๐COMMON CONCRETE PROBLEMS AND THEIR
PREVENTION @COTMp
.
โฉThere are many problems we might be facing during and after concreting.
*To produce high quality
concrete we must take some precautions to avoid
those common problems during concreting. In this
article, we will discuss on common concrete
problems and how to prevent them.
A) BLEEDING:
Bleeding refers to as a tendency of water to appear on the top surface of concrete after finishing. Due to bleeding some measure of water (with sand particles and other cementing materials) appears at the surface of the concrete.
*Following precautions should be taken to reduce
bleeding in concrete.
1. Design the mix appropriately.
2. Include least water content in the mix.
3. Use greater amount of cement content.
4. Use greater amount of fine particles.
5. Utilize a little measure of air entraining
admixture.
B) SEGREGATION:
Segregation means separation of coarse aggregates from the concrete surface due to poor compaction.
It is generally seen in the plastic stage of concrete.
As a result honeycomb, laitance, scaling, porous
layer, bond failure etc. can be formed in concrete.
Following precautions should be adopted to prevent segregation in concrete.
1. Design the mix appropriately.
2. Never use excessive water content.
3. Take care of handling, placing, and proper
compaction of concrete.
4. Do not allow the concrete to be dropped from more heights.
5. Use air entraining admixture.
6. Keep the formwork to be watertight.
C) LAITANCE:
The appearance of cement-sand particles on the
surface of freshly placed concrete is known as
laitance. It is mainly occurred due to the bad effect of bleeding and segregation of concrete. The bond between subsequent layers of concrete becomes
weaker and as a result, laitance is developed.
Following precautions can be taken to stop the
occurrence of laitance in concrete.
1. Clay, dust, silt content etc should be removed
before mixing the concrete.
2. Water-cement ratio should be maintained
properly.
3. Water should not be sprayed on the concrete
surface during finishing work.
4. Use well graded fine aggregates in the mix.
5. Add little amount of water reducing admixture in the concrete mix.
D) SCALING:
Scaling is the physical deterioration of concrete in
which the surface layer of concrete broke down,
pitted or flaked away. Due to this effect concrete
surface becomes worse. Scaling can be prevented
by taking same precautions adopted for laitance.
E) PLASTIC SHRINKAGE CRACKS:
When the evaporation rate of water mixed in the
concrete is greater than the bleed water of concrete,
plastic shrinkage cracks are developed on the
surface of the concrete. Basically, this type of
cracks occurs in very hot climate.
F) DUSTING:
Dusting can be prevented by taking following
precautions.
1. Maintain a suitable water/cement ratio in the
concrete.
2. Utilize dust free aggregates in the mix.
3. Guarantee appropriate hydration of concrete.
4. Avoid early surface finishing of concrete.
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
PREVENTION @COTMp
.
โฉThere are many problems we might be facing during and after concreting.
*To produce high quality
concrete we must take some precautions to avoid
those common problems during concreting. In this
article, we will discuss on common concrete
problems and how to prevent them.
A) BLEEDING:
Bleeding refers to as a tendency of water to appear on the top surface of concrete after finishing. Due to bleeding some measure of water (with sand particles and other cementing materials) appears at the surface of the concrete.
*Following precautions should be taken to reduce
bleeding in concrete.
1. Design the mix appropriately.
2. Include least water content in the mix.
3. Use greater amount of cement content.
4. Use greater amount of fine particles.
5. Utilize a little measure of air entraining
admixture.
B) SEGREGATION:
Segregation means separation of coarse aggregates from the concrete surface due to poor compaction.
It is generally seen in the plastic stage of concrete.
As a result honeycomb, laitance, scaling, porous
layer, bond failure etc. can be formed in concrete.
Following precautions should be adopted to prevent segregation in concrete.
1. Design the mix appropriately.
2. Never use excessive water content.
3. Take care of handling, placing, and proper
compaction of concrete.
4. Do not allow the concrete to be dropped from more heights.
5. Use air entraining admixture.
6. Keep the formwork to be watertight.
C) LAITANCE:
The appearance of cement-sand particles on the
surface of freshly placed concrete is known as
laitance. It is mainly occurred due to the bad effect of bleeding and segregation of concrete. The bond between subsequent layers of concrete becomes
weaker and as a result, laitance is developed.
Following precautions can be taken to stop the
occurrence of laitance in concrete.
1. Clay, dust, silt content etc should be removed
before mixing the concrete.
2. Water-cement ratio should be maintained
properly.
3. Water should not be sprayed on the concrete
surface during finishing work.
4. Use well graded fine aggregates in the mix.
5. Add little amount of water reducing admixture in the concrete mix.
D) SCALING:
Scaling is the physical deterioration of concrete in
which the surface layer of concrete broke down,
pitted or flaked away. Due to this effect concrete
surface becomes worse. Scaling can be prevented
by taking same precautions adopted for laitance.
