Geotechnical Engineering
What’s the minimum water content at which the soil just begins to crumble when it’s rolled into 3 mm diameter threads ?
What’s the minimum water content at which the soil just begins to crumble when it’s rolled into 3 mm diameter threads ?
Anonymous Quiz
52%
Plastic limit
20%
Liquid limit
18%
Shrinkage limit
10%
Plasticity limit
Ethio Construction Engineering
Geotechnical Engineering
What’s the minimum water content at which the soil just begins to crumble when it’s rolled into 3 mm diameter threads ?
What’s the minimum water content at which the soil just begins to crumble when it’s rolled into 3 mm diameter threads ?
GEOTECHNICAL ENGINEERING
what’s the minimum water content at which the soil begins to crumble when it’s rolled into 3mm diameter threads ?
1️⃣. Plastic limit
2️⃣. Liquid limit
3️⃣. Shrinkage limit
4️⃣. Plastic limit
@etconp
Instagram :- https://instagram.com/etconp?igshid=h82z1u7h3leg
Facebook :- https://www.facebook.com/115479406977628/posts/120058029853099/?d=n
Please update your telegram
what’s the minimum water content at which the soil begins to crumble when it’s rolled into 3mm diameter threads ?
1️⃣. Plastic limit
2️⃣. Liquid limit
3️⃣. Shrinkage limit
4️⃣. Plastic limit
@etconp
Instagram :- https://instagram.com/etconp?igshid=h82z1u7h3leg
Facebook :- https://www.facebook.com/115479406977628/posts/120058029853099/?d=n
Please update your telegram
Media is too big
VIEW IN TELEGRAM
👉የውሃ ላይ ተንቀሳቃሽ ከተሞች ያውቃሉ?
🚧እነዚህ ከተሞች እንዴት እንደሚገነቡ በ ምስል የተደገፈ ገለፃ በ ሰሎሞን ቴክ ቶክ ተዘጋጅተዋል።
🚧ቪድዮ ለማየት ከዚህ ፅሁፍ አያይዘንላቹሀል 163.5 MB ስለሆነ WIFI ቢጠቀሙ ይመረጣል።
🎥ወይም በ YOUTUBE ለማየት ከታች ባለው ሊንክ ይከታተሉት
https://youtu.be/Z23Okb1i6-U
Via Tech Talk With Solomon
#ConstructionTechnology
@etconp
🚧እነዚህ ከተሞች እንዴት እንደሚገነቡ በ ምስል የተደገፈ ገለፃ በ ሰሎሞን ቴክ ቶክ ተዘጋጅተዋል።
🚧ቪድዮ ለማየት ከዚህ ፅሁፍ አያይዘንላቹሀል 163.5 MB ስለሆነ WIFI ቢጠቀሙ ይመረጣል።
🎥ወይም በ YOUTUBE ለማየት ከታች ባለው ሊንክ ይከታተሉት
https://youtu.be/Z23Okb1i6-U
Via Tech Talk With Solomon
#ConstructionTechnology
@etconp
This media is not supported in your browser
VIEW IN TELEGRAM
👉Building Resonance
➡️Structural stability during earthquake
➡️Why do some buildings fall in earthquakes?
🚧All buildings have a natural period, or resonance, which is the number of seconds it takes for the building to naturally vibrate back and forth.
🚧The ground also has a specific resonant frequency.
🚧Hard bedrock has higher frequencies softer sediments If the period of ground motion matches the natural resonance of a building, it will undergo the largest oscillations possible and suffer the greatest damage.
🚧A sample demonstration follows the animated portion of this video clip.
@etconp
➡️Structural stability during earthquake
➡️Why do some buildings fall in earthquakes?
🚧All buildings have a natural period, or resonance, which is the number of seconds it takes for the building to naturally vibrate back and forth.
🚧The ground also has a specific resonant frequency.
🚧Hard bedrock has higher frequencies softer sediments If the period of ground motion matches the natural resonance of a building, it will undergo the largest oscillations possible and suffer the greatest damage.
🚧A sample demonstration follows the animated portion of this video clip.
@etconp
👉መሰረት /Foundation/
➡️Foundation
▶️1) ቁፋሮ እና አፈር ሙሌት
⏺መሰረት ሁልጊዜ የተረጋጋ መሬት ላይ ሊቀመጥ ይገባል።
ጥሩ አፈር ካልሆነ በተመረጠ እና ከሌላ ቦታ በመጣ አፈር በሚገባ
ተጠቅጥቆ እና ተደልድሎ ሊቀመጥ ይገባል።
⏺የተመረጠው አፈር ንብርብር/layer/ በየ 25 ሴ᎐ሜ በሚገባ
ሊጠቀጠቅ ወይም ሊደለደል/compact/ ሊደረግ ይገባል።
⏺በሚደለደልበት ወቅት በተወሰነ ረገድ እያንዳንዱን ንብርብር ለተሻለ ጥቅጠቃ እንዲያመች እርጥበት እነዲያገኝ ውሀ ማርከፍከፍ ያስፈልጋል
▶️2) አርማታ ሙሌት እና የብረት ስራ
⏺ቀጭን አርማታ/lean Concrete/ ከተመረጠው አፈር ሙሌት በላይ ሊደረግ ይገባል እንደ አስፈላጊነቱም እርጥበተ መከላከያ/water proof/ ሊደረግ ይችላል።
⏺አርማታ ሙሌት ለመሰረት፣ ቢም፣ ኮለን እና ወለል ስራ የአርማታ ጥንካሬ በትንሹ C25 ሊኖረው ይገባል በተጨማሪ እንደ ስትራክቸራል ዲዛይኑ ሊለያይ ይችላል።
⏺የቢም ብረት የላይኛው ብረት መሀል ላይ የታችኛው ደግሞ ኮለን ድጋፍ/support/ ላይ ሊሆን ይገባል እንዲሁም ማት ፋውንዴሽን ላይ የዚህ ተቃራኒ ይሆናል።
⏺ብረት 4D የብረቱን ውፍረት በአራት በማባዛት የሚሰጠንን ርዝመት በመደረብ መተላለፍ ይተበቅበታል።
⏺ዲዛይን ላይ በተቆራረጠ መስመር /hidden line የሚቀመጡ ብረቶች ሁልጊዜ የታች ብረት ሆነው ይቀመጣሉ።
⏺የአርማታ ሽፋን/concrete cover/አብዛኛውን ግዜ 5ሴ᎐ሜ ይሆናል ከመሬት በላይ ግን በ 2᎐5ሴ.ሜ ይሰራል።
⏺በአርማታ ወይም በብረት የሚሰራ ክፍተት መስጫ spacer/ ልንጠቀም ይገባል።
⚡️ይቀጥላል ...
