๐Ÿ‘‰Project Control Techniques for Successful Project Management

๐Ÿ’ซIn the world of project management, having the right control techniques can make all the difference between a project that meets goals and one that veers off track. Here are some of the top techniques to ensure projects stay on schedule, within budget, and aligned with quality standards:

1๏ธโƒฃ Earned Value Management (EVM): Evaluate project performance by comparing planned work vs. actual progress and costs.

2๏ธโƒฃ Critical Path Method (CPM): Identify the essential tasks impacting project timelines to prioritize resources effectively.

3๏ธโƒฃ Gantt Charts: Use visual timelines to track task progress and spot any delays.

4๏ธโƒฃ Work Breakdown Structure (WBS): Break down projects into manageable tasks for clear assignments and better cost estimation.

5๏ธโƒฃ Risk Management: Proactively identify and manage risks to mitigate issues before they impact the project.

6๏ธโƒฃ Change Control: Keep the project aligned by managing scope, schedule, and budget changes systematically.

7๏ธโƒฃ Cost Control: Monitor expenses and adjust to prevent budget overruns with variance analysis and forecasting.

8๏ธโƒฃ Quality Control: Regular testing, audits, and inspections to ensure deliverables meet defined standards.

9๏ธโƒฃ Resource Allocation & Leveling: Optimize resource usage to avoid overload and maintain efficiency.

๐Ÿ”Ÿ Milestone Tracking: Track key milestones to ensure significant project stages are completed on time.

Project control techniques are essential for staying on track and delivering value. By combining these methods, project managers can make informed adjustments and ensure project success!

Via Yonatan Tadesse PMP

@etconp
๐Ÿ‘24๐Ÿ‘3
When the bearing capacity of the soil is poor and the intensity of traffic is high, an additional layer is provided between the soling and sub - grade. This addition
layer is called:
Anonymous Quiz
21%
Sub - grade
46%
Sub - base
10%
Base
24%
Wearing course
โค16๐Ÿ‘4
It is the property of the material or a structure indicating the extent to which it can deform beyond the limit of yield deformation before failure or fracture is
termed as:
Anonymous Quiz
67%
Ductility
15%
Brittleness
14%
Slenderness ratio
4%
Aspect ratio
๐Ÿ‘11โค3
The cement chosen to build concrete structure in the vicinity of sea water is
Anonymous Quiz
18%
Quick setting cement
32%
Rapid hardening cement
8%
Low heat cement
42%
Sulphate resisting cement
๐Ÿ‘8๐Ÿ‘4โค2
An imaginary line lying throughout the surface of ground and preserving a constant inclination to the horizontal is known as
Anonymous Quiz
61%
Contour line
11%
Level line
20%
Contour gradient
8%
Horizontal equivalent
โค6๐Ÿ‘4๐Ÿ‘2๐ŸŽ‰1
A soil has an average particle size of 0.2 mm, it is predominantly:
Anonymous Quiz
35%
Gravel
31%
Sand
19%
Silt
14%
Clay
๐Ÿ‘20โค9
๐Ÿ‘‰แ‰ แŠ แ‹ฒแˆต แŠ แ‰ แ‰ฃ แŠจแแ‰ฐแŠ› แ‹จแŠฅแŒแˆจแŠžแ‰ฝ แ‹แ‹แ‹แˆญ แŠจแˆšแ‰ณแ‹ญแ‰ฃแ‰ธแ‹ แ‰ฆแ‰ณแ‹Žแ‰ฝ แˆ˜แŠซแŠจแˆ แ‹จแˆ˜แŒˆแŠ“แŠ› แŠ แ‹ฐแ‰ฃแ‰ฃแ‹ญ แ‰ แ‰€แ‹ณแˆšแАแ‰ต แ‹ญแŒ แ‰€แˆณแˆแข

๐Ÿšงแ‰ แ‹šแˆ… แŠ แ‹ฐแ‰ฃแ‰ฃแ‹ญ แ‰ แ‰ฐแˆˆแ‹ญ แ‰ แˆ แˆซแ‰ฐแŠ› แˆ˜แŒแ‰ขแ‹ซแŠ“ แˆ˜แ‹แŒชแ‹ซ แˆฐแŠ แ‰ถแ‰ฝ แ‰ แŠ แ‹ฐแ‰ฃแ‰ฃแ‹ฉ แˆˆแˆ˜แ‰ฐแˆ‹แˆˆแ แŠ แ‹ณแŒ‹แ‰ฝ แ‹จแˆšแˆ†แŠ‘แ‰ฃแ‰ธแ‹ แŒŠแ‹œแ‹ซแ‰ต แ‰ฅแ‹™ แАแ‹แข

