👉ሚድሮክ ኢንቨስትመንት ግሩፕ በ3.3 ቢልየን ብር ወጭ የባህርዳሩን ጣና ሆቴል በአዲስ መልክ ሊገነባው ነው።
ግሩፑ ይህንን ያስታወቀው ዛሬ በባህር ዳር ከተማ ከባለድርሻ አካላት ጋር ባደረገው ስብሰባ ነው ::
በፎርፖይንት ባይ ሸራተን ማርዮት ኢንተርናሽናል ደረጃ በአዲስ መልክ የሚገነባው ጣና ሆቴል 120 ዘመናዊ የመኝታ ክፍሎች :የስብሰባ አዳራሾች ፡ ዘመናዊ የ መዋኛ ገንዳ:
ጅምና ሰፓ ይኖሩታል ተብሏል ::
ግንባታው በ18 ወራት ወራት ውስጥ ይጠናቀቃል ተብሎ ግምት ተሰጥቶታል ::
@etconp
ግሩፑ ይህንን ያስታወቀው ዛሬ በባህር ዳር ከተማ ከባለድርሻ አካላት ጋር ባደረገው ስብሰባ ነው ::
በፎርፖይንት ባይ ሸራተን ማርዮት ኢንተርናሽናል ደረጃ በአዲስ መልክ የሚገነባው ጣና ሆቴል 120 ዘመናዊ የመኝታ ክፍሎች :የስብሰባ አዳራሾች ፡ ዘመናዊ የ መዋኛ ገንዳ:
ጅምና ሰፓ ይኖሩታል ተብሏል ::
ግንባታው በ18 ወራት ወራት ውስጥ ይጠናቀቃል ተብሎ ግምት ተሰጥቶታል ::
@etconp
❤15👍2
👉Steel Structure Components
📌Column: Vertical member that carries loads to the foundation.
📌Beam: Horizontal member supporting floors/roof loads.
📌Rafter: Sloped beam forming the roof structure.
📌Purlin: Supports roof sheets and transfers load to rafters.
📌Girt: Horizontal wall support for cladding panels.
📌Bracing (Roof/Wall): Provides stability against wind and seismic forces.
📌Knee Brace: Strengthens beam-column joints.
📌Crane Beam: Supports overhead crane movement in industrial buildings.
📌Base Plate & Anchor Bolt: Connects steel column to concrete foundation.
📌Connections (Splice/Moment/End Plate): Join steel members safely.
🚧In short: Load flows from roof → purlin → rafter → beam → column → foundation.
@etconp
📌Column: Vertical member that carries loads to the foundation.
📌Beam: Horizontal member supporting floors/roof loads.
📌Rafter: Sloped beam forming the roof structure.
📌Purlin: Supports roof sheets and transfers load to rafters.
📌Girt: Horizontal wall support for cladding panels.
📌Bracing (Roof/Wall): Provides stability against wind and seismic forces.
📌Knee Brace: Strengthens beam-column joints.
📌Crane Beam: Supports overhead crane movement in industrial buildings.
📌Base Plate & Anchor Bolt: Connects steel column to concrete foundation.
📌Connections (Splice/Moment/End Plate): Join steel members safely.
🚧In short: Load flows from roof → purlin → rafter → beam → column → foundation.
@etconp
❤8👍5
👉Types of Construction Contract
1. Lump Sum Contract
Fixed total price for the whole project
Best for projects with clear scope and drawings
2. Unit Price Contract
Payment is based on quantity of work completed
Common in road and infrastructure projects
3. Cost Plus Contract
Owner pays actual cost + contractor’s fee
Suitable for complex or changing projects
4. Time and Material Contract
Payment depends on labor time and materials used
Used for repair, maintenance, or emergency work
5. Design-Bid-Build (DBB)
Design and construction are separate contracts
Traditional and widely used method
6. Design-Build (DB)
One contractor handles both design and construction
Faster project completion and better coordination
7. Design-Build-Operate (DBO)
Contractor designs, builds, and operates the facility
Common in industrial and utility projects
8. Construction Management Contract
Construction manager supervises the entire project
Improves planning, quality, and cost control
🏷Please Subscribe Our Youtube Channel👇
https://youtube.com/@ethiopianconstruction7?si=ils307xXQQpIdCwG
@etconp
1. Lump Sum Contract
Fixed total price for the whole project
Best for projects with clear scope and drawings
2. Unit Price Contract
Payment is based on quantity of work completed
Common in road and infrastructure projects
3. Cost Plus Contract
Owner pays actual cost + contractor’s fee
Suitable for complex or changing projects
4. Time and Material Contract
Payment depends on labor time and materials used
Used for repair, maintenance, or emergency work
5. Design-Bid-Build (DBB)
Design and construction are separate contracts
Traditional and widely used method
6. Design-Build (DB)
One contractor handles both design and construction
Faster project completion and better coordination
7. Design-Build-Operate (DBO)
Contractor designs, builds, and operates the facility
Common in industrial and utility projects
8. Construction Management Contract
Construction manager supervises the entire project
Improves planning, quality, and cost control
🏷Please Subscribe Our Youtube Channel👇
https://youtube.com/@ethiopianconstruction7?si=ils307xXQQpIdCwG
@etconp
❤13👍7
👉Cantilever Beam Structure Analysis
🚧A cantilever beam is a structural member that is fixed at one end and free at the other.
🏷It resists loads through bending, shear, and deflection.
📜Here’s a short breakdown of the analysis shown:
Load (w): A uniform load acts along the beam length L.
Reactions at fixed end (A):
Vertical reaction:.VA=wL
Moment: MA=WL2/2
No horizontal reaction if no horizontal load.
Shear Force Diagram (SFD):
Starts maximum at the fixed end and decreases linearly to zero at the free end.
Bending Moment Diagram (BMD):
Maximum at the fixed end and reduces to zero at the free end (parabolic shape).
Deflection:
Maximum deflection occurs at the free end.
Smax=wL4/8EI
❇️Key idea: The fixed support carries all the load effects (shear + moment), making it the most critical point in design.