E) PLASTIC SHRINKAGE CRACKS:
When the evaporation rate of water mixed in the
concrete is greater than the bleed water of concrete,
plastic shrinkage cracks are developed on the
surface of the concrete. Basically, this type of
cracks occurs in very hot climate.
F) DUSTING:
Dusting can be prevented by taking following
precautions.
1. Maintain a suitable water/cement ratio in the
concrete.
2. Utilize dust free aggregates in the mix.
3. Guarantee appropriate hydration of concrete.
4. Avoid early surface finishing of concrete.
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
โค1
๐แแต แจ @COTMp แฐแจแณแฎแฝ แฅแแดแต แแฝแ แแฌ แฐแ แจแณแฝ แซแ แฅแซแแแฝ แฃแแแ
แฐแแ แแแณแน Discussion แแญ แ แแแแ Group แแญ แฃแตแแแกแแ แแแตแ แ แแ
..
โก @COTMp แญแแแฑ แฅแ แฅแแแแญแข
.
โฉtry these questions...
.
1. List at least four factors that affect design of
concrete mix?
2. Write procedures of laying of rising main pipes in a water supply project.
3. Estimate the quantities of brickwork and
plastering required in a wall 4 m long, 3 m high
and 30 cm thick.
*Calculate also the cost if the rate of brickwork is
320.00birr per cu m and of plastering is 8.50 birr
per sq m.
4. Given 10m3 Concrete C โ 15 Mechanical mixes
with mix ratio 1:2:4. Assuming that 30% shrinkage and 5% wastage and also take density of cement as 1400kg/m3.
Calculate the amount of cement required to make
10m3 of 1:2:4 concrete in kilograms.
*Calculate the volume of sand in cubic meter .
*Calculate the volume of gravel (crushed stone) in
cubic meter.
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแ๐
โก @COTMp แญแแแฑ แฅแ แฅแแแแญแข
.
โฉtry these questions...
.
1. List at least four factors that affect design of
concrete mix?
2. Write procedures of laying of rising main pipes in a water supply project.
3. Estimate the quantities of brickwork and
plastering required in a wall 4 m long, 3 m high
and 30 cm thick.
*Calculate also the cost if the rate of brickwork is
320.00birr per cu m and of plastering is 8.50 birr
per sq m.
4. Given 10m3 Concrete C โ 15 Mechanical mixes
with mix ratio 1:2:4. Assuming that 30% shrinkage and 5% wastage and also take density of cement as 1400kg/m3.
Calculate the amount of cement required to make
10m3 of 1:2:4 concrete in kilograms.
*Calculate the volume of sand in cubic meter .
*Calculate the volume of gravel (crushed stone) in
cubic meter.
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแ๐
๐แแต แจ @COTMp แฐแจแณแฎแฝ แฅแแดแต แแฝแ แแฌ แฐแ แตแ แซแซแญแฐแญแตแฒแญ แฅแตแตแฌแแแ แฅแ แซแซแญแฐแญแตแฒแญ แแต แแแตแแแ แฃแฅแจแ แฅแแญแข
.
โกCharacteristic Strength-แแแต แจแฎแแญแชแต แแญแ แจแฅแจแต แดแตแต แ แตแญแแ แแฅแซแแณแแฑ แดแตแต แซแแแแธแ แแคแถแฝ แแตแฅ แ แแตแต แแญแฐแแฑแ แฅแป แจแแ แแฅ แแคแต แแ แซ - แฅแตแตแฌแแแ แแแตแกแก แแญแ แฐแแ 95 แแญแฐแแฑ แจแดแตแต แแคแถแฝ แจแแ แแกแต แแคแต แแแกแก แตแแน แฅแตแตแฌแแแ แแ แแแตแญแปแแแกแก
โฉแแญแแแแ- [ fc = (mean strength)- 1.64(standard
deviation) ]
.
โกCharacteristic Load-แแแต แ แแแ แ แแแ แซแแฅแแแ แฐแฅแ แจแแณแฐแ แ แแตแฅ แ แแตแต แแญแฐแแฑ แฅแป แจแแ แแกแต load แแแกแก
โฉแแญแแแแ - [ fk = (mean load) + 1.64(standard
deviation) ]
.
*แซแซแญแฐแญแตแฒแญ แแฑแแ แแ แฅแตแตแฌแแแแ แตแแแตแต แ แแแฑแ แ แฉแ แ แแแ แดแ แแ:: แแญแแซแฑแ แฅแตแตแฌแแแแ แตแแแตแต แ แแแ แตแแฝแฌ แฅแตแตแฌแแแ แ แแ แฅแแ แแ แจแแแแตแฐแ...
*แแต แตแแแตแต แฐแแ แแตแแ แแต แแ แจแแแฐแแแ..
