👉What is Asphalt Road Construction?
💫Asphalt road construction involves the use of asphalt, a mixture of aggregates, binder, and filler, to build and maintain roads, highways, and other pavement surfaces.
🚧The components of asphalt include aggregates, binder, and filler.
⏺Aggregates are the inert materials that provide strength and bulk to the asphalt mixture. Common aggregates used include crushed rock, sand, gravel, or slags.
⏺The binder is the adhesive substance that holds the aggregates together, with bitumen being the most common binder used.
⏺Fillers are fine materials that fill the gaps between the aggregates and binder, such as limestone dust, cement, or hydrated lime.
🏷The asphalt mixture is created by combining the aggregates, binder, and filler in specific proportions.
⏺The mixture is then heated to a high temperature (around 300°F) to facilitate mixing and application.
❇️The asphalt road construction process typically involves several steps.
⏺First, the site is prepared by clearing the area, removing debris, and grading the surface. Next, a layer of compacted aggregate material is laid down to provide a stable base.
⏺The heated asphalt mixture is then applied to the base course using a paver or spreader.
🔰After the asphalt mixture is applied, it is compacted using rollers or compactors to achieve the desired density and smoothness.
🚧Finally, the surface is finished with a layer of asphalt emulsion or sealcoat to protect it from the elements.
⏺Asphalt road construction is used for a wide range of applications, including highways and roads, parking areas, railway tracks, ports and airport runways, bicycle lanes and sidewalks, and playgrounds and sports areas.
⏺Asphalt is a popular choice for road construction due to its durability, flexibility, and resistance to heavy traffic and harsh weather conditions.
@etconp
💫Asphalt road construction involves the use of asphalt, a mixture of aggregates, binder, and filler, to build and maintain roads, highways, and other pavement surfaces.
🚧The components of asphalt include aggregates, binder, and filler.
⏺Aggregates are the inert materials that provide strength and bulk to the asphalt mixture. Common aggregates used include crushed rock, sand, gravel, or slags.
⏺The binder is the adhesive substance that holds the aggregates together, with bitumen being the most common binder used.
⏺Fillers are fine materials that fill the gaps between the aggregates and binder, such as limestone dust, cement, or hydrated lime.
🏷The asphalt mixture is created by combining the aggregates, binder, and filler in specific proportions.
⏺The mixture is then heated to a high temperature (around 300°F) to facilitate mixing and application.
❇️The asphalt road construction process typically involves several steps.
⏺First, the site is prepared by clearing the area, removing debris, and grading the surface. Next, a layer of compacted aggregate material is laid down to provide a stable base.
⏺The heated asphalt mixture is then applied to the base course using a paver or spreader.
🔰After the asphalt mixture is applied, it is compacted using rollers or compactors to achieve the desired density and smoothness.
🚧Finally, the surface is finished with a layer of asphalt emulsion or sealcoat to protect it from the elements.
⏺Asphalt road construction is used for a wide range of applications, including highways and roads, parking areas, railway tracks, ports and airport runways, bicycle lanes and sidewalks, and playgrounds and sports areas.
⏺Asphalt is a popular choice for road construction due to its durability, flexibility, and resistance to heavy traffic and harsh weather conditions.
