Surveying quiz
The first reading from a level station is ____?
The first reading from a level station is ____?
Anonymous Quiz
27%
Foresight
66%
Back sight
3%
Any sight
3%
Intermediate site
👉ስለ SFD Vs BMD ኣብረን እንይ
.
🚧Shear Force Diagram = የአንድን አካል ርዝመት 'X' ብንለው በፎርሶች የሚፈጠረውን ሺር ፎርስ ደግሞ ‘ Y ’ ብንለውና ግራፍ ላይ ስለን እያንዳንዱ የርዝመቱ ነጥብ ላይ ያሉትን ሺር ፎርሶች በመስመር ስናገንኛቸው (የተገናኙ ናቸው በዕርገጥ) የምናገኘው ቅርፅ ነው SFD
.
🚧Bending Moment Diagram = ከ SFD ጋር አንድ ሆኖ ነገር ግን ለ Moment ሲሆን Bending Moment Diagram (BMD) ይባላል
.
🚧Concentrated Load ሲኖር SFD ቀጥ ብሎ ወደጎን ይሄዳል ወይም በሌላ አገላለጽ Constant ይሆናል BMD ደግሞ linearly ወይም right angle triangle በሚመስል መልኩ ይሄዳል::
.
🚧Distributed Load ሲኖር SFD linear ይሆናል BMD ደግሞ Parabolic ይሆናል
ሁልጊዜ BMD ከ SFD በ አንድ ዲግሪ ይበልጣል ( SFD constant ሲሆን BMD = linear SFD linear ሲሆን ደግሞ BMD is parabolic )
.
🚧Maximum Bending Moment = SFD ከፖዘቲቭ ወደ
ኔጌቲቭ የሚቀየርበት ነጥብ ላይ ነው Moment Maximum
የሚሆነው
.
🚧Minimum Bending Moment = SFD ከኔጌቲቭ ወደ ፖዘቲቭ የሚቀየርበት ነጥብ ላይ ይገኛል፡፡
@etconp
.
🚧Shear Force Diagram = የአንድን አካል ርዝመት 'X' ብንለው በፎርሶች የሚፈጠረውን ሺር ፎርስ ደግሞ ‘ Y ’ ብንለውና ግራፍ ላይ ስለን እያንዳንዱ የርዝመቱ ነጥብ ላይ ያሉትን ሺር ፎርሶች በመስመር ስናገንኛቸው (የተገናኙ ናቸው በዕርገጥ) የምናገኘው ቅርፅ ነው SFD
.
🚧Bending Moment Diagram = ከ SFD ጋር አንድ ሆኖ ነገር ግን ለ Moment ሲሆን Bending Moment Diagram (BMD) ይባላል
.
🚧Concentrated Load ሲኖር SFD ቀጥ ብሎ ወደጎን ይሄዳል ወይም በሌላ አገላለጽ Constant ይሆናል BMD ደግሞ linearly ወይም right angle triangle በሚመስል መልኩ ይሄዳል::
.
🚧Distributed Load ሲኖር SFD linear ይሆናል BMD ደግሞ Parabolic ይሆናል
ሁልጊዜ BMD ከ SFD በ አንድ ዲግሪ ይበልጣል ( SFD constant ሲሆን BMD = linear SFD linear ሲሆን ደግሞ BMD is parabolic )
.
🚧Maximum Bending Moment = SFD ከፖዘቲቭ ወደ
ኔጌቲቭ የሚቀየርበት ነጥብ ላይ ነው Moment Maximum
የሚሆነው
.
🚧Minimum Bending Moment = SFD ከኔጌቲቭ ወደ ፖዘቲቭ የሚቀየርበት ነጥብ ላይ ይገኛል፡፡
@etconp
Ethio Construction Engineering
Surveying quiz
The first reading from a level station is ____?
The first reading from a level station is ____?
Answer for this question 👆🏾👆🏾 is back sight
Back sight (BS) – short for "back sight reading", the first staff reading taken by the surveyor after the levelling instrument is set up and levelled. B.S is generally taken on the point of known reduced level as on the benchmark or a change point.