แแฎแฃแฅแแฒ แแซแแตแฎแนแ ( แแแ แตแณแแณแญแต แฒแญแฌแฝแ) แจแแแแตแฐแ แจแดแตแต แชแแแถแฝ แแตแฅ แแแกแก
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแ๐
.
โกCharacteristic Strength-แแแต แจแฎแแญแชแต แแญแ แจแฅแจแต แดแตแต แ แตแญแแ แแฅแซแแณแแฑ แดแตแต แซแแแแธแ แแคแถแฝ แแตแฅ แ แแตแต แแญแฐแแฑแ แฅแป แจแแ แแฅ แแคแต แแ แซ - แฅแตแตแฌแแแ แแแตแกแก แแญแ แฐแแ 95 แแญแฐแแฑ แจแดแตแต แแคแถแฝ แจแแ แแกแต แแคแต แแแกแก แตแแน แฅแตแตแฌแแแ แแ แแแตแญแปแแแกแก
โฉแแญแแแแ- [ fc = (mean strength)- 1.64(standard
deviation) ]
.
โกCharacteristic Load-แแแต แ แแแ แ แแแ แซแแฅแแแ แฐแฅแ แจแแณแฐแ แ แแตแฅ แ แแตแต แแญแฐแแฑ แฅแป แจแแ แแกแต load แแแกแก
โฉแแญแแแแ - [ fk = (mean load) + 1.64(standard
deviation) ]
.
*แซแซแญแฐแญแตแฒแญ แแฑแแ แแ แฅแตแตแฌแแแแ แตแแแตแต แ แแแฑแ แ แฉแ แ แแแ แดแ แแ:: แแญแแซแฑแ แฅแตแตแฌแแแแ แตแแแตแต แ แแแ แตแแฝแฌ แฅแตแตแฌแแแ แ แแ แฅแแ แแ แจแแแแตแฐแ...
*แแต แตแแแตแต แฐแแ แแตแแ แแต แแ แจแแแฐแแแ..
แแฎแฃแฅแแฒ แแซแแตแฎแนแ ( แแแ แตแณแแณแญแต แฒแญแฌแฝแ) แจแแแแตแฐแ แจแดแตแต แชแแแถแฝ แแตแฅ แแแกแก
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแ๐
๐แแฌ แฐแ แตแ แจ cement แฃแญแแถแฝ แฅแแแแญ @COTMp
.
โฉThere are various types of cement used in concrete construction. Each type of cement has its own properties, uses and advantages based on composition materials used during its manufacture.
โฉ13 Types of Cement and their Uses๐
1. Ordinary Portland Cement (OPC)
2. Portland Pozzolana Cement (PPC)
3. Rapid Hardening Cement
4. Quick setting cement
5. Low Heat Cement
6. Sulphates resisting cement
7. Blast Furnace Slag Cement
8. High Alumina Cement
9. White Cement
10. Coloured cement
11. Air Entraining Cement
12. Expansive cement
13. Hydrographic cement
.
โถ1. Ordinary Portland Cement (OPC)
Ordinary Portland cement is the most widely used type of cement which is
suitable for all general concrete construction.
It is most widely produced
and used type of cement around the world with annual global production of around 3.8 million cubic meters per year.
*This cement is suitable for all type of concrete construction.
โถ2. Portland Pozzolana Cement (PPC)
*Portland pozzolana cement is prepared by
grinding pozzolanic clinker with Portland
cement. It is also produced by adding pozzolana with the addition of gypsum or
calcium sulfate or by intimately and uniformly blending portland cement and fine pozzolana.
*This cement has high resistance to various
chemical attacks on concrete compared
with ordinary portland cement and thus it
is widely used. It is used in marine structures, sewage works, sewage works
and for laying concrete under water such
as bridges, piers, dams and mass concrete
works etc.
โถ3. Rapid Hardening Cement
*Rapid hardening cement attains high strength in early days it is used in
concrete where formworks are removed at an early stage and is similar to ordinary portland cement (OPC). This cement has
increased lime content and contains higher c3s content and finer grinding which gives greater strength development
than OPC at an early stage.
*The strength of rapid hardening cement at
the 3 days is similar to 7 days strength of
OPC with the same water-cement ratio.
Thus, advantage of this cement is that
formwork can be removed earlier which increases the rate of construction and
decreases cost of construction by saving
formwork cost.
*Rapid hardening cement is used in prefabricated concrete construction, road works, etc.
โถ4. Quick setting cement
The difference between the quick setting cement and rapid hardening cement is
that quick setting cement sets earlier while rate of gain of strength is similar to Ordinary Portland Cement, while rapid
hardening cement gains strength quickly.
Form works in both cases can be removed
earlier.
*Quick setting cement is used where works is to be completed in very short period and for concreting in static or running water.