๐Ÿ’ซแ‹ญแˆ…แŠ•แŠ• แ‰ฝแŒแˆญ แˆˆแˆ˜แ‰…แˆจแ แˆ˜แŒˆแŠ“แŠ›แŠ• แŠฅแŠ“ แ‹จแŠ แŠซแ‰ฃแ‰ขแ‹แŠ• แˆ˜แˆแŠญแŠ• แ‹จแˆšแ‰€แ‹ญแˆญ แ‹จแŠฅแŒแˆจแŠžแ‰ฝ แ‹จแˆ˜แˆฌแ‰ต แ‹แˆตแŒฅ แˆˆแ‹แˆตแŒฅ แˆ˜แˆธแŒ‹แŒˆแˆชแ‹ซ แˆ˜แŠ•แŒˆแ‹ต แŒแŠ•แ‰ฃแ‰ณ แŠฅแ‹จแ‰ฐแŠซแˆ„แ‹ฐ แАแ‹แข

@etconp
๐Ÿ‘15๐Ÿ”ฅ1
Earthquake_Fundamentals_by_Dr_Mesele_Haile__1730610599.pdf
3.6 MB
๐Ÿ‘‰Building Resilience: Earthquake Safety and Design for a Safer Future

๐ŸšงBuilding a Safer Ethiopia: Comprehensive Earthquake Resilience Through Engineering and Public Safety (October 29,2024) Event Slides by Dr. Mesele Haile

๐Ÿ“œ1 out of 8 documents provided by Dr. Mesele

#Earthquake #SeismicDesign #BuildingSafety #Ethiopia #Africa

(Courtesy of  ECC - Ethiopian Construction Works Corporation & Ethiopian Association of Civil Engineers)

Via Yonatan Tadesse PMP

@etconp
๐Ÿ‘18
๐Ÿ‘‰Self-compacting concrete

๐Ÿ’ซSelf-compacting concrete (SCC) is a specialized type of concrete that flows and spreads easily through formwork and around obstructions without the need for mechanical vibration. This is achieved through a careful balance of mix ingredients and the use of superplasticizers.

๐Ÿ—๏ธWhen to Use SCC

โœ”๏ธIn complex structures with dense reinforcement where conventional vibration would be difficult.
โœ”๏ธIn areas where noise reduction is important, such as urban locations.
โœ”๏ธ For elements with intricate shapes or surface textures that could be affected by vibration.
โœ”๏ธLarge construction projects where efficiency and speed are priorities.

๐Ÿ—๏ธAdvantages of SCC

โœ”๏ธImproved Quality and Finish: Provides a superior surface finish and better filling of forms.
โœ”๏ธReduced Labor and Noise: No need for vibration reduces labor costs and construction noise.
โœ”๏ธTime Efficiency: Faster placement reduces project timelines.
โœ”๏ธEnhanced Durability: Better compaction leads to improved strength and durability.
โœ”๏ธVersatility: Suitable for a variety of applications from precast structures to commercial builds.

๐Ÿ“œOverall, SCC enhances the construction process in terms of quality, efficiency, and sustainability.

#Selfcompactingconcrete #siteengineer #Civilengineer #concretetechnology

Via Yonatan Tadesse PMP

@etconp
๐Ÿ‘18โค1
๐Ÿ‘‰Subject : Foundations

๐ŸทFoundations can be shallow or deep, depending on the depth of the soil in which they are built.

๐Ÿ’ซWhat Is Shallow Foundations ??

โญ๏ธANSWER

โบShallow foundations are typically used for low-rise buildings or structures that are wider than they are tall.

๐Ÿ’ซWhat Is Deep foundation??

โญ๏ธANSWER

โบDeep foundations are used for structures that require more than 1.5 meters of depth to transfer their load.