Back sight ማለት የsurvying መሳሪያችን አደላድለን (level) አድርገን የወሰድነው የመጀመሪያ ልኬት ነው።
@etconp
Back sight (BS) – short for "back sight reading", the first staff reading taken by the surveyor after the levelling instrument is set up and levelled. B.S is generally taken on the point of known reduced level as on the benchmark or a change point.
Back sight ማለት የsurvying መሳሪያችን አደላድለን (level) አድርገን የወሰድነው የመጀመሪያ ልኬት ነው።
@etconp
Are you guys familiar with Reduced Beam Section (RBS) ?
If you participate we will make some presentation regarding this topic .
If you don’t participate we assume that you’re not interested in this topic so we will leave it.
ተሳትፎ ካደረጋችሁ ይህን ርዕስ በተመለከተ ትንሽ ዝግጅት እናዘጋጃለን በ አማርኛም በ ኢንጊልዘኛም።
ካልተሳተፍችሁ ግን በዚህ ርዕስ ፍላጎት እንደሌላችሁ በማሰብ እንተወዋለን
@etconp
If you participate we will make some presentation regarding this topic .
If you don’t participate we assume that you’re not interested in this topic so we will leave it.
ተሳትፎ ካደረጋችሁ ይህን ርዕስ በተመለከተ ትንሽ ዝግጅት እናዘጋጃለን በ አማርኛም በ ኢንጊልዘኛም።
ካልተሳተፍችሁ ግን በዚህ ርዕስ ፍላጎት እንደሌላችሁ በማሰብ እንተወዋለን
@etconp
Ethio Construction Engineering
Are you guys familiar with Reduced Beam Section (RBS) ? If you participate we will make some presentation regarding this topic . If you don’t participate we assume that you’re not interested in this topic so we will leave it. ተሳትፎ ካደረጋችሁ ይህን ርዕስ በተመለከተ…
Reduced beam section (RBS) in Amharic 🇪🇹🇪🇹🇪🇹
Moment’ን ከመቋቋሙ የ steel connection ነው። ይህም connection አይነት የተተዋወቀው እንደ አውሮጳውያን አቆጣጠር ከ1994 የ Northridge የመሬት መንቀጥቀጥ በኋላ ነው። በዚህ የመሬት መንቀጥቀጥ ማሀንዲሶች አንድ ነገር ታዘቡ ይህም brittle shear failure column’ሁ ላይ እና plastic deformation ተከሰተ ምን እንደምል steel structure design መሰረታዊ እውቀት ያላችሁ ትገነዘቡታላችሁ እናም ይህም በ theory ከሚያቁት የተለየ ነበር። ስለዚህ እንደመፍትሄ
1. Connection’ሁን ridged ማድረግ
2. የ beam’ሁን section መቀነስ
ይህም ከሆነ ተገማች ምላሽ/ውጤት ስለሚገኝ ይህም የተቆረጠ beam ለታሳበው የመሬት መንቀጥቀጥን እና የመሬት ስበት መቋቋም የሚችል section መሆን አለበት። ምስሉን በደምብ zoom አርጋችሁ ያያችሁን ከሆነ protected zone ሚባል ቦታ አለ ከ joint’ሁ እስከ reduced section’ሁ መጨረሻው ድረስ።
እንደሚታወቀው Steel construction ላይ column እና beam በ ብሎን፣ በመበየድ እናም በ revet ይገናኛሉ እናም ይህ dry connection ይባላል። እናም በ መሬት መንቀጥቀጥ ጊዜ failure ሚያስከትለው beam’ሁ ላይ ነው ማለትም ጉዳት ሚያስከትለው beam’ሁ ላይ ነው።
የ RBS ጥቅም ከ beam’ሁ top flange እና bottom flange የሆነ ያህል radius በመቁረጥ የ steel section’ኡን መቀነስ ነው። የተቆረጠው ቦታ plastic hinge ይባላል። የተቆረጠውን radius ለማወቅ የሚከተለውን ቀመር (formula) እንጠቀማለን
R= 4c² + b²
8c
b ማለት diamter’ኡ ነው በ y-axis
c ማለት የተቆረጠበት ርዝመት ነውወ በ x-axis
ወይም cut ትባላለች
ምስሉ ላይ ብትመለከቱ ግልፅ ይሆንላችኋል።
ሌላም የ beam አይነት አስተዋውቀናችሁ ነበር castellated beam ሚባል 👇🏾👇🏾👇🏾
https://t.me/ETCONp/3709
@etconp
Moment’ን ከመቋቋሙ የ steel connection ነው። ይህም connection አይነት የተተዋወቀው እንደ አውሮጳውያን አቆጣጠር ከ1994 የ Northridge የመሬት መንቀጥቀጥ በኋላ ነው። በዚህ የመሬት መንቀጥቀጥ ማሀንዲሶች አንድ ነገር ታዘቡ ይህም brittle shear failure column’ሁ ላይ እና plastic deformation ተከሰተ ምን እንደምል steel structure design መሰረታዊ እውቀት ያላችሁ ትገነዘቡታላችሁ እናም ይህም በ theory ከሚያቁት የተለየ ነበር። ስለዚህ እንደመፍትሄ