@etconp
🚧A cantilever beam is a structural member that is fixed at one end and free at the other.
🏷It resists loads through bending, shear, and deflection.
📜Here’s a short breakdown of the analysis shown:
Load (w): A uniform load acts along the beam length L.
Reactions at fixed end (A):
Vertical reaction:.VA=wL
Moment: MA=WL2/2
No horizontal reaction if no horizontal load.
Shear Force Diagram (SFD):
Starts maximum at the fixed end and decreases linearly to zero at the free end.
Bending Moment Diagram (BMD):
Maximum at the fixed end and reduces to zero at the free end (parabolic shape).
Deflection:
Maximum deflection occurs at the free end.
Smax=wL4/8EI
❇️Key idea: The fixed support carries all the load effects (shear + moment), making it the most critical point in design.
@etconp
❤6🙏6
👉 INTERCON Construction Chemicals
● Concrete Admixtures
● Bonding Agents
● Waterproofings
● Wall Putty, Prime Coat
● Concrete Repair Mortar
● Floor hardener, Epoxy
● Grout, Self-level mortar
● Quartz paint, Contextra
● Tile Adhesive & Tile Joint Fillers
● Geotextiles and other construction chemicals and materials
☎️ Tel: 0961955555
🔹 Address 1: Signal road, around
Dinberwa Hospital
🔹 Addres 2: Wellosefer, Infront of
Dani Plaza
● Concrete Admixtures
● Bonding Agents
● Waterproofings
● Wall Putty, Prime Coat
● Concrete Repair Mortar
● Floor hardener, Epoxy
● Grout, Self-level mortar
● Quartz paint, Contextra
● Tile Adhesive & Tile Joint Fillers
● Geotextiles and other construction chemicals and materials
☎️ Tel: 0961955555
🔹 Address 1: Signal road, around
Dinberwa Hospital
🔹 Addres 2: Wellosefer, Infront of
Dani Plaza
❤6👍2
👉በ3ዲ ቴክኖሎጂ የታተሙት የኮሎምቢያ የማኀበራዊ መኖሪያ ቤቶች ለዘርፉ አዲስ ተስፋ ሰንቀዋል
በደቡብ አሜሪካ ታሪክ ለመጀመሪያ ጊዜ በ3ዲ (3D) የህትመት ቴክኖሎጂ የተገነቡ የማህበራዊ መኖሪያ ቤቶች ግንባታ በኮሎምቢያ በስኬት ተጠናቀቀ፤
ግንባታው የተከናወነው "ፈንዳሲዮን በርታ ማርቲኔዝ" ለተባለ ግብረ-ሰናይ ድርጅት ሲሆን፣ የኮሎምቢያው የሲሚንቶ ግዙፍ ኩባንያ ሴሜንቶስ አርጎስ (Cementos Argos) ከዴንማርኩ የ3ዲ ፕሪንተር አምራች ኮቦድ (Cobod) ጋር በመተባበር ፕሮጀክቱን አሳክተዋል። ለግንባታውም ቦድ-2 (Bod2) የተባለውን ዘመናዊ የህትመት ማሽን ጥቅም ላይ አውለዋል፤
እነዚህ ባለ አንድ ፎቅ ቤቶች እያንዳንዳቸው 63 ካሬ ሜትር ስፋት ያላቸው ሲሆን፣ ሁለት መኝታ ቤቶች፣ ሳሎን፣ ኩሽና፣ መታጠቢያ ቤት፣ የልብስ ማጠቢያ ቦታና በረንዳ ያካተቱ ናቸው። ቤቶቹ 2.2 ሜትር ከፍታ ያላቸው የታተሙ ግድግዳዎችና ከእንጨት የተሠራ ጣሪያ ያላቸው በመሆኑ ዘመናዊነትንና ምቾትን አጣምረው የያዙ ናቸው፤
የቴክኖሎጂው ዋነኛ መገለጫ የሆነው ፍጥነት በዚህ ፕሮጀክት ላይ በተግባር የታየ ሲሆን፣ ሁለቱም ቤቶች በድምሩ በ16 የህትመት ሰዓታት ውስጥ በሶስት ቀናት ብቻ ተጠናቀዋል። ይህም ከተለመደው የግንባታ ዘዴ ጋር ሲነፃፀር በ30 በመቶ የፈጠነ መሆኑንና ግንባታን በአጭር ጊዜ ለማጠናቀቅ ያለውን አቅም አሳይቷል፤
ለህትመቱ የዋለው የሲሚንቶ ውህድ 99 በመቶ በአካባቢው ከሚገኙ ጥሬ ዕቃዎች የተዘጋጀ መሆኑ ሌላው የፕሮጀክቱ ስኬት ነው። የቤቶቹ ግድግዳዎች ከ35 ሜጋ ፓስካል (MPa) በላይ የመጫን ጥንካሬ ያላቸው በመሆኑ፣ የአካባቢውን የመሬት መንቀጥቀጥ መቋቋም የሚችሉና የጥራት ደረጃቸውን የጠበቁ ናቸው፤
@etconp
