👉Why do we use development length in beam reinforcement?
📌Development Length is essentially provided to create a bond between steel and concrete in order to transfer the bar force without slip to prevent the bar from pulling out under tension.
.
🚧Image A: The development length is provided in the beam and column junction.
*Due to this the stresses developed are easily transferred by the bond created by steel and concrete.
.
🚧Image B: The development length is not provided in the beam and column junction.
*Due to this the stresses developed in the beams will not be able to transfer it to the column.
📌Development Length is essentially provided to create a bond between steel and concrete in order to transfer the bar force without slip to prevent the bar from pulling out under tension.
.
🚧Image A: The development length is provided in the beam and column junction.
*Due to this the stresses developed are easily transferred by the bond created by steel and concrete.
.
🚧Image B: The development length is not provided in the beam and column junction.
*Due to this the stresses developed in the beams will not be able to transfer it to the column.
Ethio Construction Engineering via @like
#4. Lotte World Tower ➪ Height:- 556 meters ➪ Number of story :- 130 ➪ Floor above the ground:- 123 ➪ Floor below the ground :- 6 ➪ Number of elevator :- 58 ➪ Speed of elevator :- 10m/s ➪ Structural system:- core structure (composite) ➪ Ground floor area…
#5. One World Trade Center
➪ height:- 541.3 meters
➪ number of story :- 94
➪ floor above the ground:- 88
➪ floor below the ground:- 5
➪ floor area :- 325,279 m²
➪ elevators:- 73
➪ elevator speed :- 23mile/hour
➪ architect :- David childs
➪ Structural engineer:- WSP Cantor
➪ contractor :- Tishman construction
➪ cost :- $3.9 billion
➪ construction started :- April 27, 2006
➪ completed:- November 3, 2014
New York USA🇺🇸
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
➪ height:- 541.3 meters
➪ number of story :- 94
➪ floor above the ground:- 88
➪ floor below the ground:- 5
➪ floor area :- 325,279 m²
➪ elevators:- 73
➪ elevator speed :- 23mile/hour
➪ architect :- David childs
➪ Structural engineer:- WSP Cantor
➪ contractor :- Tishman construction
➪ cost :- $3.9 billion
➪ construction started :- April 27, 2006
➪ completed:- November 3, 2014
New York USA🇺🇸
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
👉እስቲ ኣሁን ደሞ ስለ lap length , Development length,Anchorage length ትንሽ እንንገራቹ...
.
🚧ላፕ ሌንግዝ (lap length) - ተፈላጊ የብረት (ፌሮ) ርዝመት
ውጥረትን (stresses) ከአንድ ብረት ወደሌላ የሚተላለፍበት
.
🚧ደቨሎፕመንት ሌንግዝ (Development length) -ተፈላጊ
የብረት ርዝመት ውጥረትን (stresses) ከብረቱ ወደ ኮንክሪቱ
የሚተላለፍበት
.
🚧አንኮሬጅ ሌንግዝ (Anchorage length) - ይህ ርዝመት
አይነት በቂ የሆነ ደቨሎፕመንት ሌንግዝ (development
length ) በሌለባቸው በ Support / fixed ends ላይ
provide የምናረገው ርዝመት ነው::
@etconp
.
🚧ላፕ ሌንግዝ (lap length) - ተፈላጊ የብረት (ፌሮ) ርዝመት
ውጥረትን (stresses) ከአንድ ብረት ወደሌላ የሚተላለፍበት
.
🚧ደቨሎፕመንት ሌንግዝ (Development length) -ተፈላጊ
የብረት ርዝመት ውጥረትን (stresses) ከብረቱ ወደ ኮንክሪቱ
የሚተላለፍበት
.
🚧አንኮሬጅ ሌንግዝ (Anchorage length) - ይህ ርዝመት
አይነት በቂ የሆነ ደቨሎፕመንት ሌንግዝ (development
length ) በሌለባቸው በ Support / fixed ends ላይ
provide የምናረገው ርዝመት ነው::
@etconp
👍1
👉Concrete Technology
.
➡️How to make concrete more crack resistant used for sidewalks and Any Structures?
.
📌The main reason why concrete cracks is because it shrinks.
*It shrinks as it loses water.
*Most of that happens because of evaporation when we let it dry.
.
🚧So, the first thing to do is to minimise the amount of water present in the mix.
*That is done by minimising the workability of the concrete, improving the mix design, using water reducers or high range water reducers.
.
🚧Another thing to do is to have jointing at realistic distances, and making those joints early.
.
🚧Some aggregates are more resistant to shrinkage than others. *yielding a lower shrinkage mix.
.
🚧Always put diagonal bars (plural) across reentrant corners, such as around drainage grates and other places where a diagonal crack is likely to form.
*The bars go at right angles to the expected crack, of course.
.
🚧Some other kinds of cement other than Portland cement can have a somewhat lower drying shrinkage than Portland cement.
.
🚧Concrete hardens by chemical reactions involving the cement and the water.
*Once the water is gone, strength gain, like Grandfather’s clock “stopped dead, never to go again”.😁
*Do not let your concrete dry out prematurely. *Keeping it moist is called “curing”.
#ConcreteTechnology
@etconp
.
➡️How to make concrete more crack resistant used for sidewalks and Any Structures?
.
📌The main reason why concrete cracks is because it shrinks.
*It shrinks as it loses water.
*Most of that happens because of evaporation when we let it dry.
.
🚧So, the first thing to do is to minimise the amount of water present in the mix.
*That is done by minimising the workability of the concrete, improving the mix design, using water reducers or high range water reducers.
.
