Design of RC staircase #U-shape

Both design and example

@etconp

Facebook:- https://www.facebook.com/etconp/
👍7
A soil has porosity of 30%. It’s void ratio in the loosest and densest state is 0.35 and 0.92 respectively. What will be it’s density index ?
Anonymous Quiz
17%
0.865
25%
0.872
48%
0.861
9%
0.881
👍18🔥2
Ethio Construction Engineering
A soil has porosity of 30%. It’s void ratio in the loosest and densest state is 0.35 and 0.92 respectively. What will be it’s density index ?
Answer 0.861

Here is why

Given

- Porosity of 30% = 0.3
- void ratio in the loosest state
(emin)= 0.35
- void ratio in the densest state
(emax) = 0.92

Required

Density index (ID) =?

Solution

- e = n/(1-n)

- e = 0.3/(1-0.3)

- e = 0.429

ID = (emax-e)/ (emax-emin)

ID = (0.92-0.429)/ (0.92-0.35)

ID = 0.861

@etconp

Facebook:- https://www.facebook.com/etconp/
👍35❤2👏2🔥1
Pop quiz

1. What’s point of contraflexure ?

2. What’s the difference between breast wall and retaining wall ?

3. What about cavity wall ?

4. What’s the difference about OPC
and PPC ?

5. What’s carpet area ?

6. What’s built up or plinth area ?

@etconp

Facebook:- https://www.facebook.com/etconp/

Prepared by :- JORDANO JOMOLE
👍19
👉ANSWER
1ኛ, Contraflexure
-It is the point of bending moment curve intersects zero line.
-it is a point where a moment change it's sign posetive to negative or compression to tension and vise versa
-it is a place of zero reinforcements because of zero moment but practically it is difficult to locat the exact point of contraflexure and omit reinforcement bar.

2ኛ, Retaining wall and breast wall differences

Retaining wall is designed and constructed to resist lateral earth pressure while breast wall is to sustain the face of naturla bank of the earth
Breast wall አንዳንድ በተፈጥሮ ተራራማ የሆኑ የመንገድ ስራዎች ላይ አስቸጋሪ የሆኑ ተራራማ መንገዶች ሲሰሩ ለመንገዱ ተብሎ excavation ሲሰራ ከተራራው በኩል ያለው topography በጣም ተዳፋች ከሆነ breast wall እየተሰራ ከላይ ያለው የመሬት ክፍል እየፈረሰ ወደ ታች ወደ መንገዱ እንዳይወርድ በsolpe እየተቆረጠ ይገነባል ዋና አላማውም to stabilze the hill side ነው አፈሩን ያረጋጋል ይከላከላል።
Retaining wall ደግሞ ሙሉ በሙሉ active soil pressure ወይም lateral pressure የምንለውን ከጎን በኩል አግድም የሚመጣን የአፈር ግፊት ለመከላከል ታስቦ የሚሰራ wall ነው።

3ኛ,Cavity wall
This types of wall is used for thermal insulation, sound insulation and etc...
A cavity wall( hollow wall) is a non load bearing wall with two wall and there is a space between them to separate those two wall.
The walls are interconnected by metal ties or other means.
When we construct cavity wall it doesn't need footing, instead we can use strong concret base.

4ኛ OPC and PPC
1, OPC has higher strength than PPC in the initial stage but in the long term the strength of PPC is good than OPC.
2, OPC has high heat of hydration (ውሀ አዘልነት) compared to than PPC
3 Grade of cement (strength) compressive strength of OPC and PPC
OPC has 42.5R
PPC has 32.5R

5ኛ,Carpet Area
It is simply the net usable aera in the building or the distance between the inner wall it includes a staircase in the internal parts of the building excluding external wall,veranda and terrace area etc...