โถ5. Low Heat Cement
*Low heat cement is prepared by maintaining the percentage of tricalcium Almunate below 6% by increasing the proportion of C2S. This makes the concrete to produce low heat of hydration and thus is used in mass concrete
*construction like gravity dams, as the low heat of hydration prevents the cracking of concrete due to heat.
*This cement has increased power against sulphates and is less reactive and initial
setting time is greater than OPC.
โถ6. Sulphates Resisting Cement
*Sulfate resisting cement is used to reduce the risk of sulphate attack on concrete and thus is used in construction of foundations where soil has high sulphate content.
*This cement has reduced
contents of C3A and C4AF.
Sulfate resisting cement is used in construction exposed to severe sulphate
action by water and soil in places like canals linings, culverts, retaining walls, siphons etc. ...
.
โกแญแแฅแแ ...
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
.
โฉThere are various types of cement used in concrete construction. Each type of cement has its own properties, uses and advantages based on composition materials used during its manufacture.
โฉ13 Types of Cement and their Uses๐
1. Ordinary Portland Cement (OPC)
2. Portland Pozzolana Cement (PPC)
3. Rapid Hardening Cement
4. Quick setting cement
5. Low Heat Cement
6. Sulphates resisting cement
7. Blast Furnace Slag Cement
8. High Alumina Cement
9. White Cement
10. Coloured cement
11. Air Entraining Cement
12. Expansive cement
13. Hydrographic cement
.
โถ1. Ordinary Portland Cement (OPC)
Ordinary Portland cement is the most widely used type of cement which is
suitable for all general concrete construction.
It is most widely produced
and used type of cement around the world with annual global production of around 3.8 million cubic meters per year.
*This cement is suitable for all type of concrete construction.
โถ2. Portland Pozzolana Cement (PPC)
*Portland pozzolana cement is prepared by
grinding pozzolanic clinker with Portland
cement. It is also produced by adding pozzolana with the addition of gypsum or
calcium sulfate or by intimately and uniformly blending portland cement and fine pozzolana.
*This cement has high resistance to various
chemical attacks on concrete compared
with ordinary portland cement and thus it
is widely used. It is used in marine structures, sewage works, sewage works
and for laying concrete under water such
as bridges, piers, dams and mass concrete
works etc.
โถ3. Rapid Hardening Cement
*Rapid hardening cement attains high strength in early days it is used in
concrete where formworks are removed at an early stage and is similar to ordinary portland cement (OPC). This cement has
increased lime content and contains higher c3s content and finer grinding which gives greater strength development
than OPC at an early stage.
*The strength of rapid hardening cement at
the 3 days is similar to 7 days strength of
OPC with the same water-cement ratio.
Thus, advantage of this cement is that
formwork can be removed earlier which increases the rate of construction and
decreases cost of construction by saving
formwork cost.
*Rapid hardening cement is used in prefabricated concrete construction, road works, etc.
โถ4. Quick setting cement
The difference between the quick setting cement and rapid hardening cement is
that quick setting cement sets earlier while rate of gain of strength is similar to Ordinary Portland Cement, while rapid
hardening cement gains strength quickly.
Form works in both cases can be removed
earlier.
*Quick setting cement is used where works is to be completed in very short period and for concreting in static or running water.
โถ5. Low Heat Cement
*Low heat cement is prepared by maintaining the percentage of tricalcium Almunate below 6% by increasing the proportion of C2S. This makes the concrete to produce low heat of hydration and thus is used in mass concrete
*construction like gravity dams, as the low heat of hydration prevents the cracking of concrete due to heat.
*This cement has increased power against sulphates and is less reactive and initial
setting time is greater than OPC.
โถ6. Sulphates Resisting Cement
*Sulfate resisting cement is used to reduce the risk of sulphate attack on concrete and thus is used in construction of foundations where soil has high sulphate content.
*This cement has reduced
contents of C3A and C4AF.
Sulfate resisting cement is used in construction exposed to severe sulphate
action by water and soil in places like canals linings, culverts, retaining walls, siphons etc. ...
.
โกแญแแฅแแ ...
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
๐๐๐ แจ แ
แตแ แจแแ แ @COTMp
.
โถ7. Blast Furnace Slag Cement
*Blast furnace slag cement is obtained by grinding the clinkers with about 60% slag and resembles more or less in properties of Portland cement. It can be used for works economic considerations is predominant.
โถ8. High Alumina Cement
*High alumina cement is obtained by melting mixture of bauxite and lime and grinding with the clinker.
It is a rapid hardening cement with initial and final setting time of about 3.5 and 5 hours respectively.
*The compressive strength of this cement is very high and more workable than
ordinary portland cement and is used in
*works where concrete is subjected to high temperatures, frost, and acidic action.
โถ9. White Cement
*It is prepared from raw materials free from Iron oxide and is a type of ordinary portland cement which is white in color.