🚧Another thing to do is to have jointing at realistic distances, and making those joints early.
.
🚧Some aggregates are more resistant to shrinkage than others. *yielding a lower shrinkage mix.
.
🚧Always put diagonal bars (plural) across reentrant corners, such as around drainage grates and other places where a diagonal crack is likely to form.
*The bars go at right angles to the expected crack, of course.
.
🚧Some other kinds of cement other than Portland cement can have a somewhat lower drying shrinkage than Portland cement.
.
🚧Concrete hardens by chemical reactions involving the cement and the water.
*Once the water is gone, strength gain, like Grandfather’s clock “stopped dead, never to go again”.😁
*Do not let your concrete dry out prematurely. *Keeping it moist is called “curing”.
#ConcreteTechnology
@etconp
Ethio Construction Engineering via @like
#5. One World Trade Center ➪ height:- 541.3 meters ➪ number of story :- 94 ➪ floor above the ground:- 88 ➪ floor below the ground:- 5 ➪ floor area :- 325,279 m² ➪ elevators:- 73 ➪ elevator speed :- 23mile/hour ➪ architect :- David childs ➪ Structural…
#6. Taipei 101
➪ Height :- 509.2 meters
➪ Floor above the ground:- 101
➪ Floor below the ground:- 5
➪ Floor area :- 412,500 m²
➪ Number of elevator:- 61
➪ Speed of elevator:- 38 miles per hour
➪ structural system:- core (composite)
➪ Architect:- C.Y. Lee
➪ structural engineer:- Evergreen Consulting
➪ Contractor:- KTRT Joint Venture
➪ Cost :- $1.89 billion
➪ Owner:- Taipei finical center co.
The damper has become such a popular tourist attraction that the city contracted Sanrio to create a mascot: the Damper Baby. If you’re not familiar with damper open this link https://t.me/ETCONp/1129
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
➪ Height :- 509.2 meters
➪ Floor above the ground:- 101
➪ Floor below the ground:- 5
➪ Floor area :- 412,500 m²
➪ Number of elevator:- 61
➪ Speed of elevator:- 38 miles per hour
➪ structural system:- core (composite)
➪ Architect:- C.Y. Lee
➪ structural engineer:- Evergreen Consulting
➪ Contractor:- KTRT Joint Venture
➪ Cost :- $1.89 billion
➪ Owner:- Taipei finical center co.
The damper has become such a popular tourist attraction that the city contracted Sanrio to create a mascot: the Damper Baby. If you’re not familiar with damper open this link https://t.me/ETCONp/1129
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
👉Why don’t we use circular beams in construction or in structures?
.
➡️RCC structures, the circular cross section of the RCC Beam is not adapted.
.
🚧Before we look at the reasons, please have a look at the framed structure where the conventional Rectangular section has been adapted :
.
🚧In context of the site photograph, let us have a look at some reasons :
1.Formwork :
.
▶️Very difficult It has to be made out of either MS sheets or Aluminum sections.
.
🚧Fixing it horizontally is more challenging since the base of the beam form work shall be semi circular.
.
🚧The Formwork shall need to have a provision on the top for pouring concrete.
2.The casting :
🚧Imagine that a conventional letter box is laid Horizontality and you have to pour concrete through the opening at the top.
.
🚧The concrete has to be high slump concrete so that it moves to all crevices of the section.
.
🚧Finishing the top portion of the beam shall be a highly skilled job.
.
3.The de shuttering :
.
🚧It shall not be possible to first strike off the sides and then the beam bottom .
.
🚧The form work shall have to be removed in two halves after the concrete attains the strength.
.
➡️Hope you’re clear with certain difficulties associated with the circular sections.
@etconp
.
➡️RCC structures, the circular cross section of the RCC Beam is not adapted.
.
🚧Before we look at the reasons, please have a look at the framed structure where the conventional Rectangular section has been adapted :
.
🚧In context of the site photograph, let us have a look at some reasons :
1.Formwork :
.
▶️Very difficult It has to be made out of either MS sheets or Aluminum sections.
.
🚧Fixing it horizontally is more challenging since the base of the beam form work shall be semi circular.
.
🚧The Formwork shall need to have a provision on the top for pouring concrete.
2.The casting :
🚧Imagine that a conventional letter box is laid Horizontality and you have to pour concrete through the opening at the top.
.
🚧The concrete has to be high slump concrete so that it moves to all crevices of the section.
.
🚧Finishing the top portion of the beam shall be a highly skilled job.
.
3.The de shuttering :
.
🚧It shall not be possible to first strike off the sides and then the beam bottom .
.
🚧The form work shall have to be removed in two halves after the concrete attains the strength.
.
➡️Hope you’re clear with certain difficulties associated with the circular sections.
@etconp
👉What is total station in surveying?
▶️TOTAL STATION
🚧This is an electronic tachometer, which consist of an electronic transit theodolite added electronic distance meter + internal data storage facilities. *which not only measure the horizontal and vertical angles and distances electronically but also is capable of calculating the parametric positions and levels instantaneously.
.
🚧An electronic field book can be interfaced with the instrument to record and store not only the angles and distance but also the coordinates and levels of the points and other related information.
.
🚧The least count is 1mm for linear measurements and 1″ and less for angular measurement.
.
🚧Total station can be used to measure and obtain data apart to distance and angular measurements on-site like (a)Automatic slope correction
(b)Remote elevation
(c)Missing line
(d) Horizontal c
#surveying
@etconp
▶️TOTAL STATION
🚧This is an electronic tachometer, which consist of an electronic transit theodolite added electronic distance meter + internal data storage facilities. *which not only measure the horizontal and vertical angles and distances electronically but also is capable of calculating the parametric positions and levels instantaneously.