በደቡብ አሜሪካ ታሪክ ለመጀመሪያ ጊዜ በ3ዲ (3D) የህትመት ቴክኖሎጂ የተገነቡ የማህበራዊ መኖሪያ ቤቶች ግንባታ በኮሎምቢያ በስኬት ተጠናቀቀ፤
ይህ ታሪካዊ ክንውን በሀገሪቱ ምዕራባዊ ክፍል በአንቲዮኪያ ግዛት ስር በምትገኘው ላ ዩኒየን ከተማ የተከናወነ ሲሆን፣ ዘመናዊው ቴክኖሎጂ ለቤት እጥረት አዲስና ፈጣን መፍትሄ እንደሚሆን ታምኖበታል፤
ግንባታው የተከናወነው "ፈንዳሲዮን በርታ ማርቲኔዝ" ለተባለ ግብረ-ሰናይ ድርጅት ሲሆን፣ የኮሎምቢያው የሲሚንቶ ግዙፍ ኩባንያ ሴሜንቶስ አርጎስ (Cementos Argos) ከዴንማርኩ የ3ዲ ፕሪንተር አምራች ኮቦድ (Cobod) ጋር በመተባበር ፕሮጀክቱን አሳክተዋል። ለግንባታውም ቦድ-2 (Bod2) የተባለውን ዘመናዊ የህትመት ማሽን ጥቅም ላይ አውለዋል፤
እነዚህ ባለ አንድ ፎቅ ቤቶች እያንዳንዳቸው 63 ካሬ ሜትር ስፋት ያላቸው ሲሆን፣ ሁለት መኝታ ቤቶች፣ ሳሎን፣ ኩሽና፣ መታጠቢያ ቤት፣ የልብስ ማጠቢያ ቦታና በረንዳ ያካተቱ ናቸው። ቤቶቹ 2.2 ሜትር ከፍታ ያላቸው የታተሙ ግድግዳዎችና ከእንጨት የተሠራ ጣሪያ ያላቸው በመሆኑ ዘመናዊነትንና ምቾትን አጣምረው የያዙ ናቸው፤
የቴክኖሎጂው ዋነኛ መገለጫ የሆነው ፍጥነት በዚህ ፕሮጀክት ላይ በተግባር የታየ ሲሆን፣ ሁለቱም ቤቶች በድምሩ በ16 የህትመት ሰዓታት ውስጥ በሶስት ቀናት ብቻ ተጠናቀዋል። ይህም ከተለመደው የግንባታ ዘዴ ጋር ሲነፃፀር በ30 በመቶ የፈጠነ መሆኑንና ግንባታን በአጭር ጊዜ ለማጠናቀቅ ያለውን አቅም አሳይቷል፤
ከጊዜ ቁጠባው በተጨማሪ ቴክኖሎጂው በኢኮኖሚ ረገድ ከፍተኛ ፋይዳ እንዳለው በተደረገው ምልከታ ተረጋግጧል። በግንባታው ወቅት የሚባክኑ ግብዓቶችን ከ15 እስከ 30 በመቶ መቀነስ የተቻለ ሲሆን፣ የቁሳቁስ ወጪንም በ20 በመቶ ያህል ዝቅ እንዲል በማድረግ የማህበራዊ ቤቶችን ተመጣጣኝ ዋጋ እንዲኖራቸው አድርጓል፤
ለህትመቱ የዋለው የሲሚንቶ ውህድ 99 በመቶ በአካባቢው ከሚገኙ ጥሬ ዕቃዎች የተዘጋጀ መሆኑ ሌላው የፕሮጀክቱ ስኬት ነው። የቤቶቹ ግድግዳዎች ከ35 ሜጋ ፓስካል (MPa) በላይ የመጫን ጥንካሬ ያላቸው በመሆኑ፣ የአካባቢውን የመሬት መንቀጥቀጥ መቋቋም የሚችሉና የጥራት ደረጃቸውን የጠበቁ ናቸው፤
በውህዱ ውስጥ የተካተቱት ልዩ ቃጫዎችና ኬሚካላዊ ቅመሞች ግድግዳዎቹ በአየር ንብረት መለዋወጥ ምክንያት እንዳይሰነጣጠቁ የመከላከል ብቃት አላቸው፤
በተጨማሪም ግድግዳዎቹ በመካከላቸው የአየር ክፍተት እንዲኖራቸው ተደርገው የታተሙ በመሆኑ፣ በቤት ውስጥ ያለውን ሙቀትና ቅዝቃዜ የመቆጣጠር (Thermal insulation) ብቃት እንዲኖራቸው አድርጓቸዋል፤
የ3ዲ ፕሪንተር ማሽኑ በአምስት ትናንሽ የጭነት መኪናዎች ተጭኖ አስቸጋሪ በሆነ ተራራማ መልክዓ ምድርና ዝናባማ የአየር ሁኔታ ውስጥ ተጓጉዞ ግንባታው ወዳለበት ቦታ ደርሷል። ይህም ቴክኖሎጂው መሠረተ ልማት ባልተሟላላቸውና ርቀው ለሚገኙ አካባቢዎች ግንባታን ለማካሄድ ያለውን አመቺነት በተግባር ያረጋገጠ ክስተት ሆኗል፤
ማሽኑን ለማንቀሳቀስ ከ3 እስከ 4 የሚደርሱ ሰዎች ብቻ የሚያስፈልጉ በመሆኑ፣ በዘርፉ ያለውን የሰው ኃይል እጥረት ለመቅረፍ ትልቅ እገዛ ያደርጋል። አነስተኛ መነሻ ካፒታል ያላቸው ድርጅቶችም ይህን ቴክኖሎጂ በመጠቀም ጥራት ያላቸው ቤቶችን በተመጣጣኝ ዋጋና በተወሰነ የጊዜ ገደብ ውስጥ እንዲገነቡ ዕድል እንደሚሰጥ ባለሙያዎች ገልጸዋል፤
ሴሜንቶስ አርጎስ በቀጣይ 20 የማህበራዊ መኖሪያ ቤቶችን በአንድ ላይ የመገንባት ዕቅድ የያዘ ሲሆን፣ ግድግዳዎችን ከግንባታ ቦታ ውጪ አትሞ በማምጣት የመገጣጠም ዘዴን ለመተግበር እየሰራ መሆኑን አስታውቋል፤
ይህ እንቅስቃሴ የቴክኖሎጂውን ተደራሽነት ይበልጥ እንደሚያሰፋውና በኮሎምቢያ የገጠር አካባቢዎች ያለውን የቤት ፍላጎት እንደሚቀንስ ይጠበቃል።
@etconp
❤8👍3
👉Construction Materials – Unit Weight
🚧Material Unit Weight (kN/m³) Unit Weight (kg/m³)
Concrete (Plain) 24 ---- 2400
Concrete (Reinforced) 25 ---- 2500
Cement 14.4 ---- 1440
Sand (Dry) 16 ----- 1600
Sand (Wet) 19.2 ---- 1920
Steel 78.5 ---- 7850
Brick (Common) 18.8 --- 1880
Stone (Granite/Basalt) 26.5 ---- 2650
Timber (Softwood) 5 ---- 500
Timber (Hardwood) 8 -- 800
Water 9.81 -- 1000
Bitumen 10.1 -- 1010
Aluminium 27 -- 2700
🚧Notes:
⏺1 kN/m³ ≈ 101.97 kg/m³ (rounded to ~100 for simplicity in many engineering handbooks).