1. Connection’ሁን ridged ማድረግ
2. የ beam’ሁን section መቀነስ
ይህም ከሆነ ተገማች ምላሽ/ውጤት ስለሚገኝ ይህም የተቆረጠ beam ለታሳበው የመሬት መንቀጥቀጥን እና የመሬት ስበት መቋቋም የሚችል section መሆን አለበት። ምስሉን በደምብ zoom አርጋችሁ ያያችሁን ከሆነ protected zone ሚባል ቦታ አለ ከ joint’ሁ እስከ reduced section’ሁ መጨረሻው ድረስ።
እንደሚታወቀው Steel construction ላይ column እና beam በ ብሎን፣ በመበየድ እናም በ revet ይገናኛሉ እናም ይህ dry connection ይባላል። እናም በ መሬት መንቀጥቀጥ ጊዜ failure ሚያስከትለው beam’ሁ ላይ ነው ማለትም ጉዳት ሚያስከትለው beam’ሁ ላይ ነው።
የ RBS ጥቅም ከ beam’ሁ top flange እና bottom flange የሆነ ያህል radius በመቁረጥ የ steel section’ኡን መቀነስ ነው። የተቆረጠው ቦታ plastic hinge ይባላል። የተቆረጠውን radius ለማወቅ የሚከተለውን ቀመር (formula) እንጠቀማለን
R= 4c² + b²
8c
b ማለት diamter’ኡ ነው በ y-axis
c ማለት የተቆረጠበት ርዝመት ነውወ በ x-axis
ወይም cut ትባላለች
ምስሉ ላይ ብትመለከቱ ግልፅ ይሆንላችኋል።
ሌላም የ beam አይነት አስተዋውቀናችሁ ነበር castellated beam ሚባል 👇🏾👇🏾👇🏾
https://t.me/ETCONp/3709
@etconp
Telegram
Ethio Construction Engineering
🔨 World Construction Engineering
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
Ethio Construction Engineering
Are you guys familiar with Reduced Beam Section (RBS) ? If you participate we will make some presentation regarding this topic . If you don’t participate we assume that you’re not interested in this topic so we will leave it. ተሳትፎ ካደረጋችሁ ይህን ርዕስ በተመለከተ…
Reduced beam section (RBS)
Reduced Beam Section (RBS) moment resisting connections are among the most economical and practical rigid steel connections developed 1994 Northridge earthquakes.
During that incident People observed plastic deformations in panel zone and brittle shear failure in columns and panel zones as well as connections.This proved that we cannot rely significantly on connections as they do not have any ductility capacity. So there were two options:
1 .Make the connections and panel zone of column significantly stronger and more rigid. Forcing the beam to form hinge away from the connection.
2 .Weakening the section of beam away from the beam column joint to get more predicted response of the structure.
Reduced beam section uses the second approach.
The main objective of the applied RBS geometry is to protect the connection and its components (endplate, column flange, bolts, welds) from either plastification or failure.
Reduced Beam Section is useful in order to achieve higher ductility of the seismic system and improve the performance of the structure under earthquake.
This reduced capacity of the beam section should be greater than the moment demand due to seismic demand as well as the gravity loading. By doing this, in case of an earthquake, the plastic hinge in beam is forced away from the beam column joint. Higher ductility demand can be achieved and possible brittle failure because of uncertainties is eliminated.