.
🚧An electronic field book can be interfaced with the instrument to record and store not only the angles and distance but also the coordinates and levels of the points and other related information.
.
🚧The least count is 1mm for linear measurements and 1″ and less for angular measurement.
.
🚧Total station can be used to measure and obtain data apart to distance and angular measurements on-site like (a)Automatic slope correction
(b)Remote elevation
(c)Missing line
(d) Horizontal c
#surveying
@etconp
👉በአዲስ አበባ “ቤት ለሁሉም” የተሰኘ ፕሮጀክት ሊተገበር መሆኑ ተገለፀ
**********************
🚧በአዲስ አበባ “ቤት ለሁሉም” የተሰኘ ፕሮጀክት ትግበራ በቅርቡ ይፋ እንደሚሆን የከተማዋ አስተዳደር ገለፀ።
.
🚧ከተማ አስተዳደሩ ለተቋማት ሕንጻ ኪራይ በየዓመቱ 650 ሚሊዮን ብር እንደሚያወጣም ተነግሯል።
.
🚧ከሐምሌ 25 ቀን 2012 ዓ.ም ጀምሮ አዳማ ላይ የተካሄደው የአዲስ አበባ ከተማ አስተዳደርና የክፍለ ከተሞች ዳይሬክተሮችና የቡድን መሪዎች ስልጠና ዛሬ ተጠናቋል።
.
🚧በስልጠናው ማጠናቂያ ላይ የተገኙት ምክትል ከንቲባ ታከለ ኡማ ከከተማው የቤት ፍላጎት አኳያ የተሰራው ስራ ጎልቶ አለመውጣቱንና ግንባታው ፍላጎቱን ማሟላት ካልቻለ ቤት ተገንብቷል ማለት እንደማይቻል ተናግረዋል።
🚧ለ40/60 ቤቶች 100 ሺህ፣ ለ20/80 ደግሞ 600 ሺህ ያህል ዜጎች ተመዝገበው በመጠባበቅ ላይ እንደሚገኙም ነው ያነሱት።
🚧ኢንጂነር ታከለ ኡማ በአዲስ አበባ አስተዳደር 125 ሺህ ቤቶች እየተገነቡ እንደሆነም ነው የገለጹት።
🚧እንደ ምክትል ከንቲባው ገለፃ ከፌዴራል መንግስት ጋር በመሆን ሁሉም የመዲናዋ ነዋሪ ቤት የሚያገኝበትን ሁኔታ የሚፈጥር ፕሮጀክት በቅርቡ ይፋ ይደረጋል።
Via EBC
@etconp
**********************
🚧በአዲስ አበባ “ቤት ለሁሉም” የተሰኘ ፕሮጀክት ትግበራ በቅርቡ ይፋ እንደሚሆን የከተማዋ አስተዳደር ገለፀ።
.
🚧ከተማ አስተዳደሩ ለተቋማት ሕንጻ ኪራይ በየዓመቱ 650 ሚሊዮን ብር እንደሚያወጣም ተነግሯል።
.
🚧ከሐምሌ 25 ቀን 2012 ዓ.ም ጀምሮ አዳማ ላይ የተካሄደው የአዲስ አበባ ከተማ አስተዳደርና የክፍለ ከተሞች ዳይሬክተሮችና የቡድን መሪዎች ስልጠና ዛሬ ተጠናቋል።
.
🚧በስልጠናው ማጠናቂያ ላይ የተገኙት ምክትል ከንቲባ ታከለ ኡማ ከከተማው የቤት ፍላጎት አኳያ የተሰራው ስራ ጎልቶ አለመውጣቱንና ግንባታው ፍላጎቱን ማሟላት ካልቻለ ቤት ተገንብቷል ማለት እንደማይቻል ተናግረዋል።
🚧ለ40/60 ቤቶች 100 ሺህ፣ ለ20/80 ደግሞ 600 ሺህ ያህል ዜጎች ተመዝገበው በመጠባበቅ ላይ እንደሚገኙም ነው ያነሱት።
🚧ኢንጂነር ታከለ ኡማ በአዲስ አበባ አስተዳደር 125 ሺህ ቤቶች እየተገነቡ እንደሆነም ነው የገለጹት።
🚧እንደ ምክትል ከንቲባው ገለፃ ከፌዴራል መንግስት ጋር በመሆን ሁሉም የመዲናዋ ነዋሪ ቤት የሚያገኝበትን ሁኔታ የሚፈጥር ፕሮጀክት በቅርቡ ይፋ ይደረጋል።
Via EBC
@etconp
👉Why do we provide a concrete cover?
.
📌Reinforced Concrete is a composite material.
*We have steel to take the tension and concrete the compression.
*Now, reinforcing steel is susceptible from damage due to corrosion and it needs to bond with steel to actually work as a composite.
.
🚧This film is stable in the highly alkaline environment of concrete. However, with time and exposure to Carbon di Oxide in environment which gets dissolved in water and enters the concrete through the permeability and cracks the pH of concrete reduces.
*As a result, this layer decomposes And, deleterious agents start attacking the reinforcements resulting in corrosion.
.
🚧The corroded reinforcement expands in size and spalls the cover leading to further exposure and further corrosion till the structure fails.
@etconp
.
📌Reinforced Concrete is a composite material.
*We have steel to take the tension and concrete the compression.
*Now, reinforcing steel is susceptible from damage due to corrosion and it needs to bond with steel to actually work as a composite.
.