@etconp
❤21🔥1👏1
ADVERTISMENT
ታምራት ፕሌት እና ጄ ቦልት አቅራቢ
✅የምንሰጣቸው አገልግሎቶች
🔅 ፕሌት any Size & thickness
🔅 ጄ ቦልት (ጥርስ ማዉጣትና ማጠፍ)
🔅 የተለያዩ [modefic] ስራዎችን እንሰራለን።
♦️ ማንኛዉንም ብረታ ብረት እንገዛለን።
☎️ስልክ 0904040477 ወይም 0911016833 ደውለው ያግኙን
📱ቴሌግራም ላይ ፦https://t.me/heavenic1
አድራሻ፦ ቁ 1.መርካቶ
ቁ.2 አየር ጤና ኪዳነ ምህረት
ጥራትና ታማኝነት መለያችን ነው።
ታምራት ፕሌት እና ጄ ቦልት አቅራቢ
ታምራት ፕሌት እና ጄ ቦልት አቅራቢ
✅የምንሰጣቸው አገልግሎቶች
🔅 ፕሌት any Size & thickness
🔅 ጄ ቦልት (ጥርስ ማዉጣትና ማጠፍ)
🔅 የተለያዩ [modefic] ስራዎችን እንሰራለን።
♦️ ማንኛዉንም ብረታ ብረት እንገዛለን።
☎️ስልክ 0904040477 ወይም 0911016833 ደውለው ያግኙን
📱ቴሌግራም ላይ ፦https://t.me/heavenic1
አድራሻ፦ ቁ 1.መርካቶ
ቁ.2 አየር ጤና ኪዳነ ምህረት
ጥራትና ታማኝነት መለያችን ነው።
ታምራት ፕሌት እና ጄ ቦልት አቅራቢ
❤2
👉Brazil is revolutionizing green infrastructure by turning sugarcane bagasse—the fibrous waste from juice extraction—into a key ingredient for tougher, longer-lasting, and eco-friendly roads.
🚧Mixed into asphalt and concrete, this residue reduces cracks, boosts flexibility, and enhances resistance to extreme weather, addressing a former disposal challenge.
🏷This innovation benefits the environment, economy, and sustainable construction, positioning Brazil as a leader as the world takes note.
⏺This showcases how waste can pave a sustainable future, though broader adoption and long-term performance data are still needed to fully validate its impact.
@etconp
🚧Mixed into asphalt and concrete, this residue reduces cracks, boosts flexibility, and enhances resistance to extreme weather, addressing a former disposal challenge.
🏷This innovation benefits the environment, economy, and sustainable construction, positioning Brazil as a leader as the world takes note.
⏺This showcases how waste can pave a sustainable future, though broader adoption and long-term performance data are still needed to fully validate its impact.
@etconp
❤6😱1
👉የዓለማችን ግዙፍ የቴክኖሎጂ ተቋማት
የኤ.አይ መሰረተ ልማት ለማስፋፋት እየሰሩ ነው።