🏷Values can vary slightly depending on moisture content, density, and source.
#ConstructionMaterials #UnitWeight
#CivilEngineering #BuildingMaterials #StructuralEngineering #ConstructionBasics #MaterialDensity #EngineeringKnowledge #ConstructionData #ConcreteDensity
#SteelDensity
#SandDensity #BuildingConstruction #EngineeringReference
@etconp
🚧Material Unit Weight (kN/m³) Unit Weight (kg/m³)
Concrete (Plain) 24 ---- 2400
Concrete (Reinforced) 25 ---- 2500
Cement 14.4 ---- 1440
Sand (Dry) 16 ----- 1600
Sand (Wet) 19.2 ---- 1920
Steel 78.5 ---- 7850
Brick (Common) 18.8 --- 1880
Stone (Granite/Basalt) 26.5 ---- 2650
Timber (Softwood) 5 ---- 500
Timber (Hardwood) 8 -- 800
Water 9.81 -- 1000
Bitumen 10.1 -- 1010
Aluminium 27 -- 2700
🚧Notes:
⏺1 kN/m³ ≈ 101.97 kg/m³ (rounded to ~100 for simplicity in many engineering handbooks).
🏷Values can vary slightly depending on moisture content, density, and source.
#ConstructionMaterials #UnitWeight
#CivilEngineering #BuildingMaterials #StructuralEngineering #ConstructionBasics #MaterialDensity #EngineeringKnowledge #ConstructionData #ConcreteDensity
#SteelDensity
#SandDensity #BuildingConstruction #EngineeringReference
@etconp
❤8👍7
👉Bar Schedule ማለት ምን ማለት ነው እንዴትስ ይዘጋጃል?
✅ Bar Schedule (BBS) ማለት በኮንክሪት ሥራ ውስጥ የሚጠቀሙ የብረት እስር (Reinforcement bars)
እንዴት እንደሚቈረጡ፣ እንዴት እንደሚጠመዱ (bend) እና የት እንደሚተከሉ የሚያሳይ ዝርዝር ሰነድ ነው።
በአጭር አነጋገር፡
• የዲዛይን ስዕል → “ምን ይፈልጋል” ይነግራል
• Bar Schedule → “እንዴት እንደሚሰራ” ይገልጻል
✅ በBar Schedule ውስጥ የሚካተቱ ነገሮች
የተዘጋጀ የBBS ሰነድ የሚካተቱት፦
• Bar Mark (መለያ ቁጥር)
እያንዳንዱ የብረት አይነት የሚለይበት ኮድ
• የብረት ውፍረት (Diameter)
ለምሳሌ 8mm, 12mm, 16mm
• Shape Code (የቅርጽ ኮድ)
ብረቱ የሚጠመድበት መደበኛ ቅርጽ
• የክፍል ርዝመቶች
(A, B, C…) በቅርጹ መሠረት
• ጠቅላላ የመቁረጥ ርዝመት (Cutting Length)
በመጠመድ የሚጨመር ርዝመትን ጨምሮ
• ብዛት (Number of Bars)
• ጠቅላላ ርዝመት / ክብደት
• የሚጠቀምበት ክፍል
(Beam, Slab, Column, Footing ወዘተ)
✅ አስፈላጊነቱ (በተግባር)
3.1 የእቃ ቁጥጥር
• ብረት እንዳይበዛ ወይም እንዳይጎድል ይከላከላል
• ትክክለኛ መጠን (BOQ) ለማስላት ይረዳል
3.2 ትክክለኛ ማቀናበር (Fabrication)
• በየሥራ ቦታው ብረት ትክክል እንዲቆረጥ ያደርጋል
• እንደገና መስራት (rework) ያነሳል
3.3 የሥራ አፈጻጸም
• ለቴክኒሺዎችና ሰራተኞች ግልጽ መመሪያ ይሆናል
• ስህተት ይቀንሳል
3.4 ጊዜና ወጪ
• የእቃ ንክኪ ይቀንሳል
• ሥራ ፈጣን ይሆናል
✅ የCutting Length መቁጠር
ብዙ ሰዎች የሚሳሳቱበት ነገር ይህ ነው።
Cutting length = ቀጥታ ርዝመት ብቻ አይደለም
የሚጨመሩት፦
• የመጀመሪያ ርዝመት
• የመጠመድ (bend allowance)
• የhook ርዝመት
• የlap ርዝመት (ካለ)
ለምሳሌ፦
• 90° መጠመድ ተጨማሪ ርዝመት ያስፈልጋል
• Hook በd መጠን (9d, 12d…) ይጨመራል
ትክክል ካልሆነ → ብረት አጭር ይሆናል → ከባድ ችግር
✅ Shape Code (የቅርጽ መደበኛነት)
ሁሉንም በስዕል ማብራር አይደለም፤ ኮድ ይጠቀማሉ።
ለምሳሌ፦
• ቀጥታ ብረት
• L-ቅርጽ
• U-ቅርጽ (stirrups)
• Cranked bars
ይህ ያደርገው፦
• ግንኙነት ይፈጥናል
• ስህተት ይቀንሳል
✅ የሚጠቀሙበት ቦታ
Bar Schedule በሁሉም RC ክፍሎች ይጠቀማል፦
• Beam (ጭነት ተሸካሚ መስመር)
• Slab (ሰሌዳ)
• Column (አምድ)
• Footing (መሠረት)
• Retaining wall ወዘተ
✅ ከTakeoff Sheet ጋር ግንኙነት
• Takeoff Sheet → “ስንት ብረት ያስፈልጋል?”
• Bar Schedule → “እንዴት እንቆርጠው እና እንደንጠመው?”