🚧This film is stable in the highly alkaline environment of concrete. However, with time and exposure to Carbon di Oxide in environment which gets dissolved in water and enters the concrete through the permeability and cracks the pH of concrete reduces.
*As a result, this layer decomposes And, deleterious agents start attacking the reinforcements resulting in corrosion.
.
🚧The corroded reinforcement expands in size and spalls the cover leading to further exposure and further corrosion till the structure fails.
@etconp
👉የ አዲስ አበባ ኮንስትራክሽን ቢሮ በ2012 በጀት ዓመት የተሻለ ውጤት በማስመዝገቡ ከ አዲስ አበባ ከተማ ምክር ቤት ሽልማት ተበርክቶለታል፡፡
.
🚧መላው የተቋሙ አመራርና ሰራተኞች እንኳን ለዚህ ስኬት አበቃችሁ::
@etconp
.
🚧መላው የተቋሙ አመራርና ሰራተኞች እንኳን ለዚህ ስኬት አበቃችሁ::
@etconp
Ethio Construction Engineering via @like
#6. Taipei 101 ➪ Height :- 509.2 meters ➪ Floor above the ground:- 101 ➪ Floor below the ground:- 5 ➪ Floor area :- 412,500 m² ➪ Number of elevator:- 61 ➪ Speed of elevator:- 38 miles per hour ➪ structural system:- core (composite) ➪ Architect:- C.Y.…
#7. International Commerce Centre (ICC)
➪ Height :- 484.0 meters
➪ floor above the ground:- 108
➪ floor below the ground:- 4
➪ number of story :- 113
➪ number of elevators:- 83
➪ elevator speed :- 9 m/s
➪ floor area :- 274,064 m²
➪ structural system:- reinforced-concrete central core and an eight-mega-column
➪ architect :- Kohn Pedersen Fox Associates
➪ structural engineer:- Arup
➪ contractor :- Sanfield Building Contractors Limited
➪ owner :- Sun Hung Kai Properties
➪ construction started:- 2002
➪ completed :- 2010
➪ cost :- $3.85 billion
West Kowloon ,Hong Kong 🇭🇰
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
➪ Height :- 484.0 meters
➪ floor above the ground:- 108
➪ floor below the ground:- 4
➪ number of story :- 113
➪ number of elevators:- 83
➪ elevator speed :- 9 m/s
➪ floor area :- 274,064 m²
➪ structural system:- reinforced-concrete central core and an eight-mega-column
➪ architect :- Kohn Pedersen Fox Associates
➪ structural engineer:- Arup
➪ contractor :- Sanfield Building Contractors Limited
➪ owner :- Sun Hung Kai Properties
➪ construction started:- 2002
➪ completed :- 2010
➪ cost :- $3.85 billion
West Kowloon ,Hong Kong 🇭🇰
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
👉Why is asphalt used for roads? Why is it better than concrete?
.
▶️This is usually a matter of cost and the type of vehicles that use the roadway.
▶️Concrete is more expensive than asphalt, but has a longer life.
▶️It is also a matter of construct ability and the ability to get production.
▶️Trucks generally use the right lane.
*The concrete can tolerate the loading of heavy trucks much longer than asphalt.
.
▶️The concrete is typically reinforced, which lengthens the life of the pavement.
.
🚧It is becoming more and more common to use concrete at intersections. This is an area with lots of turning movements, starting and stopping, and, interestingly, where vehicles drip lots of fluids onto the pavement. These fluids tend to reduce the life of asphalt.
*This is actually one very important reason that use see bus stops with concrete pads.
*Concrete does not have the same reaction to these fluids.
*Due to concrete’s durability, it is used at these locations.
🚧On rural roads where there are lots of driveways and approaches, and where the road may be on rolling terrain, it makes more sense to use asphalt because you have to pay special attention to the driveways and approaches.
.
🚧There are also different noise levels between concrete and asphalt. Some types of asphalt absorb the sound better than other asphalt, but asphalt, in general, is quieter than concrete.
🚧Some concrete pavement has lines in it, called tining.
*We used to tine across the roadway, perpendicular to the direction of travel.
.
🚧This proved to help drainage, but was very noisy.
*Now, they tine in the direction of travel, except on bridges.
*This is much quieter.
A road without tining is noisier than both.
*This is an important consideration when noise is a concern.
.
🚧Concrete can be place almost any time of the year.
*If it is too cold, it can be heated.
*This isn’t feasible for long distances.
It would require a lot of blankets.
*Asphalt can only be placed in warm weather, if you want to get any significant quantities down.
Generally, the temperature must be at least 50 degrees and rising to place asphalt.
*Typically, the oil isn’t even available in the winter. Cold patch is often used for small areas of asphalt paving in the colder months.
.
🚧Incidentally, you actually don’t have to wait 28 days to allow traffic onto concrete pavement.
*In order to expedite construction, they want to get traffic on it as soon as possible, so you can pave other areas.
*Usually, the contractor will use a mix design that reaches the minimum strength rather quickly.
As long as it has the required minimum strength of 3500 psi, small vehicles can get on the concrete.
🚧The strength must be 4000 psi when all traffic is allowed on it.
*We either break concrete cylinders or use data loggers to determine if strength has been reached.
*Usually, the concrete saw cutting trucks get onto the concrete within a couple of days.
*Concrete has to be cut in sections to control cracking.
*Then they seal the joint with a hot asphalt sealant. Traffic may be allowed onto the pavement within a week or so.
@etconp
.
▶️This is usually a matter of cost and the type of vehicles that use the roadway.
▶️Concrete is more expensive than asphalt, but has a longer life.