To calculate the radius of reduced section we use the following formula
R = 4C² +b²
8c
Where
C = the cut in the x-axis
b = the radius of the cut
@etconp
Reduced Beam Section (RBS) moment resisting connections are among the most economical and practical rigid steel connections developed 1994 Northridge earthquakes.
During that incident People observed plastic deformations in panel zone and brittle shear failure in columns and panel zones as well as connections.This proved that we cannot rely significantly on connections as they do not have any ductility capacity. So there were two options:
1 .Make the connections and panel zone of column significantly stronger and more rigid. Forcing the beam to form hinge away from the connection.
2 .Weakening the section of beam away from the beam column joint to get more predicted response of the structure.
Reduced beam section uses the second approach.
The main objective of the applied RBS geometry is to protect the connection and its components (endplate, column flange, bolts, welds) from either plastification or failure.
Reduced Beam Section is useful in order to achieve higher ductility of the seismic system and improve the performance of the structure under earthquake.
This reduced capacity of the beam section should be greater than the moment demand due to seismic demand as well as the gravity loading. By doing this, in case of an earthquake, the plastic hinge in beam is forced away from the beam column joint. Higher ductility demand can be achieved and possible brittle failure because of uncertainties is eliminated.
To calculate the radius of reduced section we use the following formula
R = 4C² +b²
8c
Where
C = the cut in the x-axis
b = the radius of the cut
@etconp
Telegram
Ethio Construction Engineering
🔨 World Construction Engineering
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
👉የሲዳማ ህዝብ ልዩ ምልክት የሆነውን የሻፌታ ታወር ግንባታ ስምምነት የሀዋሳ ከተማ አስተዳደር በ ትላንትና ዕለት ተፈራርሟል፡፡
🚧የሀዋሳ ከተማ አስተዳር ምክትል ከንቲባ አቶ ጥራቱ በየነን ጨምሮ ሌሎች የካቢኔ አባላትና የስራ ኃላፊዎች እንዲሁም የግንባታ ጨረታውን ያሸነፉ የኮንስትራክሽን ስራ ተቋራጭ ስራ አስኪያጆች በተገኙበት የፊርማ ስነ ስርዓቱ በሀይሌ ሪዞርት ሆቴል ተካሂዷል፡፡
🚧በሌላ በኩብ በሀዌላ ቱላ ክፍለከተማ ከቱላ ወዮ እንዲሁም ከወንዶ ማዞሪያ እስከ ቡሹሎ 8.75 ኪ.ሜ የሚሸፍን አዲስ የአስፓልት መንገድ በ508 ሚሊየን ብር ወጪ ለመገንባት ከተማ አስተዳደሩ ከይርጋለም ኮንስትራክሽን ስራ ተቋራጭ ጋር የውል ስምምነት ተፈራርሟል፡፡
ምንጭ፦ የሀዋሳ ከተማ አስተዳደር
@etconp
🚧የሀዋሳ ከተማ አስተዳር ምክትል ከንቲባ አቶ ጥራቱ በየነን ጨምሮ ሌሎች የካቢኔ አባላትና የስራ ኃላፊዎች እንዲሁም የግንባታ ጨረታውን ያሸነፉ የኮንስትራክሽን ስራ ተቋራጭ ስራ አስኪያጆች በተገኙበት የፊርማ ስነ ስርዓቱ በሀይሌ ሪዞርት ሆቴል ተካሂዷል፡፡
🚧በሌላ በኩብ በሀዌላ ቱላ ክፍለከተማ ከቱላ ወዮ እንዲሁም ከወንዶ ማዞሪያ እስከ ቡሹሎ 8.75 ኪ.ሜ የሚሸፍን አዲስ የአስፓልት መንገድ በ508 ሚሊየን ብር ወጪ ለመገንባት ከተማ አስተዳደሩ ከይርጋለም ኮንስትራክሽን ስራ ተቋራጭ ጋር የውል ስምምነት ተፈራርሟል፡፡
ምንጭ፦ የሀዋሳ ከተማ አስተዳደር
@etconp
Dear @etconp members we are preparing to present you 100 tallest building structure in the world 🌎 are you ready ? We will post one presentation in descending order daily for 100 days so that you will be familiar with 100 tallest building on earth
ውድ የቻናላችን ቤተሰቦች በአለማችን ያሉ 100 ረዣዥም ህንፃዎችን በቅደም ተከተል ለ100 ቀን ልናቀርብላችተሁ አስበናል ምን ታስባላችሁ?