✅ የሚደረጉ የተለመዱ ስህተቶች
• የbend allowance መርሳት
• የlap length ስህተት
• ከdrawing ጋር አልተመሳሰለም
• አስቸጋሪ አድርጎ መዘጋጀት
• ክብደት ከBOQ ጋር አልተረጋገጠም
✅ በSoftware መዘጋጀት
Bar Schedule በኮምፒውተር ሊሰራ ይችላል፦
• AutoCAD
• Revit
• Tekla Structures
@etconp
✅ Bar Schedule (BBS) ማለት በኮንክሪት ሥራ ውስጥ የሚጠቀሙ የብረት እስር (Reinforcement bars)
እንዴት እንደሚቈረጡ፣ እንዴት እንደሚጠመዱ (bend) እና የት እንደሚተከሉ የሚያሳይ ዝርዝር ሰነድ ነው።
በአጭር አነጋገር፡
• የዲዛይን ስዕል → “ምን ይፈልጋል” ይነግራል
• Bar Schedule → “እንዴት እንደሚሰራ” ይገልጻል
✅ በBar Schedule ውስጥ የሚካተቱ ነገሮች
የተዘጋጀ የBBS ሰነድ የሚካተቱት፦
• Bar Mark (መለያ ቁጥር)
እያንዳንዱ የብረት አይነት የሚለይበት ኮድ
• የብረት ውፍረት (Diameter)
ለምሳሌ 8mm, 12mm, 16mm
• Shape Code (የቅርጽ ኮድ)
ብረቱ የሚጠመድበት መደበኛ ቅርጽ
• የክፍል ርዝመቶች
(A, B, C…) በቅርጹ መሠረት
• ጠቅላላ የመቁረጥ ርዝመት (Cutting Length)
በመጠመድ የሚጨመር ርዝመትን ጨምሮ
• ብዛት (Number of Bars)
• ጠቅላላ ርዝመት / ክብደት
• የሚጠቀምበት ክፍል
(Beam, Slab, Column, Footing ወዘተ)
✅ አስፈላጊነቱ (በተግባር)
3.1 የእቃ ቁጥጥር
• ብረት እንዳይበዛ ወይም እንዳይጎድል ይከላከላል
• ትክክለኛ መጠን (BOQ) ለማስላት ይረዳል
3.2 ትክክለኛ ማቀናበር (Fabrication)
• በየሥራ ቦታው ብረት ትክክል እንዲቆረጥ ያደርጋል
• እንደገና መስራት (rework) ያነሳል
3.3 የሥራ አፈጻጸም
• ለቴክኒሺዎችና ሰራተኞች ግልጽ መመሪያ ይሆናል
• ስህተት ይቀንሳል
3.4 ጊዜና ወጪ
• የእቃ ንክኪ ይቀንሳል
• ሥራ ፈጣን ይሆናል
✅ የCutting Length መቁጠር
ብዙ ሰዎች የሚሳሳቱበት ነገር ይህ ነው።
Cutting length = ቀጥታ ርዝመት ብቻ አይደለም
የሚጨመሩት፦
• የመጀመሪያ ርዝመት
• የመጠመድ (bend allowance)
• የhook ርዝመት
• የlap ርዝመት (ካለ)
ለምሳሌ፦
• 90° መጠመድ ተጨማሪ ርዝመት ያስፈልጋል
• Hook በd መጠን (9d, 12d…) ይጨመራል
ትክክል ካልሆነ → ብረት አጭር ይሆናል → ከባድ ችግር
✅ Shape Code (የቅርጽ መደበኛነት)
ሁሉንም በስዕል ማብራር አይደለም፤ ኮድ ይጠቀማሉ።
ለምሳሌ፦
• ቀጥታ ብረት
• L-ቅርጽ
• U-ቅርጽ (stirrups)
• Cranked bars
ይህ ያደርገው፦
• ግንኙነት ይፈጥናል
• ስህተት ይቀንሳል
✅ የሚጠቀሙበት ቦታ
Bar Schedule በሁሉም RC ክፍሎች ይጠቀማል፦
• Beam (ጭነት ተሸካሚ መስመር)
• Slab (ሰሌዳ)
• Column (አምድ)
• Footing (መሠረት)
• Retaining wall ወዘተ
✅ ከTakeoff Sheet ጋር ግንኙነት
• Takeoff Sheet → “ስንት ብረት ያስፈልጋል?”
• Bar Schedule → “እንዴት እንቆርጠው እና እንደንጠመው?”
✅ የሚደረጉ የተለመዱ ስህተቶች
• የbend allowance መርሳት
• የlap length ስህተት
• ከdrawing ጋር አልተመሳሰለም
• አስቸጋሪ አድርጎ መዘጋጀት
• ክብደት ከBOQ ጋር አልተረጋገጠም
✅ በSoftware መዘጋጀት
Bar Schedule በኮምፒውተር ሊሰራ ይችላል፦
• AutoCAD
• Revit
• Tekla Structures
@etconp
❤18👍11
🔨 10 Common Foundation Mistakes – Explained
1. Poor Soil Investigation
Skipping soil testing means the wrong foundation type may be chosen, leading to instability and costly repairs later.
2. Incorrect Foundation Depth
Shallow foundations in weak or expansive soils can cause cracks, uneven settlement, and structural failure.
3. Improper Compaction
Loose soil beneath footings reduces load‑bearing capacity, making the foundation prone to sinking.
4. Wrong Concrete Mix
Using low‑grade or poorly mixed concrete weakens the foundation, reducing durability and strength.
5. Poor Reinforcement Placement
Incorrect spacing, cover, or alignment of steel bars compromises structural integrity.
6. Inadequate Curing
Skipping curing causes shrinkage cracks and weak concrete, shortening the building’s lifespan.
7. Ignoring Drainage
Water accumulation around foundations softens soil, leading to settlement and erosion.
8. No Anti‑Termite Treatment
Termites can damage wooden components, indirectly weakening the structure.
9. Overloading Foundation
Not accounting for future loads like extra floors or heavy equipment risks overstressing the foundation.