▶️It is also a matter of construct ability and the ability to get production.
▶️Trucks generally use the right lane.
*The concrete can tolerate the loading of heavy trucks much longer than asphalt.
.
▶️The concrete is typically reinforced, which lengthens the life of the pavement.
.
🚧It is becoming more and more common to use concrete at intersections. This is an area with lots of turning movements, starting and stopping, and, interestingly, where vehicles drip lots of fluids onto the pavement. These fluids tend to reduce the life of asphalt.
*This is actually one very important reason that use see bus stops with concrete pads.
*Concrete does not have the same reaction to these fluids.
*Due to concrete’s durability, it is used at these locations.
🚧On rural roads where there are lots of driveways and approaches, and where the road may be on rolling terrain, it makes more sense to use asphalt because you have to pay special attention to the driveways and approaches.
.
🚧There are also different noise levels between concrete and asphalt. Some types of asphalt absorb the sound better than other asphalt, but asphalt, in general, is quieter than concrete.
🚧Some concrete pavement has lines in it, called tining.
*We used to tine across the roadway, perpendicular to the direction of travel.
.
🚧This proved to help drainage, but was very noisy.
*Now, they tine in the direction of travel, except on bridges.
*This is much quieter.
A road without tining is noisier than both.
*This is an important consideration when noise is a concern.
.
🚧Concrete can be place almost any time of the year.
*If it is too cold, it can be heated.
*This isn’t feasible for long distances.
It would require a lot of blankets.
*Asphalt can only be placed in warm weather, if you want to get any significant quantities down.
Generally, the temperature must be at least 50 degrees and rising to place asphalt.
*Typically, the oil isn’t even available in the winter. Cold patch is often used for small areas of asphalt paving in the colder months.
.
🚧Incidentally, you actually don’t have to wait 28 days to allow traffic onto concrete pavement.
*In order to expedite construction, they want to get traffic on it as soon as possible, so you can pave other areas.
*Usually, the contractor will use a mix design that reaches the minimum strength rather quickly.
As long as it has the required minimum strength of 3500 psi, small vehicles can get on the concrete.
🚧The strength must be 4000 psi when all traffic is allowed on it.
*We either break concrete cylinders or use data loggers to determine if strength has been reached.
*Usually, the concrete saw cutting trucks get onto the concrete within a couple of days.
*Concrete has to be cut in sections to control cracking.
*Then they seal the joint with a hot asphalt sealant. Traffic may be allowed onto the pavement within a week or so.
@etconp
Ethio Construction Engineering via @like
#7. International Commerce Centre (ICC) ➪ Height :- 484.0 meters ➪ floor above the ground:- 108 ➪ floor below the ground:- 4 ➪ number of story :- 113 ➪ number of elevators:- 83 ➪ elevator speed :- 9 m/s ➪ floor area :- 274,064 m² ➪ structural system:…
#8. Lakhta Center
➪ Height:- 462 meters
➪ Floor above the ground:- 87
➪ Floor below the ground:- 3
➪ Number of story:- 91
➪ Number of elevator:- 40
➪ Elevator speed:- 8m/s
➪ Floor area :- 143,400 m²
➪ Structural system:- Core: Reinforced Concrete Columns: Concrete Encased Steel Floor Spanning: Steel
➪ Architect :- RMJM
➪ structural engineer:- Gorproject, Inforceproject
➪ contractor :- Rönesans Holding
➪ cost :- $1.77billion
➪ owner:- Gazprom Neft
➪ construction started :- 2012
➪ completed:- 2019
Lakhta, Saint Petersburg, Russia 🇷🇺
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
➪ Height:- 462 meters
➪ Floor above the ground:- 87
➪ Floor below the ground:- 3
➪ Number of story:- 91
➪ Number of elevator:- 40
➪ Elevator speed:- 8m/s
➪ Floor area :- 143,400 m²
➪ Structural system:- Core: Reinforced Concrete Columns: Concrete Encased Steel Floor Spanning: Steel
➪ Architect :- RMJM
➪ structural engineer:- Gorproject, Inforceproject
➪ contractor :- Rönesans Holding
➪ cost :- $1.77billion
➪ owner:- Gazprom Neft
➪ construction started :- 2012
➪ completed:- 2019
Lakhta, Saint Petersburg, Russia 🇷🇺
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
👉What is the definition of the slenderness ratio of a column? What is its importance?
.
📌Simplest architect’s definition : ”How long and thin is something , basically ratio of its length to its width”
.
🚧Slender is something that is long and thin Also, If something’s long and thin(slender), it has “high” length as compared to the width and hence high slenderness ratio and hence high chance of buckling.
.
🚧Something that’s slender goes sideways when pushed. (Going sideways is called buckling).
*From now on I will refer swaying sideways as Buckling.
.
🚧Something that’s not so slender do not buckle, instead that thing just gets crushed. (It is also called crushing failure).
.
🚧Now. Engineers were confused They wanted to know which column would buckle. Why? Because the column which buckle are designed in a different way and which gets crushed are designed in a little different manner.
*So its important to know which column would buckle beforehand. Now they knew that there is some relationship between being thin and buckling sideways
*So, they somewhat modified the architectural definition of the slenderness according to their needs which would tell if the column will get buckle or not And that term my friend is called slenderness ratio (measurement of how thin and long a column is).
🚧Notice that engineer’s definition focuses on buckling and not on the dimensions of the member. Lets say, if something is long and thin, and it does not buckle means it is not slender according to engineers.
➡️Now, how is it if something is long and thin, and it does not buckle?