💫ኢንቪዲያና ኦፕን ኤ.አይ የ100 ቢ. ዶላር ስምምነት አድርገዋል።
🚧በኤ.አይ ቴክኖሎጂ ዘርፍ የሚሰሩ ተቋማት ለቴክኖሎጂው ትግበራ የሚያስፈልጉ መሰረተ ልማቶችን ለማምረት የሚያስችሉ ስምምነቶችን እያደረጉ መሆኑን ሮይተርስ አስነብቧል፡፡
ግዙፉ የቺፕ አምራች ኩባንያ ኢንቪዲያ እና ኦፕን ኤ.አይ የዳታ ሴንተር ቺፖችን ለማምረት የሚያስችል የ100ቢሊዮን ዶላር ስምምነት አድርገዋል፡፡ በሌላ በኩል፤ ሜታ ኩባንያን በመጪዎቹ አመታት የክላውድ ኮምፒውቲንግ ተጠቃሚ የሚያደርግ የ20 ቢሊዮን ዶላር ስምምነት ከኦራክል ኩባንያ ጋር ተፈርሟል፡፡
ሜታ እና ጉግል በክላውድ ኮምፒውቲንግ ላይ ለመስራት የ10 ቢሊዮን ዶላር ስምምነት ማሰራቸው የሚታወስ ነው፡፡ የቴስላ ኩባንያ ፈጣን የቴክኖሎጂውን ቺፖች ለመጠቀም የሚያስችለውን ስምምነት ከሳምሰንግ ጋር በ16.5 ቢሊዮን ዶላር ተፈራርሟል፡፡
በአሜሪካ የተዋወቀው እና ሶፍትባንክ፣ ኦፕን ኤ.አይ እንዲሁም ኦራክል በጋራ የሚሰሩት ስታርጌት ፕሮጀክት 500 ቢሊየን ዶላር የተመደበለት መሆኑ አይዘነጋም፡፡
በያዝነው የፈረንጆቹ አመት ተፅዕኖ ፈጣሪ የዘርፉ አንቀሳቃሽ ኩባንያዎች፣ ለቴክኖሎጂው እድገት አጋዥ የሆኑ ስምምነቶች አድርገዋል፡፡ በተለያዩ ጊዜያት የተደረጉት እነዚህ ስምምነቶች፣ በፍጥነት እያደገ የሚገኘዉን የኤ.አይ ቴክኖሎጂ አብሮ ለማልማት አስፈላጊ የሆኑ መሰረተ ልማቶችን የመገንባት ፍላጎት እያደገ ስለመሆኑ አመላካች ነው ሲል የኢትዮጵያ አርቴፊሻል ኢንተለጀንስ ኢንስቲቲዩት አስነብቧል፡፡
@etconp
የኤ.አይ መሰረተ ልማት ለማስፋፋት እየሰሩ ነው።
💫ኢንቪዲያና ኦፕን ኤ.አይ የ100 ቢ. ዶላር ስምምነት አድርገዋል።
🚧በኤ.አይ ቴክኖሎጂ ዘርፍ የሚሰሩ ተቋማት ለቴክኖሎጂው ትግበራ የሚያስፈልጉ መሰረተ ልማቶችን ለማምረት የሚያስችሉ ስምምነቶችን እያደረጉ መሆኑን ሮይተርስ አስነብቧል፡፡
ግዙፉ የቺፕ አምራች ኩባንያ ኢንቪዲያ እና ኦፕን ኤ.አይ የዳታ ሴንተር ቺፖችን ለማምረት የሚያስችል የ100ቢሊዮን ዶላር ስምምነት አድርገዋል፡፡ በሌላ በኩል፤ ሜታ ኩባንያን በመጪዎቹ አመታት የክላውድ ኮምፒውቲንግ ተጠቃሚ የሚያደርግ የ20 ቢሊዮን ዶላር ስምምነት ከኦራክል ኩባንያ ጋር ተፈርሟል፡፡
ሜታ እና ጉግል በክላውድ ኮምፒውቲንግ ላይ ለመስራት የ10 ቢሊዮን ዶላር ስምምነት ማሰራቸው የሚታወስ ነው፡፡ የቴስላ ኩባንያ ፈጣን የቴክኖሎጂውን ቺፖች ለመጠቀም የሚያስችለውን ስምምነት ከሳምሰንግ ጋር በ16.5 ቢሊዮን ዶላር ተፈራርሟል፡፡
በአሜሪካ የተዋወቀው እና ሶፍትባንክ፣ ኦፕን ኤ.አይ እንዲሁም ኦራክል በጋራ የሚሰሩት ስታርጌት ፕሮጀክት 500 ቢሊየን ዶላር የተመደበለት መሆኑ አይዘነጋም፡፡
በያዝነው የፈረንጆቹ አመት ተፅዕኖ ፈጣሪ የዘርፉ አንቀሳቃሽ ኩባንያዎች፣ ለቴክኖሎጂው እድገት አጋዥ የሆኑ ስምምነቶች አድርገዋል፡፡ በተለያዩ ጊዜያት የተደረጉት እነዚህ ስምምነቶች፣ በፍጥነት እያደገ የሚገኘዉን የኤ.አይ ቴክኖሎጂ አብሮ ለማልማት አስፈላጊ የሆኑ መሰረተ ልማቶችን የመገንባት ፍላጎት እያደገ ስለመሆኑ አመላካች ነው ሲል የኢትዮጵያ አርቴፊሻል ኢንተለጀንስ ኢንስቲቲዩት አስነብቧል፡፡
@etconp
❤11👍1
👉 Dead Load vs Live Load (ACI Code)
🟩 Dead Load (DL):
⏺Permanent load on a structure.