*It is costlier and is used for architectural purposes such as precast curtain wall and facing panels, terrazzo surface etc. and for interior and exterior
decorative work like external renderings of buildings, facing slabs, floorings, ornamental concrete products, paths of gardens, swimming pools etc.
โถ10. Colored cement
*It is produced by mixing 5- 10% mineral pigments with ordinary cement. They are widely used for decorative works in floors.
โถ11. Air Entraining Cement
*Air entraining cement is produced by adding indigenous air entraining agents such as resins, glues, sodium salts of
sulphates etc. during the grinding of clinker.
*This type of cement is especially suited to improve the workability with smaller water cement ratio and to improve frost
resistance of concrete.
โถ12. Expansive Cement
*Expansive cement expands slightly with time and does not shrink during and after the time of hardening.
*This cement is mainly used for grouting anchor bolts and prestressed concrete ducts.
โถ13. Hydrographic cement
*Hydrographic cement is prepared by mixing water repelling chemicals and has high workability and strength.
*It has the property of repelling water and is unaffected during monsoon or rains. Hydrophobic cement is mainly used for the construction of water structures such dams, water tanks, spillways, water retaining structures etc.
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
.
โถ7. Blast Furnace Slag Cement
*Blast furnace slag cement is obtained by grinding the clinkers with about 60% slag and resembles more or less in properties of Portland cement. It can be used for works economic considerations is predominant.
โถ8. High Alumina Cement
*High alumina cement is obtained by melting mixture of bauxite and lime and grinding with the clinker.
It is a rapid hardening cement with initial and final setting time of about 3.5 and 5 hours respectively.
*The compressive strength of this cement is very high and more workable than
ordinary portland cement and is used in
*works where concrete is subjected to high temperatures, frost, and acidic action.
โถ9. White Cement
*It is prepared from raw materials free from Iron oxide and is a type of ordinary portland cement which is white in color.
*It is costlier and is used for architectural purposes such as precast curtain wall and facing panels, terrazzo surface etc. and for interior and exterior
decorative work like external renderings of buildings, facing slabs, floorings, ornamental concrete products, paths of gardens, swimming pools etc.
โถ10. Colored cement
*It is produced by mixing 5- 10% mineral pigments with ordinary cement. They are widely used for decorative works in floors.
โถ11. Air Entraining Cement
*Air entraining cement is produced by adding indigenous air entraining agents such as resins, glues, sodium salts of
sulphates etc. during the grinding of clinker.
*This type of cement is especially suited to improve the workability with smaller water cement ratio and to improve frost
resistance of concrete.
โถ12. Expansive Cement
*Expansive cement expands slightly with time and does not shrink during and after the time of hardening.
*This cement is mainly used for grouting anchor bolts and prestressed concrete ducts.
โถ13. Hydrographic cement
*Hydrographic cement is prepared by mixing water repelling chemicals and has high workability and strength.
*It has the property of repelling water and is unaffected during monsoon or rains. Hydrophobic cement is mainly used for the construction of water structures such dams, water tanks, spillways, water retaining structures etc.
.
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
โค1
๐Today Tip @COTMp
.
โก แ แ แแต แแตแญ แซแฌ แแ แซแ แ แฅแแฌแต แฅแแ แแแแ??
โฉแจแฅแแฌแต๐
โถ แตแแต =0.4แ
โถแแแต =0.2แ
=1/(0.4*0.2)
=12.5
=~13
๐ฉแตแแแ แ แ แแต แแตแญ แซแฌ 13 แแฌ แฅแแฌแต แฅแแ แแแแ แแแต แแแข
Join on telegram:- @etconp
Follow us on Instagram:- @etconp
.
โก แ แ แแต แแตแญ แซแฌ แแ แซแ แ แฅแแฌแต แฅแแ แแแแ??
โฉแจแฅแแฌแต๐
โถ แตแแต =0.4แ
โถแแแต =0.2แ
=1/(0.4*0.2)
=12.5
=~13
๐ฉแตแแแ แ แ แแต แแตแญ แซแฌ 13 แแฌ แฅแแฌแต แฅแแ แแแแ แแแต แแแข
Join on telegram:- @etconp
Follow us on Instagram:- @etconp
๐Today Tip 2 @COTMp
.
โก Question - แ แแต G+22 แจแแ แ แแ แฅแแดแต แแ แแแ แ แญแแต Column แณแแ แแ แแแแฃแต แจแแแฝแแ??
.
โกAnswer - Shear wall แ แแ แแ
.
โก Question - แจ36 แ.แ แ แแญ แแแ แแฎแแฝ แแแแตแแ Lapping แจแแญแแแฐแ??
.