10. Poor Supervision
Lack of site monitoring allows small errors to pile up, resulting in major structural issues.
⚡️Remember: Strong buildings start with strong foundations!
#CivilEngineering #ConstructionTips #ConcreteAndSteel #BuildingStrong
#Plumbing
@etconp
1. Poor Soil Investigation
Skipping soil testing means the wrong foundation type may be chosen, leading to instability and costly repairs later.
2. Incorrect Foundation Depth
Shallow foundations in weak or expansive soils can cause cracks, uneven settlement, and structural failure.
3. Improper Compaction
Loose soil beneath footings reduces load‑bearing capacity, making the foundation prone to sinking.
4. Wrong Concrete Mix
Using low‑grade or poorly mixed concrete weakens the foundation, reducing durability and strength.
5. Poor Reinforcement Placement
Incorrect spacing, cover, or alignment of steel bars compromises structural integrity.
6. Inadequate Curing
Skipping curing causes shrinkage cracks and weak concrete, shortening the building’s lifespan.
7. Ignoring Drainage
Water accumulation around foundations softens soil, leading to settlement and erosion.
8. No Anti‑Termite Treatment
Termites can damage wooden components, indirectly weakening the structure.
9. Overloading Foundation
Not accounting for future loads like extra floors or heavy equipment risks overstressing the foundation.
10. Poor Supervision
Lack of site monitoring allows small errors to pile up, resulting in major structural issues.
⚡️Remember: Strong buildings start with strong foundations!
#CivilEngineering #ConstructionTips #ConcreteAndSteel #BuildingStrong
#Plumbing
@etconp
❤15👍8
👉Simple Supported Beam Structure Analysis
💫A simply supported beam is a structural element supported at both ends, usually with a pin at one end and a roller at the other. It carries loads (like uniformly distributed load, w) along its span L.
1. Support Reactions
Because of symmetry (for uniform load):
Ra=Rb=WL/2
2. Shear Force Diagram (SFD)
Shear force decreases linearly from left to right:
V(x)=WL/2 - Wx
3. Bending Moment Diagram (BMD)
Bending moment is maximum at the center of the beam:
Mmax=WL2/8
Summary:
⏺Equal reactions at supports
Linear shear force variation
Parabolic bending moment with maximum at center
#SimpleSupportedBeam
#BeamDesign
#StructuralEngineering
#CivilEngineering
#EngineeringBasics
#ShearForce
#BendingMoment
#StructuralAnalysis
#BuildingDesign
#ConstructionEngineering
@etconp
💫A simply supported beam is a structural element supported at both ends, usually with a pin at one end and a roller at the other. It carries loads (like uniformly distributed load, w) along its span L.
1. Support Reactions
Because of symmetry (for uniform load):
Ra=Rb=WL/2
2. Shear Force Diagram (SFD)
Shear force decreases linearly from left to right:
V(x)=WL/2 - Wx
3. Bending Moment Diagram (BMD)
Bending moment is maximum at the center of the beam:
Mmax=WL2/8
Summary:
⏺Equal reactions at supports
Linear shear force variation
Parabolic bending moment with maximum at center
#SimpleSupportedBeam
#BeamDesign
#StructuralEngineering
#CivilEngineering
#EngineeringBasics
#ShearForce
#BendingMoment
#StructuralAnalysis
#BuildingDesign
#ConstructionEngineering
@etconp
❤5👍3
👉Quantity of Water in a Rectangular Tank
💫1. Tank Volume
🚧Use the basic formula:
V = L×B×H
For the given tank:
12 ft × 8 ft × 6 ft = 576 cubic feet (cuft)
💫2. Convert Volume to Water (Liters)
1 cubic meter = 1000 liters
1 cubic meter = 35.31 cuft
So, 1 cuft ≈ 28.31 liters
💫3. Total Water in Tank
576 × 28.31 = 16,307 liters (≈ 16.3 m³)
💫4. Convert to Gallons
US gallon: ≈ 4,308 gallons
UK gallon: ≈ 3,592 gallons
💫5. Simple Shortcut (if dimensions in meters)
Volume × 1000 = liters
❇️Summary: The tank holds about 16,300 liters of water, depending on full capacity.
#WaterTank
#CivilEngineering #QuantityTakeoff #ConstructionBasics #SiteEngineering #WaterCalculation
#TankDesign #EngineeringStudents #VolumeCalculation #ConcreteTank
#Hydraulics #WaterEngineering #BuildingConstruction
#CivilNotes
@etconp
💫1. Tank Volume
🚧Use the basic formula:
V = L×B×H
For the given tank:
12 ft × 8 ft × 6 ft = 576 cubic feet (cuft)
💫2. Convert Volume to Water (Liters)
1 cubic meter = 1000 liters
1 cubic meter = 35.31 cuft
So, 1 cuft ≈ 28.31 liters
💫3. Total Water in Tank
576 × 28.31 = 16,307 liters (≈ 16.3 m³)
💫4. Convert to Gallons
US gallon: ≈ 4,308 gallons
UK gallon: ≈ 3,592 gallons
💫5. Simple Shortcut (if dimensions in meters)
Volume × 1000 = liters
❇️Summary: The tank holds about 16,300 liters of water, depending on full capacity.
#WaterTank
#CivilEngineering #QuantityTakeoff #ConstructionBasics #SiteEngineering #WaterCalculation
#TankDesign #EngineeringStudents #VolumeCalculation #ConcreteTank
#Hydraulics #WaterEngineering #BuildingConstruction
#CivilNotes
@etconp
❤10🎉1
1. What is a hanging beam?
Answer:A hanging beam is a beam supported by tension members (cables/rods) from above instead of resting on supports below.
2. How is a hanging beam different from a simply supported beam?
Answer: Hanging beam: supported from top (tension) Simply supported beam: supported from bottom (compression reaction)
3. What type of forces act in the supporting members?
Answer:Only tensile forces act in the cables or rods.