6ኛ, Built up area or plinth area
It is the out to out dimension of the wall of the building at any floor በአጭሩ በየትኛውም ፍሎር ላይ የህንፃው ውጪ ለውጪ ልኬት ማለት ነው።

@etconp
👍40❤10
The performance of specific task in CPM (critical path method) is known as
Anonymous Quiz
20%
Dummy
53%
Activity
17%
Event
9%
Constant
👍17❤2
👍13❤6🔥1👏1
When the water table is close to the ground surface , the bearing capacity of a soil is reduced to
Anonymous Quiz
24%
¼
29%
½
20%
⅓
27%
¾
👍21
The equation τ = C + σ tan φ is given by.
Anonymous Quiz
32%
Rankine
27%
Coulomb
5%
Culaman
36%
Mohr
❤1
👍4
The moment distribution method in structural analysis can be treated as
Anonymous Quiz
31%
Force method
37%
Displacement method
23%
Flexibility method
9%
None of these
👍7😁2
If ‘H’ is the overall height of a retaining wall retaining a surcharge, the width of the base slab usually provided, is
Anonymous Quiz
39%
0.3 H
21%
0.4 H
23%
0.5 H
17%
0.7 H
👍8
👍14
Distribution of shear intensity over a rectangular section of a beam, follows:
Anonymous Quiz
9%
A circular curve
45%
A straight line
38%
A parabolic curve
8%
An elliptical curve
👍12
In a simply supported slab, alternate bars are curtailed at
Anonymous Quiz
72%
1/4th of the span
9%
1/5th of the span
12%
1/6th of the span
8%
1/7th of the span
👍20
Ethio Construction Engineering
In a simply supported slab, alternate bars are curtailed at
Expiation

Curtailment is a way of reducing the area of tensile reinforcement at points/areas (either on a beam/slab) where bending moment is minimum or zero for the purpose of achieving an economic design.
Condition of curtailment - At least 50% of the total main reinforcement shall be carried through at the bottom on to the bearing and anchored in accordance
let us find out the BM in simply supported slab at 1/7th of span or 0.15L from the face of the support. (Considering unit strip)

BM =w. l/2 x 0.15 l - 0.15 w. l x 0.15 l/2 =0.06375 wl²

Which is almost equal to 1/16 wl² or in other words it is 50 %of maximum. Moment at mid span (for udl) wl²/8
Thus we can curtail 50 % of bars or alternate bars depending upon moment requirement at app. 1/7th of the span from face of the support, subject to the provision of minimum reinforcement.

Ethiopian Construction Work Professionals - ETCONp

Telegram:- https://www.facebook.com/etconp/
👍12
Network of Sanitary pipeline

📍 leghar Addis Ababa In front of
Awash bank head office

@etconp

Facebook:- https://www.facebook.com/etconp/
👍8
Bar Bending Schedule

Just like any other schedules, bar bending schedule is most important part of any project.
It helps in doing reconciliation of steel and controlling the wastage at site.
If bar bending schedule (BBS) is not prepared at site, then contractor and its workmen tend to cut and and bend bars without quantifying it and leads to more wastage due to over doing it.

Engineer who going to use this sheet for doing BBS should aware of following;
- Should be able to read the structural and architectural drawings.
Should know where the lapping of bar is to be done.

- Should know how to calculate number of bar as per spacing in any given member.

- Basic knowledge of using excel sheet.

@etconp

Facebook:- https://www.facebook.com/etconp/
👍15👏2
concrete mix design question

design the concrete for an unreinforced, air-entrained pavement, in a very cold climate where there is no statistical data available for the proposed mix design; 25 cm thick; specified 28-day concrete flexural strength of 4.7 MPa; the coarse aggregates have a bulk specific gravity of 2.70; a rodded density of 1650 kg/m3 at the saturated surface dry (SSD) condition and a moisture content of 1.5% above the SSD condition; the fine aggregates have a bulk specific gravity of 2.65 with a fineness modulus of 2.75 and a moisture of 5% above the (SSD) condition. The apparent specific gravity of the Portland cement = 3.15.

If more than 30 members participate we will post the solution ….. we don’t need intensive participation at least show us you are with us

ከ 30 በላይ አባላት ተሳትፏቸውን ካሳዩን ጥያቄውን ለመስራት ዝግጁ ነን ቢያንስ ትንሽ ሞክራችሁ አብሮነታችሁን አሳዩን

@etconp

Facebook:- https://www.facebook.com/etconp/
👍43🥰1