎1)በጉልበቶች እና ዳሌ ላይ የሚፈጠር አካላዊ ጫናን ለመቀነስ፣
‎2)መሰናክሎችን ለመከላከል እና
‎3)ተፈጥሯዊ ደህንነቱ የተጠበቀ የመውጣት እንቅስቃሴን ለማረጋገጥ ተመራጭ ተደርጎ ይወሰዳል።
‎
‎⭐️የግንባታ ኮድ ደረጃዎች/Building Code Standards፡- max riser heights ያለው can go up to 190-200 ሚሊ ሜትር በአንዳንድ ኮዶች ከፍ ሊል ቢችልም፣ 150 ሚሜ–170 ሚሜ በአጠቃላይ ለአጠቃቀም ምቹነት በተለይም በመኖሪያ ሕንፃዎች ውስጥ ይመረጣል።
‎
‎⏺ወጥነት ያለው ሪትም/Consistent Rhythm፡ ዝቅተኛ፣ ወጥ የሆነ ከፍታ (እንደ 15 ሴ.ሜ) መጠበቅ ተጠቃሚው የእግር መራመጃቸውን እንዳይሰብር ያደርጋል፣ ይህም የደህንነት ዋና ምክንያት ነው።
‎
‎🎲ሃሳባዊ የእርምጃ ሬሾ/Ideal Step Ratio፡ የ15 ሴ.ሜ መወጣጫ ብዙውን ጊዜ ከ30 ሴ.ሜ ትሬድ (1:2 ሬሾ) ጋር በጥሩ ሁኔታ ይጣመራል፣ ደህንነቱ የተጠበቀ፣ ገደላማ ያልሆነ (ከ30°-35° አካባቢ)።
‎
‎📜አውዳዊ ስሌቶች/Contextual Calculations) በእርስዎ ምሳሌ፡-
‎
💫Vertical Height Calculation፡- 30 ሴ.ሜ ቁመታዊ ቦታ/vertical space መሸፈን ካስፈለገ እያንዳንዳቸው 15 ሴ.ሜ መወጣጫ ያላቸውን ሁለት እርከኖች መጠቀም (15+15=30) ደረጃውን የጠበቀ ምቹ የንድፍ ምርጫ ከአንድ ቁልቁል 30 ሴ.ሜ እርምጃ ነው/ If a 30 cm vertical space needs to be covered, using two steps with a 15 cm riser each (15+15=30) is a standard, comfortable design choice rather than one steep 30 cm step.
‎
‎🚧የቅጽ ሥራ ስሌት/Formwork Calculation፡- የበረራውን አጠቃላይ ቁመት (አቀባዊ ርዝመት/Vertical Length) ሲያሰሉ መሐንዲሶች የሚጠቀሙት: የRisers ብዛት * የRisers ከፍታ (ለምሳሌ 15 ሴ.ሜ)።
‎
‎💫መወጣጫው ከ15 ሴ.ሜ (ለምሳሌ ከ18-20 ሴ.ሜ) ከፍ ያለ ከሆነ አሁንም በኮድ ውስጥ ነው ያለው፣ ግን ምቹ አይደለም። 15 ሴ.ሜ መጠቀም በቀላሉ ergonomic ምርጥ ልምምድ ለ "ገራገር" ደረጃዎች/a "gentle" staircase ነው።

‎⭐️የ YouTube ገፃችን ለመቀላቀል ከታች ባለው ሊንክ በመግባት SubScribe አርገው ቤተሰብ ይሁኑ👇

https://youtube.com/@ethiopianconstruction7?si=ils307xXQQpIdCwG
‎
‎@etconp
❤7👍2👏1