⏺Includes self-weight of beams, slabs, columns, walls, and finishes.
⏺Does not change during building life.
⏺ACI Factor (USD): 1.2 × DL
🟥 Live Load (LL):
▶️Temporary or movable load.
📍Includes weight of people, furniture, vehicles, wind, or snow.
🔰Varies with usage or time.
▶️ACI Factor (USD): 1.6 × LL
✅ Design Load Combination (ACI 318): 1.2 DL + 1.6 LL
📘 Summary:
▶️DL = Permanent load (structure weight)
🎲LL = Variable load (occupancy & use)
#CivilEngineering
#StructuralDesign
#ConstructionKnowledge
#BuildingDesignTips
#CivilWorks
#EngineeringBasics
#EducationalContent
#EngineeringVibes
#LearnCivilEngineering
@etconp
🟩 Dead Load (DL):
⏺Permanent load on a structure.
⏺Includes self-weight of beams, slabs, columns, walls, and finishes.
⏺Does not change during building life.
⏺ACI Factor (USD): 1.2 × DL
🟥 Live Load (LL):
▶️Temporary or movable load.
📍Includes weight of people, furniture, vehicles, wind, or snow.
🔰Varies with usage or time.
▶️ACI Factor (USD): 1.6 × LL
✅ Design Load Combination (ACI 318): 1.2 DL + 1.6 LL
📘 Summary:
▶️DL = Permanent load (structure weight)
🎲LL = Variable load (occupancy & use)
#CivilEngineering
#StructuralDesign
#ConstructionKnowledge
#BuildingDesignTips
#CivilWorks
#EngineeringBasics
#EducationalContent
#EngineeringVibes
#LearnCivilEngineering
@etconp
❤14🙏5
👉What is Slump Test and Why It Matters?
📌Definition: The Slump Test is a simple test used to measure the workability and consistency
of fresh concrete before placing it in formwork.
💫Purpose:
• To check the uniformity of concrete from batch to batch.
• To ensure proper water-cement ratio and desired workability.
Equipment Used:
• Slump cone (300mm high, 200mm bottom dia, 100mm top dia)
• Tamping rod (16mm dia, 600mm long)
• Base plate and measuring scale
📜Procedure:
1. Fill the cone with fresh concrete in 3 layers, each tamped 25 times.
2. Remove the cone vertically and measure the subsidence (slump) of concrete.
3. The difference in height gives the slump value (in mm).
⭐️Types of Slump:
• True Slump – Concrete subsides uniformly.
• Shear Slump – Concrete slides sideways (indicates poor cohesion).
• Collapse Slump – Concrete completely collapses (too wet mix).
Typical Slump Values:
• Mass Concrete: 25–50 mm
• Reinforced Foundation: 50–100 mm
• Slabs & Beams: 75–125 mm
• Pumped Concrete: 100–150 mm
💥Importance:
⏺The slump test ensures proper workability, reduces segregation risk, and confirms concrete quality before casting.
#SlumpTest #ConcreteTesting #WorkabilityTest #CivilEngineering #QualityControl
#ConstructionSite #FreshConcrete #SiteEngineer #ConcreteWork
#EngineeringKnowledge
@etconp
📌Definition: The Slump Test is a simple test used to measure the workability and consistency
of fresh concrete before placing it in formwork.
💫Purpose:
• To check the uniformity of concrete from batch to batch.
• To ensure proper water-cement ratio and desired workability.
Equipment Used:
• Slump cone (300mm high, 200mm bottom dia, 100mm top dia)
• Tamping rod (16mm dia, 600mm long)
• Base plate and measuring scale
📜Procedure:
1. Fill the cone with fresh concrete in 3 layers, each tamped 25 times.
2. Remove the cone vertically and measure the subsidence (slump) of concrete.
3. The difference in height gives the slump value (in mm).
⭐️Types of Slump:
• True Slump – Concrete subsides uniformly.