@etconp
ውድ የቻናላችን ቤተሰቦች በአለማችን ያሉ 100 ረዣዥም ህንፃዎችን በቅደም ተከተል ለ100 ቀን ልናቀርብላችተሁ አስበናል ምን ታስባላችሁ?
@etconp
Forwarded from Ethio Construction Engineering (जॉर्डनो ג׳ורדנו ጆርዳኖ جوردانو จอร์แดโน่ JORDANO Ιορδάνοςஜார்டானோ)
What is the difference between C30 concrete and M30 concrete? And what does PSI mean?
እኛ እንደምናውቀው የ concrete grade የሚገለፀው C-5,C-20, C-30...... እየተባለ ነው።
ግን እዚህ ምስል ላይ የምትመለከቱት 👆🏾👆🏾.... M5,M30, M30 እያለ ነው።
❓ምንድንነው የሁለቱ ልዩነት
ሌላኛው እዚህ ምስል ላይ PSI ይላል።
❔what does PSI stands for
#share this and let’s discuss @cotmp
ይህን ጥያቄ ለጓደኞቻችው በማጋራት አጋርነታችሁን አሳዩን 🙏።
@etconp
እኛ እንደምናውቀው የ concrete grade የሚገለፀው C-5,C-20, C-30...... እየተባለ ነው።
ግን እዚህ ምስል ላይ የምትመለከቱት 👆🏾👆🏾.... M5,M30, M30 እያለ ነው።
❓ምንድንነው የሁለቱ ልዩነት
ሌላኛው እዚህ ምስል ላይ PSI ይላል።
❔what does PSI stands for
#share this and let’s discuss @cotmp
ይህን ጥያቄ ለጓደኞቻችው በማጋራት አጋርነታችሁን አሳዩን 🙏።
@etconp
Forwarded from Ethio Construction Engineering (जॉर्डनो ג׳ורדנו ጆርዳኖ جوردانو จอร์แดโน่ JORDANO Ιορδάνοςஜார்டானோ)
Answer for this question
C - stands for concrete strength class
M- stands for MIX
Concrete strength’ሁን የሚያገኘው ከ mix design ነው።
M30 signifies that a CUBE of size
15cm x 15 cm x 15cm made of cement ( Portland cement) + sand ( fine aggregate) + gravel ( coarse aggregate) in such ratio that is characteristic strength (𝑓𝑐𝑘) is 30N/mm² after 28days of curing , whereas C30 symbolizes a CYLINDRICAL sample in which cement ( Portland cement ) + fine aggregate ( sand) + gravel( coarse aggregate) are mixed in such ratio that’s characteristic strength (𝑓𝑐𝑘) after 28 days of curing is 30N/mm² .
Let’s see the conversion
Strength of cylinder sample= 0.8 x strength of cube
Example M20 is equivalent to to C16 and M20 is equivalent to 20
Standard
➪ Cube size as I mentioned
15cmx 15cm x15cm
➪ cylinder size
15 cm diameter x 30 cm height
PSI stands for pounds per square inch
1 PSI= 0.00689 MPA
#watermark
#share
ይህን በማጋራት አጋርነታችሁን አሳዩን 🙏።
@etconp
C - stands for concrete strength class
M- stands for MIX
Concrete strength’ሁን የሚያገኘው ከ mix design ነው።
M30 signifies that a CUBE of size
15cm x 15 cm x 15cm made of cement ( Portland cement) + sand ( fine aggregate) + gravel ( coarse aggregate) in such ratio that is characteristic strength (𝑓𝑐𝑘) is 30N/mm² after 28days of curing , whereas C30 symbolizes a CYLINDRICAL sample in which cement ( Portland cement ) + fine aggregate ( sand) + gravel( coarse aggregate) are mixed in such ratio that’s characteristic strength (𝑓𝑐𝑘) after 28 days of curing is 30N/mm² .
