๐๏ธ DEFECTS LIABILITY PERIOD โ WHAT DOES IT MEAN?
Some construction contracts specify a period during which the contractor has defined obligations relating to defects in completed work.
The exact responsibilities depend on the contract and applicable law.
๐น What May Happen During This Period?
๐ Defects may be reported through the required process.
๐ The relevant work may be inspected.
๐ ๏ธ Corrective work may be required under the contract.
๐ Records of notifications and completed corrections may be maintained.
๐ Contractual deadlines and procedures must be observed.
๐น What Should Contractors Do?
1๏ธโฃ Understand the contract's defect notification procedure.
2๏ธโฃ Keep completion and handover records.
3๏ธโฃ Respond to valid notices according to contractual requirements.
4๏ธโฃ Document inspections and corrective work.
5๏ธโฃ Confirm completion of required actions.
๐ Important: A defects liability period is not necessarily the same as a product warranty or the entire period of legal responsibility for defects.
โ ๏ธ Always read the actual contract and seek appropriate professional advice where obligations are unclear.
@ETCONP
Some construction contracts specify a period during which the contractor has defined obligations relating to defects in completed work.
The exact responsibilities depend on the contract and applicable law.
๐น What May Happen During This Period?
๐ Defects may be reported through the required process.
๐ The relevant work may be inspected.
๐ ๏ธ Corrective work may be required under the contract.
๐ Records of notifications and completed corrections may be maintained.
๐ Contractual deadlines and procedures must be observed.
๐น What Should Contractors Do?
1๏ธโฃ Understand the contract's defect notification procedure.
2๏ธโฃ Keep completion and handover records.
3๏ธโฃ Respond to valid notices according to contractual requirements.
4๏ธโฃ Document inspections and corrective work.
5๏ธโฃ Confirm completion of required actions.
๐ Important: A defects liability period is not necessarily the same as a product warranty or the entire period of legal responsibility for defects.
โ ๏ธ Always read the actual contract and seek appropriate professional advice where obligations are unclear.
@ETCONP
โค2๐1
๐ VARIATION ORDERS IN CONSTRUCTION โ WHAT SHOULD CONTRACTORS KNOW?
A variation is an authorized change to the work under a construction contract, subject to the contract's terms and procedures.
Variations may become necessary when project requirements change or previously defined work needs to be adjusted.
๐น Examples of Variations
๐๏ธ Changes to the scope of work.
๐ Revised dimensions or specifications.
๐งฑ Additional or omitted work.
๐ Changes to quantities where contractually permitted.
๐น How Should a Variation Be Managed?
1๏ธโฃ Identify and describe the proposed change.
2๏ธโฃ Review the relevant contract provisions.
3๏ธโฃ Assess technical implications.
4๏ธโฃ Evaluate cost and schedule effects.
5๏ธโฃ Obtain the required authorization.
6๏ธโฃ Record the change and supporting documents.
7๏ธโฃ Update relevant project records and forecasts.
โ ๏ธ A contractor should not assume that every additional activity automatically entitles them to extra payment or time. The contractual basis and approval procedures matter.
๐ Always follow the contract's variation and change-control process.
@ETCONP
A variation is an authorized change to the work under a construction contract, subject to the contract's terms and procedures.
Variations may become necessary when project requirements change or previously defined work needs to be adjusted.
๐น Examples of Variations
๐๏ธ Changes to the scope of work.
๐ Revised dimensions or specifications.
๐งฑ Additional or omitted work.
๐ Changes to quantities where contractually permitted.
๐น How Should a Variation Be Managed?
1๏ธโฃ Identify and describe the proposed change.
2๏ธโฃ Review the relevant contract provisions.
3๏ธโฃ Assess technical implications.
4๏ธโฃ Evaluate cost and schedule effects.
5๏ธโฃ Obtain the required authorization.
6๏ธโฃ Record the change and supporting documents.
7๏ธโฃ Update relevant project records and forecasts.
โ ๏ธ A contractor should not assume that every additional activity automatically entitles them to extra payment or time. The contractual basis and approval procedures matter.
๐ Always follow the contract's variation and change-control process.
@ETCONP
๐2
๐CONSTRUCTION MATERIALS TESTING MANUAL
๐๏ธแจแแแฃแณ แฅแฌ แแแแฝแ แจแฅแซแต แแญแแซ (Material Testing) แ แฐแแฃแญ แแแญ แญแแแแ?
๐แญแ แแ แจแแซ แแแชแซ แจแฒแแแถแฃ แ แแชแแตแฃ แฎแแญแชแตแฃ แกแฅแฃ แฅแแญแฃ แฅแจแตแฃ แ แแญแฃ แแญแ แฅแ แจแแ แแจแแจแซ แแณแแถแฝแ แจแแญแแซ แแดแแฝ แญแแแข
โ แCivil แฅแ Material Engineers
โ แLaboratory Technicians
โ แQA/QC Engineers
โ แSite Engineers
โ แ COTEM แฅแ Civil Engineering Students
๐ฏ แจแแซ แฅแแแตแแ แซแณแตแแค แจแแแฃแณ แฅแซแตแ แซแจแแแก!
๐ฅแญแ แแญแฅ แแแญแซ แแ แแ แจแณแฝ แฃแแ แแแญ แซแแญแฑแต๐
https://ye-buna.com/etconp?ref=product_detail&product=6ae709e5de7bd_etconp
๐๏ธแจแแแฃแณ แฅแฌ แแแแฝแ แจแฅแซแต แแญแแซ (Material Testing) แ แฐแแฃแญ แแแญ แญแแแแ?
๐แญแ แแ แจแแซ แแแชแซ แจแฒแแแถแฃ แ แแชแแตแฃ แฎแแญแชแตแฃ แกแฅแฃ แฅแแญแฃ แฅแจแตแฃ แ แแญแฃ แแญแ แฅแ แจแแ แแจแแจแซ แแณแแถแฝแ แจแแญแแซ แแดแแฝ แญแแแข
โ แCivil แฅแ Material Engineers
โ แLaboratory Technicians
โ แQA/QC Engineers
โ แSite Engineers
โ แ COTEM แฅแ Civil Engineering Students
๐ฏ แจแแซ แฅแแแตแแ แซแณแตแแค แจแแแฃแณ แฅแซแตแ แซแจแแแก!
๐ฅแญแ แแญแฅ แแแญแซ แแ แแ แจแณแฝ แฃแแ แแแญ แซแแญแฑแต๐
https://ye-buna.com/etconp?ref=product_detail&product=6ae709e5de7bd_etconp
๐1