• Shear Slump – Concrete slides sideways (indicates poor cohesion).
• Collapse Slump – Concrete completely collapses (too wet mix).
Typical Slump Values:
• Mass Concrete: 25–50 mm
• Reinforced Foundation: 50–100 mm
• Slabs & Beams: 75–125 mm
• Pumped Concrete: 100–150 mm
💥Importance:
⏺The slump test ensures proper workability, reduces segregation risk, and confirms concrete quality before casting.
#SlumpTest #ConcreteTesting #WorkabilityTest #CivilEngineering #QualityControl
#ConstructionSite #FreshConcrete #SiteEngineer #ConcreteWork
#EngineeringKnowledge
@etconp
❤18👍2🥰1
👉የአለም ሎሬት ሜትር አርቲስት አፈወርቅ ተክሌ ቤት ወይም ቪላ አልፋ እድሳት መጠናቀቁ ተገለጸ
💫የአለም ሎሬት ሜትር አርቲስት አፈወርቅ ተክሌ ቤት ወይም ቪላ አልፋ እስከ ጥቅምት 2018 ለሕዝብ ክፍት ይሆናል ቢባልም፤ ክፍት ከመደረጉ በፊት መሰራት ያለባቸው ሥራዎች ገና ባለመጠናቀቃቸው እስከ ሚያዚያ ወር ሊቆይ እንደሚችል ነው የተገልጿል፡፡
የተከበሩ የአለም ሎሬት ሜትር አርቲስት አፈወርቅ ተክሌ በሚያዚያ 2 ቀን 2004 ዓ.ም ካረፉ በኋላ ዝግ ሆኖ እስካሁን የዘለቀው ቪላ አልፋ፤ የተለያዩ የጥገና ሥራዎች እየተሰሩለት ነው ቢባልም ግን ለሕዝብ እይታ ተከልክሎ 14ኛ ዓመቱን ይዟል፡፡
ቪላ አልፋ የጥገና ሥራው ከመጀመሩ በፊት ውስጡ ያሉት ተንቀሳቃሽ የጥበብ ሥራዎች እና ሌሎችም ንብረቶች ወደ ቅርስ ባለ-ስልጣን መስሪያ ቤቱ እንዲሄዱ ተደርጎ እንደነበርም የሚታወስ ነው፡፡
ከመሬት በታች በሚወጣ እና ከላይ በሚዘንብ ዝናብ ቪላ አልፋ በጣም ተጎድቶ ነበር፤ አሁን ላይ ግን ከውጭ ሀገራትም ይሁን ከሀገር ውስጥ የአርቲስቱን ሥራዎች እየተመለከቱ ባለሙያዎች ትምህርት ለመውሰድ በሚችሉበት ደረጃ ጥገናው ተደርጓል ነው የተባለው፡፡
እንደ ሙዚየም የሚደራጅ በመሆኑ ጊዜ እንደወሰደም ነው የተገለጸው፡፡
የእድሳቱ ሥራ ተጠናቆ የርክክብ እና ቅርሶችን በቦታቸው የመመለስ ሥራዎች ብቻ ቀርቷል ሲሉም የብሄራዊ ሙዚየም መሪ ስራ አስፈጻሚ አቶ አንዷለም ግርማይ ለአሐዱ ተናግረዋል፡፡
"የእድሳቱ ሥራ ጥንቃቄዎችን የሚጠይቅ ነበር" ያሉት አቶ እንዷለም፤ የርክክብ ሥራዎች ሲጠናቀቁ ቪላ አልፋን በ2018 እስከ ሚያዚያ ወር ለእይታ ክፍት ለማድረግ ታስቧል ነው ያሉት፡፡
የእድሳት ሥራው 65 ሚሊየን ብር እንዳስወጣ ከዚህ በፊት የወጡ መረጃዎች ያመለክታሉ፡የእድሳት ሥራው በምዕራፎች የተከፋፈለ ነበር ነው የተባለው፡፡
@etconp