@etconp
๐Ÿ‘13โค4
Intercon Construction Chemicals 
    
๐Ÿ‘‰ Authorized agent of MC (Conmix), Weber and SIMENTEK

โ— Concrete Admixtures
โ— Bonding Agents
โ— Waterproofings
โ— Concrete Repair, Grout   
โ— Tile Adhesive & Tile Joint Fillers 
โ— Wall Putty, Prime Coat, Rush Coat
โ— Quartz, Contextra
โ— Specialized paints (Thermal and Insulation Paints, Street and Playground Paints)
โ— Floor hardener, Epoxy              
โ— Geotextiles, Geo-membranes and other construction chemicals and materials

Tel: 0961955555 or 0961955559
Address: Signal, around signal mall
๐Ÿ‘2๐Ÿ‘1
แ‰ณแˆแˆซแ‰ต  แ•แˆŒแ‰ต แŠฅแŠ“ แŒ„แ‰ฆแˆแ‰ต แŠ แ‰…แˆซแ‰ข

๐Ÿ“Œแ•แˆŒแ‰ตแŠ“ แŒ„แ‰ฆแˆแ‰ต แ‰ แˆแˆˆแŒ‰แ‰ต แŠ แ‹ญแАแ‰ต แ‹จแ‰ฐแ‹˜แŒ‹แŒ€ แŠ แˆˆแŠ•

โœ‚๏ธแˆ‹แˆœแˆซ แˆ˜แ‰แˆจแŒซ แˆ˜แ‰ฅแˆปแŠ“  แˆ›แŒ แŠแ‹ซ แˆ›แˆฝแŠ–แ‰ฝ แŠ แˆ‰แŠ•

๐Ÿ”—แŒแˆฎ (แ‰ถแŠ•แ‹ฒแŠ–) แŒฅแˆญแˆต แŠฅแŠ“แ‰ แŒƒแˆˆแŠ• แŠฅแŠ•แ‹ฒแˆแˆ แŠฅแŠ“แŒฅแ‹แˆˆแŠ•

๐Ÿ“แˆ›แŠ•แŠ›แ‹‰แŠ•แˆ แ‹จแˆžแ‹ฐแŠแŠญ แˆตแˆซแ‹Žแ‰ฝแŠ• แŠฅแŠ•แˆฐแˆซแˆˆแŠ•

๐Ÿ“แŠขแ‰ตแ‹ฎแŒตแ‹ซ แ‹‰แˆตแŒฅ แ‹จแ‰ตแˆ แŠฅแŠ•แˆแŠญแˆŽแ‰ณแˆˆแŠ•

แŠ แ‹ตแˆซแˆปแ‰ฝแŠ•แฆ แ‰.1 แŠ แ‹‰แ‰ถแ‰ฅแˆต แ‰ฐแˆซ(แˆ˜แˆณแˆˆแˆšแ‹ซ)
                    แ‰.2 แˆ˜แˆญแŠซแ‰ถ
                    แ‰.3 แ‰ฐแŠญแˆˆแˆ€แ‹ญแˆ›แŠ–แ‰ต

0904040477
0911016833
๐Ÿ‘4โค1
๐Ÿ‘‰๐‘ช๐’๐’๐’”๐’•๐’“๐’–๐’„๐’•๐’Š๐’๐’ ๐‘ช๐’๐’‚๐’Š๐’Ž๐’” ๐‘ญ๐’๐’“ ๐‘ฝ๐’‚๐’“๐’Š๐’‚๐’•๐’Š๐’๐’ ๐‘ฐ๐’ ๐‘ธ๐’–๐’‚๐’๐’•๐’Š๐’•๐’š

๐ŸทParties may contemplate minor variation in quantity from contract estimate, especially if engineering documents aren't issued โ€œApproved for Construction (AFC)โ€

๐Ÿ’ซEven when AFC drawing issued prior to establishing contract price, change may occur, cause deviation from approved design & significantly increase or decrease required quantity to be installed & contractorโ€™s cost

โบUnder unit price contract contractor typically buy material, add overhead, profit markup & agree to perform work for this unit price

โ–ถ๏ธIf ownerโ€™s estimated quantity is higher than actual quantity, contractor may claim for unrecovered overhead cost & profit

โญ๏ธ๐•๐š๐ฅ๐ฎ๐ž ๐„๐ง๐ ๐ข๐ง๐ž๐ž๐ซ๐ข๐ง๐ 

Owner realize cost saving as result of value engineering, design change, reduce quantity, then request credit from contractor

Contractor might not pass on full saving achieved from ownerโ€™s change, potentially cause dispute with owner who expect larger credit

๐”๐ง๐›๐š๐ฅ๐š๐ง๐œ๐ž๐ ๐๐ซ๐ข๐œ๐ข๐ง๐ 

Contractor take risk with unit price contract tactically apply its overhead & profit % in unbalanced manner to items for which it expects large quantity increases as design matures, thus receiving additional profit layer

Such practice may backfire if โ€œover-pricedโ€ items quantities don't increase or decrease as result of value engineering, thus reduce contractorโ€™s overhead & profit recovery