🚧The answer lies in how you support the column. If you support and restrain it very well from both sides(say fixed supports both sides), it will be hard to buckle for the same load you’ve used before. If you restrain it less(say one way fixed and other way pinned), it will be relatively easy. So, to accommodate that effect, we apply a restrain factor to length which gives us the effective length.
🚧So, basically i lied, that is, the column would buckle for sure, but at a greater load.
🚧We know now that Engineers definition of the slenderness ratio (basically tendency to buckle) depends not on physical length but instead on effective length unlike our architect’s definition.
🚧Effective length also tells us the length under which effective bending is happening.
@etconp
.
📌Simplest architect’s definition : ”How long and thin is something , basically ratio of its length to its width”
.
🚧Slender is something that is long and thin Also, If something’s long and thin(slender), it has “high” length as compared to the width and hence high slenderness ratio and hence high chance of buckling.
.
🚧Something that’s slender goes sideways when pushed. (Going sideways is called buckling).
*From now on I will refer swaying sideways as Buckling.
.
🚧Something that’s not so slender do not buckle, instead that thing just gets crushed. (It is also called crushing failure).
.
🚧Now. Engineers were confused They wanted to know which column would buckle. Why? Because the column which buckle are designed in a different way and which gets crushed are designed in a little different manner.
*So its important to know which column would buckle beforehand. Now they knew that there is some relationship between being thin and buckling sideways
*So, they somewhat modified the architectural definition of the slenderness according to their needs which would tell if the column will get buckle or not And that term my friend is called slenderness ratio (measurement of how thin and long a column is).
🚧Notice that engineer’s definition focuses on buckling and not on the dimensions of the member. Lets say, if something is long and thin, and it does not buckle means it is not slender according to engineers.
➡️Now, how is it if something is long and thin, and it does not buckle?
🚧The answer lies in how you support the column. If you support and restrain it very well from both sides(say fixed supports both sides), it will be hard to buckle for the same load you’ve used before. If you restrain it less(say one way fixed and other way pinned), it will be relatively easy. So, to accommodate that effect, we apply a restrain factor to length which gives us the effective length.
🚧So, basically i lied, that is, the column would buckle for sure, but at a greater load.
🚧We know now that Engineers definition of the slenderness ratio (basically tendency to buckle) depends not on physical length but instead on effective length unlike our architect’s definition.
🚧Effective length also tells us the length under which effective bending is happening.
@etconp
👍1
Ethio Construction Engineering
Types of Dam and their description Can you name the components of a dam from A up to K ? If more than 10 members participate In Our Discussion Group we will post the answer @COTMp ላይ ተሳተፉ ከ 10 በላይ ቤተሰቦች ከተሳተፋችሁ መልሱን እንለቃለን። @etconp
Answer for this question 👆🏾👆🏾
A. Crest : the top of the dam , in some cases used to provide a roadway or walkway over the dam.
.
B. Heel: the part of the damn in contact with ground on the upstream slide.
C. Toe : the part of the damn in contact with the ground on the downstream side.
.
D. Foundation : excavated surface or undistributed material Used to transfer load from the superstructure to the ground.
.
E. Spillway: structure that provides for controlled conveyance of water flows downstream of the dam.
.
F. Gallery :- small room within large dams used to monitor the performance of the dam,with a drain floor for water seepage.
.
G. Outlet: also called sluiceway , used to release water from the reservoir for water supply, irrigation and hydro power.
.
H. Blowoff: opening within the dam near the base to drain the reservoir.
.
I. Freeboard: vertical distance between the spillway level and the crest of the dam.
.
J. Pervious material: substance that allow water to pass through.
.
K. Impervious material: substances that do not allow water pass through.
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
A. Crest : the top of the dam , in some cases used to provide a roadway or walkway over the dam.
.
B. Heel: the part of the damn in contact with ground on the upstream slide.
C. Toe : the part of the damn in contact with the ground on the downstream side.
.
D. Foundation : excavated surface or undistributed material Used to transfer load from the superstructure to the ground.
.
E. Spillway: structure that provides for controlled conveyance of water flows downstream of the dam.
.
F. Gallery :- small room within large dams used to monitor the performance of the dam,with a drain floor for water seepage.
.
G. Outlet: also called sluiceway , used to release water from the reservoir for water supply, irrigation and hydro power.
.
H. Blowoff: opening within the dam near the base to drain the reservoir.
.
I. Freeboard: vertical distance between the spillway level and the crest of the dam.
.
J. Pervious material: substance that allow water to pass through.
.
K. Impervious material: substances that do not allow water pass through.
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
👉what is Shear wall
▶️Shear wall is a structural member in a reinforced concrete framed structure to resist lateral forces such as wind forces.
*Shear walls are generally used in high rise buildings subject to lateral wind.
.
📌Advantage of Shear Wall
▶️Shear walls provide large strength and stiffness to buildings in the direction of their orientation, which significantly reduces lateral sway of the building and thereby reduces damage to structure and its contents.
*Since shear walls carry large horizontal earthquake forces, the overturning effects on them are large.
@etconp
▶️Shear wall is a structural member in a reinforced concrete framed structure to resist lateral forces such as wind forces.
*Shear walls are generally used in high rise buildings subject to lateral wind.
.
📌Advantage of Shear Wall
▶️Shear walls provide large strength and stiffness to buildings in the direction of their orientation, which significantly reduces lateral sway of the building and thereby reduces damage to structure and its contents.
*Since shear walls carry large horizontal earthquake forces, the overturning effects on them are large.