💫የአለም ሎሬት ሜትር አርቲስት አፈወርቅ ተክሌ ቤት ወይም ቪላ አልፋ እስከ ጥቅምት 2018 ለሕዝብ ክፍት ይሆናል ቢባልም፤ ክፍት ከመደረጉ በፊት መሰራት ያለባቸው ሥራዎች ገና ባለመጠናቀቃቸው እስከ ሚያዚያ ወር ሊቆይ እንደሚችል ነው የተገልጿል፡፡
የተከበሩ የአለም ሎሬት ሜትር አርቲስት አፈወርቅ ተክሌ በሚያዚያ 2 ቀን 2004 ዓ.ም ካረፉ በኋላ ዝግ ሆኖ እስካሁን የዘለቀው ቪላ አልፋ፤ የተለያዩ የጥገና ሥራዎች እየተሰሩለት ነው ቢባልም ግን ለሕዝብ እይታ ተከልክሎ 14ኛ ዓመቱን ይዟል፡፡
ቪላ አልፋ የጥገና ሥራው ከመጀመሩ በፊት ውስጡ ያሉት ተንቀሳቃሽ የጥበብ ሥራዎች እና ሌሎችም ንብረቶች ወደ ቅርስ ባለ-ስልጣን መስሪያ ቤቱ እንዲሄዱ ተደርጎ እንደነበርም የሚታወስ ነው፡፡
ከመሬት በታች በሚወጣ እና ከላይ በሚዘንብ ዝናብ ቪላ አልፋ በጣም ተጎድቶ ነበር፤ አሁን ላይ ግን ከውጭ ሀገራትም ይሁን ከሀገር ውስጥ የአርቲስቱን ሥራዎች እየተመለከቱ ባለሙያዎች ትምህርት ለመውሰድ በሚችሉበት ደረጃ ጥገናው ተደርጓል ነው የተባለው፡፡
እንደ ሙዚየም የሚደራጅ በመሆኑ ጊዜ እንደወሰደም ነው የተገለጸው፡፡
የእድሳቱ ሥራ ተጠናቆ የርክክብ እና ቅርሶችን በቦታቸው የመመለስ ሥራዎች ብቻ ቀርቷል ሲሉም የብሄራዊ ሙዚየም መሪ ስራ አስፈጻሚ አቶ አንዷለም ግርማይ ለአሐዱ ተናግረዋል፡፡
"የእድሳቱ ሥራ ጥንቃቄዎችን የሚጠይቅ ነበር" ያሉት አቶ እንዷለም፤ የርክክብ ሥራዎች ሲጠናቀቁ ቪላ አልፋን በ2018 እስከ ሚያዚያ ወር ለእይታ ክፍት ለማድረግ ታስቧል ነው ያሉት፡፡
የእድሳት ሥራው 65 ሚሊየን ብር እንዳስወጣ ከዚህ በፊት የወጡ መረጃዎች ያመለክታሉ፡የእድሳት ሥራው በምዕራፎች የተከፋፈለ ነበር ነው የተባለው፡፡
@etconp
❤9👍1🥰1
👉TESTS FOR SAND
💫1. Sieve Analysis Test
⏺Used to determine the particle size distribution of sand. Pass sand through sieves
(4.75 mm to 150 µm). Helps to classify as fine, medium, or coarse.
💫2. Silt Content Test
⏺Determines the percentage of silt or clay in sand.
⏺Mix 50 ml sand with 50 ml water in a cylinder, shake, and settle for 3–4 hours.
⏺Silt should not exceed 8%.
💫3. Bulking of Sand Test
⏺Checks the increase in sand volume due to moisture.
⏺Add small amount of water
and note the volume change. Normal bulking = 10–25%.
💫4. Specific Gravity Test
⏺Determines density ratio of sand compared to water. Ideal specific gravity = 2.6 –2.7.