Let’s see the conversion
Strength of cylinder sample= 0.8 x strength of cube
Example M20 is equivalent to to C16 and M20 is equivalent to 20
Standard
➪ Cube size as I mentioned
15cmx 15cm x15cm
➪ cylinder size
15 cm diameter x 30 cm height
PSI stands for pounds per square inch
1 PSI= 0.00689 MPA
#watermark
#share
ይህን በማጋራት አጋርነታችሁን አሳዩን 🙏።
@etconp
Telegram
Ethio Construction Engineering
🔨 World Construction Engineering
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
Six main types of bridge
1. Arch bridge counter load in its arch action An arch bridge is a bridge with abutments at each end shaped as a curved arch.
2. truss bridge is a bridge whose load-bearing superstructure is composed of a truss, a structure of connected elements usually forming triangular units.
3. Beam bridges are the simplest structural forms for bridge spans supported by pier at each end. No moments are transferred throughout the support,
4. suspension bridge is a type of bridge in which the deck is hung below suspension cables on vertical suspenders
5. cable-stayed bridge has one or more towers (or pylons), from which cables support the bridge deck. A distinctive feature are the cables or stays, which run directly from the tower to the deck, normally forming a fan-like pattern or a series of parallel lines.
6. cantilever bridge is a bridge built using cantilevers, structures that project horizontally into space, supported on only one end and join at the center
@etconp
Insta:-@etconp
1. Arch bridge counter load in its arch action An arch bridge is a bridge with abutments at each end shaped as a curved arch.
2. truss bridge is a bridge whose load-bearing superstructure is composed of a truss, a structure of connected elements usually forming triangular units.
3. Beam bridges are the simplest structural forms for bridge spans supported by pier at each end. No moments are transferred throughout the support,
4. suspension bridge is a type of bridge in which the deck is hung below suspension cables on vertical suspenders
5. cable-stayed bridge has one or more towers (or pylons), from which cables support the bridge deck. A distinctive feature are the cables or stays, which run directly from the tower to the deck, normally forming a fan-like pattern or a series of parallel lines.
6. cantilever bridge is a bridge built using cantilevers, structures that project horizontally into space, supported on only one end and join at the center
@etconp
Insta:-@etconp
Forwarded from Ethio Construction Engineering (जॉर्डनो ג׳ורדנו ጆርዳኖ جوردانو จอร์แดโน่ JORDANO Ιορδάνοςஜார்டானோ)
As you know to determine weight of the bar we use two formulas
1. W= D² x Length of the bar
162
2. W = D² X length of the bar
52.9
When do we use the first formula when do we use the second formula ?
Share this question with your friends ?
@etconp
1. W= D² x Length of the bar
162
2. W = D² X length of the bar
52.9
When do we use the first formula when do we use the second formula ?
Share this question with your friends ?
@etconp
Telegram
Ethio Construction Engineering
🔨 World Construction Engineering
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
Latest updates, tips, and tutorials on building, civil engineering, and construction in World.
Learn, build, and grow with us!
📨 @Philemona7 Or @ETCONpBOT
For Ad:- https://telega.io/c/etconp
#SOM
SYSTEM OF FORCES
When two or more forces act on a body, they are called to form a system of forces. Following
systems of forces are important from the subject point of view :
1. Coplanar forces. The forces, whose lines of action lie on the same plane, are known as
coplanar forces.
2. Collinear forces. The forces, whose lines of action lie on the same line, are known as
collinear forces.
3. Concurrent forces. The forces, which meet at one point, are known as concurrent forces. The concurrent forces may or may not be collinear.
4. Coplanar concurrent forces. The forces, which meet at one point and their lines of action
also lie on the same plane, are known as coplanar concurrent forces.
5. Coplanar non-concurrent forces. The forces, which do not meet at one point, but their
lines of action lie on the same plane, are known as coplanar non-concurrent forces.
6. Non-coplanar concurrent forces. The forces, which meet at one point, but their lines of
action do not lie on the same plane, are known as non-coplanar concurrent forces.
7. Non-coplanar non-concurrent forces. The forces, which do not meet at one point and their
lines of action do not lie on the same plane, are called non-coplanar non-concurrent forces.
Join📚share📚Helpful
@ETCONP
SYSTEM OF FORCES
When two or more forces act on a body, they are called to form a system of forces. Following
systems of forces are important from the subject point of view :
1. Coplanar forces. The forces, whose lines of action lie on the same plane, are known as
coplanar forces.