@etconp
Ethio Construction Engineering
👉what is Shear wall ▶️Shear wall is a structural member in a reinforced concrete framed structure to resist lateral forces such as wind forces. *Shear walls are generally used in high rise buildings subject to lateral wind. . 📌Advantage of Shear Wall ▶️Shear…
👉ስለ SHEAR WALL እንንገራቹ
.
➡SHEAR WALLማለት የአግዳሚ ወይም horizontal load ተፅዕኖዎችን የሚቋቋሙልን ግድግዳዎች ናቸው፡፡
⏩ሺር ዎል የተባሉበትም ምክንያት የመሬት መንቀጥቀጥ በጎን አቅጣጫ ስለሚመጣና ዎሎቹ ላይ የሺር ተፅዕኖ ስለሚያሳድር ነው ( ሺር በ Thickness ትይዩ በሆነ አቅጣጫ እንደሚመጣ ልብ ማለት ይገባል፡፡
⏩Horizontal force የሆኑት Earth Quake እና Wind Load በዎሎቹ Thickness ትይዩ በሆነ አቅጣጫ ነው የሚመጡት::
.
⏩ሺር ዎሎች በትክክል ዲዛይን ተደርገው ትክክለኛ ቦታቸው ላይ ካልተቀመጡ ከጥቅማቸው ይልቅ ጉዳታቸው እጅግ ብዙ ነው ይህም ህንጻውን አፍራሽ ግብረ ሃይል ናቸው - ስለዚህ እንዴት ማስቀመጥ እንዳለብን ቀጥለን እንመልከት👇
.
1) አንድ ህንፃ ላይ የሚፈቀደው ትንሹ የሺር ዎል ብዛት ሶስት ነው ቢያንስ-ሶስት
.
2) ሶስት ወይም ከዛ በላይ ሺር ዎሎች ካሉን የዎሎቹ አክሲሶች አንድ ነጥብ ላይ መገናኘት የለባቸውም::
3) ትይዩ እንዲሆኑ የሚፈቀደው ቢበዛ ለሁለት ዎሎች ነው፡፡
*ሺር ዎሎች ከኮለንና ቢም ይልቅ የህንፃውን ጥንካሬ ወይም Stiffness ወደ ራሳቸው የመጎተት ከፍተኛ አቅም አላቸው ፤ እንደሚታወቀው የመሬት መንቀጥቀጥ act የሚያደርገው center of Mass ላይ ነው ፤ የመሬት መንቀጥቀጥን በተሻለ ሁኔታ ለመቋቋም ደግሞ የህንፃው ጥንካሬ ወይም Center of Stiffness የሚገኝበት ነጥብና የህንጻው Center of Mass የሚገኝበት ነጥብ በተቻለ መጠን መቀራረብ አለበት ፤ እናም ስናጠቃልለው - በትክክል ያልተቀመጡ ሺር ዎሎች የህንጻውን Center of Stiffness ወይም ጥንካሬ ወደራሳቸው ሲጎትቱት ከ Center of Mass እንዲርቅ ያደርጉታል በመራራቃቸው የተነሳ እሽክርክሪት ፎርስ ወይም Torsion ይፈጠራል ስለዚህ Torsion ህንፃው እንዲፈርስ ያደርገዋል፡፡
▶የኒውተን ሶስተኛ ህግ ምን ይላል... “The forces of action and reaction between interacting bodies are equal in magnitude, opposite in direction and COLLINEAR” – ሁለት ፎርሶች Collinear force የሚባሉት ደግሞ በአንድ መስመር act ሲያደርጉ ነው፡፡
🚧የመሬት መንቀጥቀጡ CM ላይ Act ሲያደርግ CS ደግሞ በሺር ዎሎቹ ስለተጎተተ ሌላ ቦታ React ያደርጋል በዚህ የተነሳ Collinear force አይደሉም ማለት ነው ስለዚህ Newton Third Law ውድቅ ሆነ ማለት ነው፡፡
*Action እና Reaction በመጠንም ይሁን በአቅጣጫ እኩል ስለማይሆኑ ትርፍ balance ያልተደረገ force ይፈጠራል - Newton First Lawን ታሳቢ በማድረግ ህንፃው Equilibrium ላይ አይሆንም ማለት ነው፡፡
*የኒውተን ሁለተኛ ህግስ ማን አለው የሚል ሰው ካለ - በመሬት መንቀጥቀጥ ሳቢያ የሚፈጠረው ፎርስ ማለት የህንፃው ክብደት ሲባዛ በእንቅጥቃጤው የሚፈጠር Acceleration ነው - ይህም
Newton Second Law ነው::
.
⏩ስናጠቃልለው ከጥፋት ለመዳን ሺር ዎልን ስናስቀምጥ ከላይ ያሉትን ነጥቦች ተግባራዊ ማድረግ አለብን፡፡
@etconp
.
➡SHEAR WALLማለት የአግዳሚ ወይም horizontal load ተፅዕኖዎችን የሚቋቋሙልን ግድግዳዎች ናቸው፡፡
⏩ሺር ዎል የተባሉበትም ምክንያት የመሬት መንቀጥቀጥ በጎን አቅጣጫ ስለሚመጣና ዎሎቹ ላይ የሺር ተፅዕኖ ስለሚያሳድር ነው ( ሺር በ Thickness ትይዩ በሆነ አቅጣጫ እንደሚመጣ ልብ ማለት ይገባል፡፡
⏩Horizontal force የሆኑት Earth Quake እና Wind Load በዎሎቹ Thickness ትይዩ በሆነ አቅጣጫ ነው የሚመጡት::
.