💫5. Organic Impurities Test
⏺Checks for organic matter or clay.
⏺Mix sand with NaOH solution; brown color indicates impurities.
💫6. Moisture Content Test
⏺Finds the amount of water in sand.
⏺Dry the sample at 110°C and calculate moisture % using weight difference.
💫7. Fineness Modulus Test
⏺Indicates sand quality and gradation.
⏺FM = (Cumulative % retained on sieves) /100. Fine sand = 2.2–2.6, Coarse = 2.6–2.9.
🏷Good quality sand ensures strong and durable concrete.
#MaterialTesting
#SandTesting
#QualityControl
#LabTesting
#SoilAndSand
#BuildingMaterialsTest
#ConstructionTesting
#ConcreteQuality
#SiltContentTest
#SieveAnalysis
@etconp
💫1. Sieve Analysis Test
⏺Used to determine the particle size distribution of sand. Pass sand through sieves
(4.75 mm to 150 µm). Helps to classify as fine, medium, or coarse.
💫2. Silt Content Test
⏺Determines the percentage of silt or clay in sand.
⏺Mix 50 ml sand with 50 ml water in a cylinder, shake, and settle for 3–4 hours.
⏺Silt should not exceed 8%.
💫3. Bulking of Sand Test
⏺Checks the increase in sand volume due to moisture.
⏺Add small amount of water
and note the volume change. Normal bulking = 10–25%.
💫4. Specific Gravity Test
⏺Determines density ratio of sand compared to water. Ideal specific gravity = 2.6 –2.7.
💫5. Organic Impurities Test
⏺Checks for organic matter or clay.
⏺Mix sand with NaOH solution; brown color indicates impurities.
💫6. Moisture Content Test
⏺Finds the amount of water in sand.
⏺Dry the sample at 110°C and calculate moisture % using weight difference.
💫7. Fineness Modulus Test
⏺Indicates sand quality and gradation.
⏺FM = (Cumulative % retained on sieves) /100. Fine sand = 2.2–2.6, Coarse = 2.6–2.9.
🏷Good quality sand ensures strong and durable concrete.
#MaterialTesting
#SandTesting
#QualityControl
#LabTesting
#SoilAndSand
#BuildingMaterialsTest
#ConstructionTesting
#ConcreteQuality
#SiltContentTest
#SieveAnalysis
@etconp
1❤16👍9👏2😱1🙏1
A project has a negative Schedule Performance Index (SPI < 1) and a negative Cost Performance Index (CPI < 1). This indicates:
Anonymous Quiz
18%
A. Project is ahead of schedule and under budget
50%
B. Project is behind schedule and over budget
12%
C. Project is ahead of schedule but over budget
20%
D. Project is behind schedule but under budget
👏11❤2
Which standard covers the specification for Portland cement?
Anonymous Quiz
51%
A) ASTM C150
33%
B) ISO 9001
8%
C) IS 456
9%
D) BS 8110
❤15👏2
Which of the following methods allows for both time-cost trade-off and resource analysis?
Anonymous Quiz
50%
A) Gantt chart
18%
B) Line of Balance
22%
C) Time-Scaled Network
11%
D) Precedence Diagramming Method
👌6❤5👍1
What is the value of minimum nominal clear cover for slab?
Anonymous Quiz
54%
15
17%
20
26%
25
3%
30
🙏11❤4
The propagation of shear crack in a prestressed concrete member depends on :
Anonymous Quiz
18%
Tensile reinforcement
23%
Compression reinforcement
47%
Shear reinforcement
12%
Shape of the cross section of beam
👏5❤3
What is the loading rate used in compressive strength test?
Anonymous Quiz
23%
14 N/mm² per hour
52%
14 N/mm² per minute
14%
Both a and b
10%
None of the above
❤8
What is the total percentage of aggregates in concrete in terms of volume?
Anonymous Quiz
25%
65%-80%
5%
90%
59%
60%-75%
12%
40%
👌5❤4