4. What is the equilibrium condition of a hanging beam under UDL?
Answer:Total upward tension = total downward loPic
5. What are the support reactions for a uniformly distributed load (UDL)?
Answer:For symmetric loading:
6. What is the shape of the shear force diagram (SFD)?
Answer:It is a straight line (linear variation) from positive to negative.
7. What is the shape of the bending moment diagram (BMD)?
Answer: It is a parabolic curve with maximum at midspan.
8. Where does maximum bending moment occur?
Answer: At the mid-span of the beam.
@etconp
Answer:A hanging beam is a beam supported by tension members (cables/rods) from above instead of resting on supports below.
2. How is a hanging beam different from a simply supported beam?
Answer: Hanging beam: supported from top (tension) Simply supported beam: supported from bottom (compression reaction)
3. What type of forces act in the supporting members?
Answer:Only tensile forces act in the cables or rods.
4. What is the equilibrium condition of a hanging beam under UDL?
Answer:Total upward tension = total downward loPic
5. What are the support reactions for a uniformly distributed load (UDL)?
Answer:For symmetric loading:
6. What is the shape of the shear force diagram (SFD)?
Answer:It is a straight line (linear variation) from positive to negative.
7. What is the shape of the bending moment diagram (BMD)?
Answer: It is a parabolic curve with maximum at midspan.
8. Where does maximum bending moment occur?
Answer: At the mid-span of the beam.
@etconp
❤11👍4
Common Construction Materials
🧱 Bricks
- Made from clay
- Strong and durable
- Used for walls and partitions
🏗️ Cement
- Binding material
- Mixed with sand & water
- Used in mortar and concrete
🏢 Concrete
- Mix of cement, sand, gravel & water
- Very strong
- Used in foundations, beams, slabs, roads
🔩 Steel
- High strength
- Used for reinforcement and structural frames
- Common in buildings and bridges
🪨 Stone
- Natural rock material
- Very strong and long-lasting
- Used for foundations, walls and decoration
🪟 Glass
- Transparent material
- Used in windows, doors and facades
- Allows natural light inside
⚙️ Plastic (PVC)
- Lightweight and waterproof
- Used for pipes, fittings and insulation
🏖️ Sand
- Fine aggregate
- Used in concrete, mortar and plastering
- Fills the gaps and improves workability
🪨 Aggregates (Gravel)
- Coarse aggregate
- Mixed with cement and sand to make concrete
- Gives strength and stability
@etconp
🧱 Bricks
- Made from clay
- Strong and durable
- Used for walls and partitions
🏗️ Cement
- Binding material
- Mixed with sand & water
- Used in mortar and concrete
🏢 Concrete
- Mix of cement, sand, gravel & water
- Very strong
- Used in foundations, beams, slabs, roads
🔩 Steel
- High strength
- Used for reinforcement and structural frames
- Common in buildings and bridges
🪨 Stone
- Natural rock material
- Very strong and long-lasting
- Used for foundations, walls and decoration
🪟 Glass
- Transparent material
- Used in windows, doors and facades
- Allows natural light inside
⚙️ Plastic (PVC)
- Lightweight and waterproof
- Used for pipes, fittings and insulation
🏖️ Sand
- Fine aggregate
- Used in concrete, mortar and plastering
- Fills the gaps and improves workability
🪨 Aggregates (Gravel)
- Coarse aggregate
- Mixed with cement and sand to make concrete
- Gives strength and stability
@etconp
❤13
📐 Circular Water Tank Design (20,000 Liters)
Objective: Design a circular water tank to store 20 m³ (20,000 liters) with a maximum depth of 2 meters.
Step 1 – Capacity Conversion:
- 20,000 liters = 20 m³
Step 2 – Trial Depths:
- Depth = 0.5 m → Diameter ≈ 7.0 m
- Depth = 1.0 m → Diameter ≈ 5.0 m
- Depth = 1.5 m → Diameter ≈ 4.1 m
- Depth = 2.0 m → Diameter ≈ 3.56 m
Step 3 – Final Design:
- Depth = 1.5 m
- Diameter = 4.10 m
- Capacity ≈ 20 m³
✅ Practical Choice:
A depth of 1.5 m with a diameter of 4.10 m balances construction feasibility and storage efficiency.
🔑 Key Takeaway
For a 20,000-liter circular tank, the most practical design is:
Depth = 1.5 m, Diameter = 4.10 m
#WaterTankDesign #ConcreteAndSteel #CivilTechTime #ConstructionDetails #StructuralEngineering #PlumbingDesign
@etconp
Objective: Design a circular water tank to store 20 m³ (20,000 liters) with a maximum depth of 2 meters.
Step 1 – Capacity Conversion:
- 20,000 liters = 20 m³
Step 2 – Trial Depths:
- Depth = 0.5 m → Diameter ≈ 7.0 m
- Depth = 1.0 m → Diameter ≈ 5.0 m
- Depth = 1.5 m → Diameter ≈ 4.1 m
- Depth = 2.0 m → Diameter ≈ 3.56 m
Step 3 – Final Design:
- Depth = 1.5 m
- Diameter = 4.10 m
- Capacity ≈ 20 m³
✅ Practical Choice:
A depth of 1.5 m with a diameter of 4.10 m balances construction feasibility and storage efficiency.
🔑 Key Takeaway
For a 20,000-liter circular tank, the most practical design is:
Depth = 1.5 m, Diameter = 4.10 m
#WaterTankDesign #ConcreteAndSteel #CivilTechTime #ConstructionDetails #StructuralEngineering #PlumbingDesign
@etconp
❤8👍2
👉Bridge Column (Pier) Design
🚧Bridge columns, or piers, are vital vertical supports transferring loads from the superstructure to the foundation.
⏺Their design ensures stability, strength, and durability under combined axial, bending, and shear forces.