โกAnswer - แแฎแแน แณแญแแธแ แตแแแ แตแแแ Lap แฅแแฐแญแแธแ แแต แตแซแแตแแญ แฅแแฒแแญ แแ แแแแ แจแ แ แแแ แ แแ แต แ แฐแจแแชแ แแแฑแ แ แแต แแญ แแฐแชแซ แตแแ แฒแซแแตแญ แซแแ แแฎ/ แฝแฆ แซแตแแแแแ - แ แตแธแแช แแ::
.
โก Question - แแแถแฝ แแตแฅ แแแแตแแ แแตแณแแต แจแแแ แแ??
.
โกAnswer - แ แแตแแณ แจแฐแจแ แ แ แฃแ แ แฃแฅ แคแต แแตแฅ แแ แฅแแ แฅแแแ แแ แญแฐแแแ??
แแแถแฝ แจแฅแ แณแธแ แ แฐแจแแช แฅแแ แตแแด แตแแแซแฐแญแ แฐแแฝ แญแฐแแ แแ แ แแฃแต แ แฐแ แจแฐแจแฐแฐ แค แแฅแซแต แจแ แ l แแแแ แฅแแ - แฅแแ แฐแแฝ แแแซแธแแ แฅแซแตแฐแซแจแ แค l แแ แณแธแแ แฅแซแฐแแ แแแแ แแณ
แฅแแฒแแ แแณแฃแธแแ แฅแแฒแฐแจแ แแ แแแต แแตแฅ แแตแณแแต แจแแแ แแ::
.
๐๐๐๐๐
Join for more updates via the link below;
t.me/COTMp
๐๐๐๐๐
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแแข
.
โก Question - แ แแต G+22 แจแแ แ แแ แฅแแดแต แแ แแแ แ แญแแต Column แณแแ แแ แแแแฃแต แจแแแฝแแ??
.
โกAnswer - Shear wall แ แแ แแ
.
โก Question - แจ36 แ.แ แ แแญ แแแ แแฎแแฝ แแแแตแแ Lapping แจแแญแแแฐแ??
.
โกAnswer - แแฎแแน แณแญแแธแ แตแแแ แตแแแ Lap แฅแแฐแญแแธแ แแต แตแซแแตแแญ แฅแแฒแแญ แแ แแแแ แจแ แ แแแ แ แแ แต แ แฐแจแแชแ แแแฑแ แ แแต แแญ แแฐแชแซ แตแแ แฒแซแแตแญ แซแแ แแฎ/ แฝแฆ แซแตแแแแแ - แ แตแธแแช แแ::
.
โก Question - แแแถแฝ แแตแฅ แแแแตแแ แแตแณแแต แจแแแ แแ??
.
โกAnswer - แ แแตแแณ แจแฐแจแ แ แ แฃแ แ แฃแฅ แคแต แแตแฅ แแ แฅแแ แฅแแแ แแ แญแฐแแแ??
แแแถแฝ แจแฅแ แณแธแ แ แฐแจแแช แฅแแ แตแแด แตแแแซแฐแญแ แฐแแฝ แญแฐแแ แแ แ แแฃแต แ แฐแ แจแฐแจแฐแฐ แค แแฅแซแต แจแ แ l แแแแ แฅแแ - แฅแแ แฐแแฝ แแแซแธแแ แฅแซแตแฐแซแจแ แค l แแ แณแธแแ แฅแซแฐแแ แแแแ แแณ
แฅแแฒแแ แแณแฃแธแแ แฅแแฒแฐแจแ แแ แแแต แแตแฅ แแตแณแแต แจแแแ แแ::
.
๐๐๐๐๐
Join for more updates via the link below;
t.me/COTMp
๐๐๐๐๐
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแแข
Telegram
ETCONp Discussion
๐ฉแแแแแแ แแณแฅ แฅแ แ แตแฐแซแจแต @Philemona7
โ๏ธแญแ แจ @etconp แแแซแซ แแฉแแน แแแข
โThis is discussion group of @ETCONpWORK
.
๐แแณแฐแฅแซ ...
.
โก๏ธแแฉแ แแญ แแแแแ แจ แฎแแตแตแซแญแฝแ แแณแฎแฝ แแช แแแ แ แ แแแ แ แญแแแตแ!
@ETCONpBOT แแแแ แฅแแแฐแแแแ๐
โ๏ธแญแ แจ @etconp แแแซแซ แแฉแแน แแแข
โThis is discussion group of @ETCONpWORK
.
๐แแณแฐแฅแซ ...
.
โก๏ธแแฉแ แแญ แแแแแ แจ แฎแแตแตแซแญแฝแ แแณแฎแฝ แแช แแแ แ แ แแแ แ แญแแแตแ!
@ETCONpBOT แแแแ แฅแแแฐแแแแ๐
๐1
Ethio Construction Engineering
Photo
๐10 key terms of Project management and schedule
you should know. @COTMp ๐
.
1. WBS (Work Breakdown Structure): Is hierarchical that breaks down the work into manageable clods so that each level of WBS could be easily understood by the project team.