2. Collinear forces. The forces, whose lines of action lie on the same line, are known as
collinear forces.
3. Concurrent forces. The forces, which meet at one point, are known as concurrent forces. The concurrent forces may or may not be collinear.
4. Coplanar concurrent forces. The forces, which meet at one point and their lines of action
also lie on the same plane, are known as coplanar concurrent forces.
5. Coplanar non-concurrent forces. The forces, which do not meet at one point, but their
lines of action lie on the same plane, are known as coplanar non-concurrent forces.
6. Non-coplanar concurrent forces. The forces, which meet at one point, but their lines of
action do not lie on the same plane, are known as non-coplanar concurrent forces.
7. Non-coplanar non-concurrent forces. The forces, which do not meet at one point and their
lines of action do not lie on the same plane, are called non-coplanar non-concurrent forces.
Join📚share📚Helpful
@ETCONP
SURVEYING...
📌▪Some important points related to Surveying▪
▪The basic principle of surveying working from whole to part
👉 Prevents accumulation of errors and localised minor errors
▪An Equilateral triangle is considered to be the best well conditional triangle
( 30° to 120° )
▪The best shape of triangle in triangulation is isosceles with base angle 56°14'
▪A good draftsman can plot a distance as small as a 0.25mm
▪ Control survey for fixing the points on the boundary
▪ land/Cadstral survey to measure the area of land ,
To Fix the legal boundaries and to locate the reference points
▪ Astronomical survey
Study about celestial body,
Determination of latitude and longitude.
▪ Archaeological survey
To Know The civilization of People.
👉The principle involved in chain survey is of triangulation
👉 Compass survey uses the principle of traversing .
👉The principle of plane table survey is parallelism .
👉The principle of Tacheometer is based on property of isosceles triangle, where ratio of the distance of the base from the apex and the length of the base is always constant .
▪Least Count Of Surveying Instruments
👉Prismatic Compass = 30'
👉 Surveyor Compass = 15'
👉 Total station= 1sec
👉Theodolite = 20"
👉 levelling Staff = 5mm
👉 Dummy level=5mm
▪Important Points in surveying.
👉Horizontal plane tangential to the level surface.
👉Level surfaces parallel to the mean spheroidal surface of the earth
👉RL of the line of collimation is known as the height of instrument
👉 Differential levelling also known as compound levelling or continuous levelling
👉Fly levelling is used to connect the benchmark to the starting point of alignment of any project
👉 Check levelling is the fly levelling done at the end of the days work to connect the point with starting point on that particular day to check the accuracy of the days work.
Join👉👉 @ETCONP
📌▪Some important points related to Surveying▪
▪The basic principle of surveying working from whole to part
👉 Prevents accumulation of errors and localised minor errors
▪An Equilateral triangle is considered to be the best well conditional triangle
( 30° to 120° )
▪The best shape of triangle in triangulation is isosceles with base angle 56°14'
▪A good draftsman can plot a distance as small as a 0.25mm
▪ Control survey for fixing the points on the boundary
▪ land/Cadstral survey to measure the area of land ,
To Fix the legal boundaries and to locate the reference points
▪ Astronomical survey
Study about celestial body,
Determination of latitude and longitude.
▪ Archaeological survey
To Know The civilization of People.
👉The principle involved in chain survey is of triangulation
👉 Compass survey uses the principle of traversing .
👉The principle of plane table survey is parallelism .
👉The principle of Tacheometer is based on property of isosceles triangle, where ratio of the distance of the base from the apex and the length of the base is always constant .
▪Least Count Of Surveying Instruments
👉Prismatic Compass = 30'
👉 Surveyor Compass = 15'
👉 Total station= 1sec
👉Theodolite = 20"
👉 levelling Staff = 5mm
👉 Dummy level=5mm
▪Important Points in surveying.
👉Horizontal plane tangential to the level surface.
👉Level surfaces parallel to the mean spheroidal surface of the earth
👉RL of the line of collimation is known as the height of instrument
👉 Differential levelling also known as compound levelling or continuous levelling
👉Fly levelling is used to connect the benchmark to the starting point of alignment of any project
👉 Check levelling is the fly levelling done at the end of the days work to connect the point with starting point on that particular day to check the accuracy of the days work.