⏩ሺር ዎሎች በትክክል ዲዛይን ተደርገው ትክክለኛ ቦታቸው ላይ ካልተቀመጡ ከጥቅማቸው ይልቅ ጉዳታቸው እጅግ ብዙ ነው ይህም ህንጻውን አፍራሽ ግብረ ሃይል ናቸው - ስለዚህ እንዴት ማስቀመጥ እንዳለብን ቀጥለን እንመልከት👇
.
1) አንድ ህንፃ ላይ የሚፈቀደው ትንሹ የሺር ዎል ብዛት ሶስት ነው ቢያንስ-ሶስት
.
2) ሶስት ወይም ከዛ በላይ ሺር ዎሎች ካሉን የዎሎቹ አክሲሶች አንድ ነጥብ ላይ መገናኘት የለባቸውም::
3) ትይዩ እንዲሆኑ የሚፈቀደው ቢበዛ ለሁለት ዎሎች ነው፡፡
*ሺር ዎሎች ከኮለንና ቢም ይልቅ የህንፃውን ጥንካሬ ወይም Stiffness ወደ ራሳቸው የመጎተት ከፍተኛ አቅም አላቸው ፤ እንደሚታወቀው የመሬት መንቀጥቀጥ act የሚያደርገው center of Mass ላይ ነው ፤ የመሬት መንቀጥቀጥን በተሻለ ሁኔታ ለመቋቋም ደግሞ የህንፃው ጥንካሬ ወይም Center of Stiffness የሚገኝበት ነጥብና የህንጻው Center of Mass የሚገኝበት ነጥብ በተቻለ መጠን መቀራረብ አለበት ፤ እናም ስናጠቃልለው - በትክክል ያልተቀመጡ ሺር ዎሎች የህንጻውን Center of Stiffness ወይም ጥንካሬ ወደራሳቸው ሲጎትቱት ከ Center of Mass እንዲርቅ ያደርጉታል በመራራቃቸው የተነሳ እሽክርክሪት ፎርስ ወይም Torsion ይፈጠራል ስለዚህ Torsion ህንፃው እንዲፈርስ ያደርገዋል፡፡
▶የኒውተን ሶስተኛ ህግ ምን ይላል... “The forces of action and reaction between interacting bodies are equal in magnitude, opposite in direction and COLLINEAR” – ሁለት ፎርሶች Collinear force የሚባሉት ደግሞ በአንድ መስመር act ሲያደርጉ ነው፡፡
🚧የመሬት መንቀጥቀጡ CM ላይ Act ሲያደርግ CS ደግሞ በሺር ዎሎቹ ስለተጎተተ ሌላ ቦታ React ያደርጋል በዚህ የተነሳ Collinear force አይደሉም ማለት ነው ስለዚህ Newton Third Law ውድቅ ሆነ ማለት ነው፡፡
*Action እና Reaction በመጠንም ይሁን በአቅጣጫ እኩል ስለማይሆኑ ትርፍ balance ያልተደረገ force ይፈጠራል - Newton First Lawን ታሳቢ በማድረግ ህንፃው Equilibrium ላይ አይሆንም ማለት ነው፡፡
*የኒውተን ሁለተኛ ህግስ ማን አለው የሚል ሰው ካለ - በመሬት መንቀጥቀጥ ሳቢያ የሚፈጠረው ፎርስ ማለት የህንፃው ክብደት ሲባዛ በእንቅጥቃጤው የሚፈጠር Acceleration ነው - ይህም
Newton Second Law ነው::
.
⏩ስናጠቃልለው ከጥፋት ለመዳን ሺር ዎልን ስናስቀምጥ ከላይ ያሉትን ነጥቦች ተግባራዊ ማድረግ አለብን፡፡
@etconp
👍1
Ethio Construction Engineering via @like
#8. Lakhta Center ➪ Height:- 462 meters ➪ Floor above the ground:- 87 ➪ Floor below the ground:- 3 ➪ Number of story:- 91 ➪ Number of elevator:- 40 ➪ Elevator speed:- 8m/s ➪ Floor area :- 143,400 m² ➪ Structural system:- Core: Reinforced Concrete Columns:…
#9. Landmark 81
➪ Height:- 461.2 meters
➪ floor above the ground:- 81
➪ floor below the ground:- 3
➪ Number of story:- 85
➪ Number of elevator:- 29
➪ elevator speed :- 8m/s
➪ Ground floor area:- 249,000m²
➪ structural system:- Core: Reinforced Concrete
* Columns: Concrete Encased Steel
* Floor Spanning: Reinforced Concrete
➪ Architect :- Atkins
➪ structural engineer:- Arup
➪ main contractor :- Mace Limited; Coteccons Group
➪ owner:- Vingroup
➪ construction started:- 2015
➪ completion:- 2018
➪ project cost :- $1.5 billion
Ho Chi Minh, Vietnam 🇻🇳
Telegram:- @etconp
Instagram:- https://www.instagram.com/etconp
➪ Height:- 461.2 meters
➪ floor above the ground:- 81
➪ floor below the ground:- 3
➪ Number of story:- 85
➪ Number of elevator:- 29
➪ elevator speed :- 8m/s
➪ Ground floor area:- 249,000m²
➪ structural system:- Core: Reinforced Concrete
* Columns: Concrete Encased Steel
* Floor Spanning: Reinforced Concrete
➪ Architect :- Atkins
➪ structural engineer:- Arup
➪ main contractor :- Mace Limited; Coteccons Group
➪ owner:- Vingroup
➪ construction started:- 2015
➪ completion:- 2018
➪ project cost :- $1.5 billion
Ho Chi Minh, Vietnam 🇻🇳