๐‚๐ก๐š๐ง๐ ๐ž๐ฌ ๐‚๐ฅ๐š๐ฎ๐ฌ๐ž ๐€๐ฌ ๐‘๐ž๐ฆ๐ž๐๐ฒ

-๐•๐š๐ซ๐ข๐š๐ญ๐ข๐จ๐ง ๐ข๐ง ๐„๐ฌ๐ญ๐ข๐ฆ๐š๐ญ๐ž๐ ๐๐ฎ๐š๐ง๐ญ๐ข๐ญ๐ฒ "๐•๐„๐" ๐‚๐ฅ๐š๐ฎ๐ฌ๐ž
Equitably assign risk of increase or decrease in estimated quantity result from information or conditions not reasonably apparent to parties when they enter into contract to prevent harmful losses

Contract include provision, after given variation % (e.g 15-25 %), there can be adjustment to unit price

Technical specs & drawings describe what work is payable

-๐ƒ๐ข๐Ÿ๐Ÿ๐ž๐ซ๐ข๐ง๐  ๐’๐ข๐ญ๐ž ๐‚๐จ๐ง๐๐ข๐ญ๐ข๐จ๐ง๐ฌ ๐‚๐ฅ๐š๐ฎ๐ฌ๐ž

โ€œDiffering Site Conditionsโ€ clause override โ€œVEQโ€ clause when:
1)Actual quantities clearly exceed contemplation of parties; &

2)Cost of doing extra work greatly differs from stated unit-price because of factors not foreseen by either party

โ€œDiffering Site Conditionsโ€ clause may also prevail over use of โ€œVEQโ€ clause:
1)Ownerโ€™s estimate found to be prepared negligently; &

2)Owner fail to disclose โ€œsuperior knowledgeโ€ result quantity overrun

Contractor must maintain record of all cost associated with change or extra work

Advantage of recovery under โ€œDiffering Site Conditionsโ€ to contractor isn't limited to unit price but can recover actual cost plus reasonable overhead & profit

๐๐จ๐ญ๐ข๐œ๐ž ๐‘๐ž๐ช๐ฎ๐ข๐ซ๐ž๐ฆ๐ž๐ง๐ญ

VEQ clause usually don't specify contractor to notify owner in advance if actual quantity to exceed estimated quantity

The only notice requirement imposed by VEQ clause is related to requests for (EOT)

Via Yonatan Tadesse PMP

@etconp
๐Ÿ‘19โค2๐Ÿ‘1
๐Ÿ‘‰TYPES OF DRAWINGS USED IN BUILDING CONSTRUCTION

๐ŸšงDrawings are the most important things we need to start any construction project.

๐ŸทThere are different types of drawings for different purposes.

๐Ÿ“œIn this article, we will discuss different types of construction drawings (also known as working drawing)

โบConstruction drawings provide detail measurements and clear section of every building parts.

โบAfter reviewing, the drawings are justified and modified and finally approved for construction.

๐Ÿ’ซThe different types of construction drawings are listed below.

1) ARCHITECTURAL DRAWING

โบThis type of drawing provides complete view of a building. It demonstrates the location of the building and all building parts where they will be placed.

โบThere are different types of architectural drawings
with different names such as plan, elevation, section
etc.

2) STRUCTURAL DRAWING

โ–ถ๏ธAs the name suggests, this type of drawing provides information about structure, like strength of different structural elements, structural materials, grade, size and placement of reinforcement etc.

3) ELECTRICAL DRAWING

โบThis type of drawings provide the details and location of electrical wiring, fixtures, substation etc.

โ–ถ๏ธThe electrical load calculation is also given in the drawing.

4) PLUMBING AND SANITARY DRAWINGS

โบThese drawings give the location of sanitary, piping
for water supply system, fixture, and the process to
connect every fixture etc.

@etconp
๐Ÿ‘33โค3
Earthquake_slide_02_1730726722.pdf
8 MB
Building Resilience: Earthquake Safety and Design for a Safer Future

Event Slides by Dr. Mesele Haile

2 out of 8 documents provided by Dr. Mesele

#Earthquake #SeismicDesign #BuildingSafety #Ethiopia #Africa

ECC - Ethiopian Construction Works Corporation
Ethiopian Association of Civil Engineers

@etconp
Earthquake_Slides_03__1730726877.pdf
2.4 MB
Building Resilience: Earthquake Safety and Design for a Safer Future

Event Slides by Dr. Mesele Haile

The third Slide, out of 8 documents provided by Dr. Mesele

#Earthquake #SeismicDesign #BuildingSafety #Ethiopia #Africa