🏷Key Design Steps:
1. Load Calculation: Combine dead, live, and environmental loads (wind, earthquake, water).
2. Axial Capacity: Compute concrete and steel contribution using AASHTO LRFD formulas.
3. Slenderness Check: Evaluate buckling through slenderness ratio and apply moment magnification if needed.
4. Shear Strength: Sum concrete and steel resistance for total shear capacity.
5. Interaction Diagram: Verify that the design point lies within the safe zone of the P–M curve.
6. Thumb Rules:
- Column diameter ≈ 1/10–1/15 of height
- Reinforcement ratio: 1–4%
- Use proper ties/spirals for confinement
❇️Design Tip: Always ensure adequate cover, detailing, and load transfer to the foundation for long-term performance.
@etconp
🚧Bridge columns, or piers, are vital vertical supports transferring loads from the superstructure to the foundation.
⏺Their design ensures stability, strength, and durability under combined axial, bending, and shear forces.
🏷Key Design Steps:
1. Load Calculation: Combine dead, live, and environmental loads (wind, earthquake, water).
2. Axial Capacity: Compute concrete and steel contribution using AASHTO LRFD formulas.
3. Slenderness Check: Evaluate buckling through slenderness ratio and apply moment magnification if needed.
4. Shear Strength: Sum concrete and steel resistance for total shear capacity.
5. Interaction Diagram: Verify that the design point lies within the safe zone of the P–M curve.
6. Thumb Rules:
- Column diameter ≈ 1/10–1/15 of height
- Reinforcement ratio: 1–4%
- Use proper ties/spirals for confinement
❇️Design Tip: Always ensure adequate cover, detailing, and load transfer to the foundation for long-term performance.
@etconp
❤5👏3
👉How to Calculate Staircase Concrete Volume
💫This infographic explains the step-by-step method for calculating the concrete quantity required for an RCC staircase.
🏷Calculate the number of steps using total height ÷ riser height.
❇️Find the horizontal length using steps × tread.
⏺Determine the waist slab length with the Pythagorean theorem.
⏺Compute the waist slab volume and single step volume separately.
⏺Add all step volumes to the waist slab volume to get the total concrete volume.
✅ Total concrete required for this staircase = 1.5 m³
#StaircaseDesign #ConcreteVolume #CivilEngineering #Construction #RCCStaircase #QuantitySurveying #BuildingConstruction #EngineeringCalculation #StructuralEngineering
@etconp
💫This infographic explains the step-by-step method for calculating the concrete quantity required for an RCC staircase.
🏷Calculate the number of steps using total height ÷ riser height.
❇️Find the horizontal length using steps × tread.
⏺Determine the waist slab length with the Pythagorean theorem.
⏺Compute the waist slab volume and single step volume separately.
⏺Add all step volumes to the waist slab volume to get the total concrete volume.
✅ Total concrete required for this staircase = 1.5 m³
#StaircaseDesign #ConcreteVolume #CivilEngineering #Construction #RCCStaircase #QuantitySurveying #BuildingConstruction #EngineeringCalculation #StructuralEngineering
@etconp
❤10👏1
👉ሰሜን ኮሪያንና ሩሲያን የሚያገናኘው ቁልፍ ድልድይ ግንባታ መጠናቀቁን የሳተላይት ምስሎች አሳዩ
🚧በሰሜን ኮሪያና በሩሲያ ድንበር ላይ የሚገኘውን ቱመን ወንዝን የሚያቋርጠው አዲሱ ስትራቴጂካዊ የጎዳና ድልድይ ግንባታ ተጠናቆ ለአገልግሎት ዝግጁ መሆኑን የሳተላይት ምስሎች ማሳየታቸው ተዘግቧል።
አዲሱ ድልድይ ከዚህ ቀደም ሁለቱን ሀገራት በየብስ ያገናኝ ከነበረውና "የጓደኝነት ድልድይ" ተብሎ ከሚጠራው ነባር የባቡር መስመር ጎን የተገነባ ነው።
የሩሲያ ትራንስፖርት ሚኒስቴር እንዳስታወቀው አዲሱ ድልድይ በቀን እስከ 300 ተሽከርካሪዎችንና 2 ሺህ 850 ሰዎችን የማስተናገድ አቅም አለው።
የሩሲያ የመንግሥት መገናኛ ብዙኃን እንደዘገቡት ከሆነ ድልድዩን ለመገንባት የወጣው ጠቅላላ ወጪ ከ9 ቢሊዮን ሩብል በላይ እንደሆነ ተገምቷል።
ይህ የግንባታ ወጪ በወቅታዊ የምንዛሬ ተመን ሲሰላ 120 ሚሊዮን የአሜሪካ ዶላር ወይም 88 ሚሊዮን የእንግሊዝ ፓውንድ ገደማ ይሆናል።
ምንጭ : ቢቢሲ
@etconp
🚧በሰሜን ኮሪያና በሩሲያ ድንበር ላይ የሚገኘውን ቱመን ወንዝን የሚያቋርጠው አዲሱ ስትራቴጂካዊ የጎዳና ድልድይ ግንባታ ተጠናቆ ለአገልግሎት ዝግጁ መሆኑን የሳተላይት ምስሎች ማሳየታቸው ተዘግቧል።
አዲሱ ድልድይ ከዚህ ቀደም ሁለቱን ሀገራት በየብስ ያገናኝ ከነበረውና "የጓደኝነት ድልድይ" ተብሎ ከሚጠራው ነባር የባቡር መስመር ጎን የተገነባ ነው።
የሩሲያ ትራንስፖርት ሚኒስቴር እንዳስታወቀው አዲሱ ድልድይ በቀን እስከ 300 ተሽከርካሪዎችንና 2 ሺህ 850 ሰዎችን የማስተናገድ አቅም አለው።
የሩሲያ የመንግሥት መገናኛ ብዙኃን እንደዘገቡት ከሆነ ድልድዩን ለመገንባት የወጣው ጠቅላላ ወጪ ከ9 ቢሊዮን ሩብል በላይ እንደሆነ ተገምቷል።
ይህ የግንባታ ወጪ በወቅታዊ የምንዛሬ ተመን ሲሰላ 120 ሚሊዮን የአሜሪካ ዶላር ወይም 88 ሚሊዮን የእንግሊዝ ፓውንድ ገደማ ይሆናል።
ምንጭ : ቢቢሲ
@etconp
❤5👍2