Join👉👉 @ETCONP
Engineering mechanics
Analysis of simple trusses
🔰 Method of joints
👉 Analysis should be started from joint where there are not more than two members in which forces are unknown.
Step I) calculate support reaction
Step II Draw FBD of each joint & compute member forces.
🔰 Method of sections
Step I) calculate support reaction
Step II) Consider a section. Section should not cut more than 3 members in which forces are unknown.
Step III) Conditiona of equilibrium is applied on either part of truss and forces are determined.
🔰 Zero force members(VIMP)
RULE 1) If at any joint only two members are meeting & there is no external load & support then those members carry zero force
RULE 2) If at a joint '3' members meeting such that two members are collinear & no external load or support reaction acting at joint then third member is zero force member.
RULE 3) If panel shear in particular member is zero then that member carries zero force.
Join👉👉 @ETCONP
Analysis of simple trusses
🔰 Method of joints
👉 Analysis should be started from joint where there are not more than two members in which forces are unknown.
Step I) calculate support reaction
Step II Draw FBD of each joint & compute member forces.
🔰 Method of sections
Step I) calculate support reaction
Step II) Consider a section. Section should not cut more than 3 members in which forces are unknown.
Step III) Conditiona of equilibrium is applied on either part of truss and forces are determined.
🔰 Zero force members(VIMP)
RULE 1) If at any joint only two members are meeting & there is no external load & support then those members carry zero force
RULE 2) If at a joint '3' members meeting such that two members are collinear & no external load or support reaction acting at joint then third member is zero force member.
RULE 3) If panel shear in particular member is zero then that member carries zero force.
Join👉👉 @ETCONP
Forwarded from Ethio Construction Engineering
Strain (Deformation)
Strain is defined as "deformation of a solid due to stress".
Normal strain - elongation or contraction of a line segment
Shear strain - change in angle between two line segments originally perpendicular Normal strain and can be expressed as
ε = dl / l o
= σ / E (3)
where
dl = change of length (m, in)
l o = initial length (m, in)
ε = strain - unit-less
E = Young's modulus (Modulus of Elasticity) (Pa , (N/ m 2 ), psi (lb f /in 2 ))
Young's modulus can be used to predict the elongation or compression of an object when exposed to a force
Note that strain is a dimensionless unit since it is the ratio of two lengths. But it also common practice to state it as the ratio of two length units - like m/m or in/in .
Poisson's ratio is the ratio of relative contraction strain
Example - Stress and Change of Length
The rod in the example above is 2 m long and made of steel with Modulus of Elasticity 200 GPa (200 10 9 N/m 2 ) . The change of length can be calculated by transforming (3) to
dl = σ lo / E
= (127 10 6 Pa) (2 m) / (200 10 9 Pa)
= 0.00127 m
= 1.27 mm
Strain Energy
Stressing an object stores energy in it. For an axial load the energy stored can be expressed as
U = 1/2 F n dl
where
U = deformation energy (J (N m), ft lb)
Strain is defined as "deformation of a solid due to stress".
Normal strain - elongation or contraction of a line segment
Shear strain - change in angle between two line segments originally perpendicular Normal strain and can be expressed as
ε = dl / l o
= σ / E (3)
where
dl = change of length (m, in)
l o = initial length (m, in)
ε = strain - unit-less
E = Young's modulus (Modulus of Elasticity) (Pa , (N/ m 2 ), psi (lb f /in 2 ))
Young's modulus can be used to predict the elongation or compression of an object when exposed to a force
Note that strain is a dimensionless unit since it is the ratio of two lengths. But it also common practice to state it as the ratio of two length units - like m/m or in/in .
Poisson's ratio is the ratio of relative contraction strain
Example - Stress and Change of Length
The rod in the example above is 2 m long and made of steel with Modulus of Elasticity 200 GPa (200 10 9 N/m 2 ) . The change of length can be calculated by transforming (3) to
dl = σ lo / E
= (127 10 6 Pa) (2 m) / (200 10 9 Pa)
= 0.00127 m
= 1.27 mm
Strain Energy
Stressing an object stores energy in it. For an axial load the energy stored can be expressed as
U = 1/2 F n dl
where
U = deformation energy (J (N m), ft lb)