.
2. Milestone:
These are the significant points in time or an event
that mark important moments during the project.
These are mainly used for
โ Starting phase
โ Ending phase
โ Fixed dates on plan
.
3. Baseline:
Is used to measure the performance of the project.
There are three baselines in project management.
These are โ
โ Schedule baseline
โ Cost baseline
โ Scope baseline
4. Gantt Chart:
Is a bar chart that displays the scheduled
.
information graphically.
5. Critical Path Method (CPM) Critical Path Method (CPM) is a step by step approach in which one can analyze critical and non- critical tasks.
6. Dummy Activity:
dummy activity is a simulated activity of sorts, one that is of a zero duration.
.
7. Float:
Float, also called slack, is the amount of time a
task can slip before it bumps into another task.
8. Chart Dependencies:
.
the predecessor is the first task; it controls the start
or end date for all related successor tasks. The
successor, by contrast, is the task whose start or
end date is controlled by the predecessor.
.
9. Types of relationship:
โ Finish to Start: Predecessor must finish before Successor can start.
โ Start to Start:Predecessor must start before Successor can start.
โ Finish to Finish: Predecessor must finish before Successor can finish.
โ Start to Finish: Predecessor must start before Successor can finish.
.
10. Lead time and Lag time: Lead time causes the successor task to begin
before its predecessor task concludes.
Lag time causes the successor task to begin some time after its predecessor task concludes.
.
๐๐๐๐๐
Join for more updates via the link below;
t.me/COTMp
๐๐๐๐๐
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
you should know. @COTMp ๐
.
1. WBS (Work Breakdown Structure): Is hierarchical that breaks down the work into manageable clods so that each level of WBS could be easily understood by the project team.
.
2. Milestone:
These are the significant points in time or an event
that mark important moments during the project.
These are mainly used for
โ Starting phase
โ Ending phase
โ Fixed dates on plan
.
3. Baseline:
Is used to measure the performance of the project.
There are three baselines in project management.
These are โ
โ Schedule baseline
โ Cost baseline
โ Scope baseline
4. Gantt Chart:
Is a bar chart that displays the scheduled
.
information graphically.
5. Critical Path Method (CPM) Critical Path Method (CPM) is a step by step approach in which one can analyze critical and non- critical tasks.
6. Dummy Activity:
dummy activity is a simulated activity of sorts, one that is of a zero duration.
.
7. Float:
Float, also called slack, is the amount of time a
task can slip before it bumps into another task.
8. Chart Dependencies:
.
the predecessor is the first task; it controls the start
or end date for all related successor tasks. The
successor, by contrast, is the task whose start or
end date is controlled by the predecessor.
.
9. Types of relationship:
โ Finish to Start: Predecessor must finish before Successor can start.
โ Start to Start:Predecessor must start before Successor can start.
โ Finish to Finish: Predecessor must finish before Successor can finish.
โ Start to Finish: Predecessor must start before Successor can finish.
.
10. Lead time and Lag time: Lead time causes the successor task to begin
before its predecessor task concludes.
Lag time causes the successor task to begin some time after its predecessor task concludes.
.
๐๐๐๐๐
Join for more updates via the link below;
t.me/COTMp
๐๐๐๐๐
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข
Telegram
ETCONp Discussion
๐ฉแแแแแแ แแณแฅ แฅแ แ แตแฐแซแจแต @Philemona7
โ๏ธแญแ แจ @etconp แแแซแซ แแฉแแน แแแข
โThis is discussion group of @ETCONpWORK
.
๐แแณแฐแฅแซ ...
.
โก๏ธแแฉแ แแญ แแแแแ แจ แฎแแตแตแซแญแฝแ แแณแฎแฝ แแช แแแ แ แ แแแ แ แญแแแตแ!
@ETCONpBOT แแแแ แฅแแแฐแแแแ๐
โ๏ธแญแ แจ @etconp แแแซแซ แแฉแแน แแแข
โThis is discussion group of @ETCONpWORK
.
๐แแณแฐแฅแซ ...
.
โก๏ธแแฉแ แแญ แแแแแ แจ แฎแแตแตแซแญแฝแ แแณแฎแฝ แแช แแแ แ แ แแแ แ แญแแแตแ!
@ETCONpBOT แแแแ แฅแแแฐแแแแ๐
๐ญ1
๐Important points for a Construction Site Engineer @COTMp
.
โถA site engineer has to perform a lot of activities on the site. His/her role involves a lot of responsibility which includes giving sufficient advice and supervision when there are any technical issues, or for proper management and for the preparation of day to day reports of the construction works.
*There are some works which are recurring and hence a few tips might be useful for a civil engineer if
they are remembered. They help in faster
*calculations as well as to address problems at
the site.
