Almonte river viaduct
The construction process of almonte river viaduct.
The bridge 🌉 construction began in July 2011GC and completion was reached at the end of 2016GC
➡️Length:- 996meters
➡️Main span :- 384meters
➡️Arch concrete C80/95(m3):-9.748
➡️Rest of structure concrete(m3):-44.351
➡️Reinforcement steel B500(t):- 7.255
➡️post tension steel (t):- 541
➡️ Temporary cable- stays steel:- 857
➡️Temporary tower steel(t):- 894
➡️ Retaining ground anchors(m):- 6.03
➡️ cost:- 41 million euros 💶
Service date:- November 2016
Madrid, Spain 🇪🇸
#bridge #viaduct #highway #railway
#almonte
Source:- Adif
ፋይሉ 5.9MB ስለሆነ WiFi ቢጠቀሙ ይመረጣል
@etconp
The construction process of almonte river viaduct.
The bridge 🌉 construction began in July 2011GC and completion was reached at the end of 2016GC
➡️Length:- 996meters
➡️Main span :- 384meters
➡️Arch concrete C80/95(m3):-9.748
➡️Rest of structure concrete(m3):-44.351
➡️Reinforcement steel B500(t):- 7.255
➡️post tension steel (t):- 541
➡️ Temporary cable- stays steel:- 857
➡️Temporary tower steel(t):- 894
➡️ Retaining ground anchors(m):- 6.03
➡️ cost:- 41 million euros 💶
Service date:- November 2016
Madrid, Spain 🇪🇸
#bridge #viaduct #highway #railway
#almonte
Source:- Adif
ፋይሉ 5.9MB ስለሆነ WiFi ቢጠቀሙ ይመረጣል
@etconp
Forwarded from Ethio Construction Engineering (जॉर्डनो ג׳ורדנו ጆርዳኖ جوردانو จอร์แดโน่ JORDANO Ιορδάνοςஜார்டானோ)
This media is not supported in your browser
VIEW IN TELEGRAM
Almonte river viaduct
The construction process of almonte river viaduct.
The bridge 🌉 construction began in July 2011GC and completion was reached at the end of 2016GC
➡️Length:- 996meters
➡️Main span :- 384meters
➡️Arch concrete C80/95(m3):-9.748
➡️Rest of structure concrete(m3):-44.351
➡️Reinforcement steel B500(t):- 7.255
➡️post tension steel (t):- 541
➡️ Temporary cable- stays steel:- 857
➡️Temporary tower steel(t):- 894
➡️ Retaining ground anchors(m):- 6.03
➡️ cost:- 41 million euros 💶
Service date:- November 2016
Madrid, Spain 🇪🇸
#bridge #viaduct #highway #railway
#almonte
Source:- Adif
ፋይሉ 5.9MB ስለሆነ WiFi ቢጠቀሙ ይመረጣል
@etconp
The construction process of almonte river viaduct.
The bridge 🌉 construction began in July 2011GC and completion was reached at the end of 2016GC
➡️Length:- 996meters
➡️Main span :- 384meters
➡️Arch concrete C80/95(m3):-9.748
➡️Rest of structure concrete(m3):-44.351
➡️Reinforcement steel B500(t):- 7.255
➡️post tension steel (t):- 541
➡️ Temporary cable- stays steel:- 857
➡️Temporary tower steel(t):- 894
➡️ Retaining ground anchors(m):- 6.03
➡️ cost:- 41 million euros 💶
Service date:- November 2016
Madrid, Spain 🇪🇸
#bridge #viaduct #highway #railway
#almonte
Source:- Adif
ፋይሉ 5.9MB ስለሆነ WiFi ቢጠቀሙ ይመረጣል
@etconp
This media is not supported in your browser
VIEW IN TELEGRAM
👉Almonte river viaduct
🚧The construction process of almonte river viaduct.
🌟The bridge 🌉 construction began in July 2011GC and completion was reached at the end of 2016GC
➡️Length:- 996meters
➡️Main span :- 384meters
➡️Arch concrete C80/95(m3):-9.748
➡️Rest of structure concrete(m3):-44.351
➡️Reinforcement steel B500(t):- 7.255
➡️post tension steel (t):- 541
➡️ Temporary cable- stays steel:- 857
➡️Temporary tower steel(t):- 894
➡️ Retaining ground anchors(m):- 6.03
➡️ cost:- 41 million euros 💶
✨Service date:- November 2016
🖱Madrid, Spain 🇪🇸
#bridge #viaduct #highway #railway
#almonte
Source:- Adif
@etconp
🚧The construction process of almonte river viaduct.
🌟The bridge 🌉 construction began in July 2011GC and completion was reached at the end of 2016GC
➡️Length:- 996meters
➡️Main span :- 384meters
➡️Arch concrete C80/95(m3):-9.748
➡️Rest of structure concrete(m3):-44.351
➡️Reinforcement steel B500(t):- 7.255
➡️post tension steel (t):- 541
➡️ Temporary cable- stays steel:- 857
➡️Temporary tower steel(t):- 894
➡️ Retaining ground anchors(m):- 6.03
➡️ cost:- 41 million euros 💶
✨Service date:- November 2016
🖱Madrid, Spain 🇪🇸
#bridge #viaduct #highway #railway
#almonte
Source:- Adif