โฉPoints to Remember for Civil Site Engineer ๐
:
โถ36mm is the maximum diameter of the bars used for lapping.
*Bars having more than this diameter are not allowed.
โถMaximum chair spacing is 1m and the minimum diameter used for these bars is 12mm.
โถMinimum diameter used for dowels bars is
12mm.
โถLongitudinal reinforcement should not be less than 0.8% of gross area of cross section
and not be more than 6% of the same.
โถMinimum number of bars used for square
columns is 4 and that of a circle is 6.
โถThe main bars used in the slabs should not
be less than 8mm when HYSD bars are used
and 10mm when plain bars are used.
โถThe distribution bars in slabs should not less
than 8mm and not more than 1/8 of slab
thickness.
โถMinimum thickness of slab is 125mm.
โถMaximum free fall of concrete is allowed to
1.50m.
โถLap slices not be employed for bars greater
than 36 mm.
โถPH value of the water should not be less
than 6.
โถCompressive strength of Bricks is 3.5 N/
mm
โถWater absorption of bricks should not be
more than 15 %.
โถ Binding wire required in steel reinforcement
is 8 kg per MT.
.
๐ Density of Materials
*Bricks : 1600-1920kg/m
*Concrete block:1920kg/m
*Reinforced concrete :2310-2700kg/m
โฉDe shuttering time of different RCC Members
*For columns : 16-24 hrs.
*Soffit formwork to slabs : 3days
*Soffit to beams props : 7days
*Beams spanning upto 4.5m : 7days
.
๐๐๐๐๐
Join for more updates via the link below;
t.me/COTMp
๐๐๐๐๐
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแแข
.
โถA site engineer has to perform a lot of activities on the site. His/her role involves a lot of responsibility which includes giving sufficient advice and supervision when there are any technical issues, or for proper management and for the preparation of day to day reports of the construction works.
*There are some works which are recurring and hence a few tips might be useful for a civil engineer if
they are remembered. They help in faster
*calculations as well as to address problems at
the site.
โฉPoints to Remember for Civil Site Engineer ๐
:
โถ36mm is the maximum diameter of the bars used for lapping.
*Bars having more than this diameter are not allowed.
โถMaximum chair spacing is 1m and the minimum diameter used for these bars is 12mm.
โถMinimum diameter used for dowels bars is
12mm.
โถLongitudinal reinforcement should not be less than 0.8% of gross area of cross section
and not be more than 6% of the same.
โถMinimum number of bars used for square
columns is 4 and that of a circle is 6.
โถThe main bars used in the slabs should not
be less than 8mm when HYSD bars are used
and 10mm when plain bars are used.
โถThe distribution bars in slabs should not less
than 8mm and not more than 1/8 of slab
thickness.
โถMinimum thickness of slab is 125mm.
โถMaximum free fall of concrete is allowed to
1.50m.
โถLap slices not be employed for bars greater
than 36 mm.
โถPH value of the water should not be less
than 6.
โถCompressive strength of Bricks is 3.5 N/
mm
โถWater absorption of bricks should not be
more than 15 %.
โถ Binding wire required in steel reinforcement
is 8 kg per MT.
.
๐ Density of Materials
*Bricks : 1600-1920kg/m
*Concrete block:1920kg/m
*Reinforced concrete :2310-2700kg/m
โฉDe shuttering time of different RCC Members
*For columns : 16-24 hrs.
*Soffit formwork to slabs : 3days
*Soffit to beams props : 7days
*Beams spanning upto 4.5m : 7days
.
๐๐๐๐๐
Join for more updates via the link below;
t.me/COTMp
๐๐๐๐๐
โก แ แแแ Join แ แแจแ แฅแ แแแฐแแ แฅแ แแแซแแต แแ แผแญ แซแตแญแแข แฅแแแฐแแแแแข
Telegram
ETCONp Discussion
๐ฉแแแแแแ แแณแฅ แฅแ แ แตแฐแซแจแต @Philemona7
โ๏ธแญแ แจ @etconp แแแซแซ แแฉแแน แแแข
โThis is discussion group of @ETCONpWORK
.
๐แแณแฐแฅแซ ...
.
โก๏ธแแฉแ แแญ แแแแแ แจ แฎแแตแตแซแญแฝแ แแณแฎแฝ แแช แแแ แ แ แแแ แ แญแแแตแ!
@ETCONpBOT แแแแ แฅแแแฐแแแแ๐
โ๏ธแญแ แจ @etconp แแแซแซ แแฉแแน แแแข
โThis is discussion group of @ETCONpWORK
.
๐แแณแฐแฅแซ ...
.
โก๏ธแแฉแ แแญ แแแแแ แจ แฎแแตแตแซแญแฝแ แแณแฎแฝ แแช แแแ แ แ แแแ แ แญแแแตแ!
@ETCONpBOT แแแแ แฅแแแฐแแแแ๐
๐2