#Foundation
@etconp
➡️Foundation
▶️1) ቁፋሮ እና አፈር ሙሌት
⏺መሰረት ሁልጊዜ የተረጋጋ መሬት ላይ ሊቀመጥ ይገባል።
ጥሩ አፈር ካልሆነ በተመረጠ እና ከሌላ ቦታ በመጣ አፈር በሚገባ
ተጠቅጥቆ እና ተደልድሎ ሊቀመጥ ይገባል።
⏺የተመረጠው አፈር ንብርብር/layer/ በየ 25 ሴ᎐ሜ በሚገባ
ሊጠቀጠቅ ወይም ሊደለደል/compact/ ሊደረግ ይገባል።
⏺በሚደለደልበት ወቅት በተወሰነ ረገድ እያንዳንዱን ንብርብር ለተሻለ ጥቅጠቃ እንዲያመች እርጥበት እነዲያገኝ ውሀ ማርከፍከፍ ያስፈልጋል
▶️2) አርማታ ሙሌት እና የብረት ስራ
⏺ቀጭን አርማታ/lean Concrete/ ከተመረጠው አፈር ሙሌት በላይ ሊደረግ ይገባል እንደ አስፈላጊነቱም እርጥበተ መከላከያ/water proof/ ሊደረግ ይችላል።
⏺አርማታ ሙሌት ለመሰረት፣ ቢም፣ ኮለን እና ወለል ስራ የአርማታ ጥንካሬ በትንሹ C25 ሊኖረው ይገባል በተጨማሪ እንደ ስትራክቸራል ዲዛይኑ ሊለያይ ይችላል።
⏺የቢም ብረት የላይኛው ብረት መሀል ላይ የታችኛው ደግሞ ኮለን ድጋፍ/support/ ላይ ሊሆን ይገባል እንዲሁም ማት ፋውንዴሽን ላይ የዚህ ተቃራኒ ይሆናል።
⏺ብረት 4D የብረቱን ውፍረት በአራት በማባዛት የሚሰጠንን ርዝመት በመደረብ መተላለፍ ይተበቅበታል።
⏺ዲዛይን ላይ በተቆራረጠ መስመር /hidden line የሚቀመጡ ብረቶች ሁልጊዜ የታች ብረት ሆነው ይቀመጣሉ።
⏺የአርማታ ሽፋን/concrete cover/አብዛኛውን ግዜ 5ሴ᎐ሜ ይሆናል ከመሬት በላይ ግን በ 2᎐5ሴ.ሜ ይሰራል።
⏺በአርማታ ወይም በብረት የሚሰራ ክፍተት መስጫ spacer/ ልንጠቀም ይገባል።
⚡️ይቀጥላል ...
#Foundation
@etconp
👉ዶ/ር ኢንጂነር ስለሺ በቀለ የኮይሻ የሃይድሮ ኤሌክትሪክ ማመንጫ ግድብ ግንባታን ጎበኙ!
🚧የውሃ፣ መስኖ እና ኢነርጂ ሚኒስትር ዶክተር ኢንጂነር ስለሺ በቀለ ከተመድ የአፍሪካ ኢኮኖሚ ኮሚሽን ዋና ጸሃፊ ከቬራ ሶንግዌ ጋር በመሆን የኮይሻና የጊቤ 3 የሃይል ማመንጫን መጎብኘታቸውን በማህበራዊ ትስስር ገፃቸው አስፍረዋል፡፡
🚧ጊቤ ሶስት ከ3 አመታት በፊት ግንባታው ተጠናቆ በአሁኑ ሰአት 1870 ሜጋ ዋት ሃይል የማመንጨት አቅም ያለው ላይ ሲሆን አሁን ግንባታው 39 በመቶ የደረሰው ጊቤ 4 ወይንም ኮይሻ ሲጠናቀቅ ደግሞ 2160 ሜጋ ዋት የኤሌክትሪክ ሃይል ያመነጫል ሲሉም ጠቅሰዋል፡፡
🚧ይህና የሕዳሴ ግድብ ሲጠናቀቁ አሁን ባለው የኤሌክትሪክ ሃይል ምርት ላይ 170% በማሳደግ በ 2022 ሙሉ በሙሉ ለገራችን ዜጎች ሃይል ለማቅረብ በምናደርገው ጥረት ላይ ትልቁን ሚና እንደሚጫወት ነው የገለጹት::
@etconp
🚧የውሃ፣ መስኖ እና ኢነርጂ ሚኒስትር ዶክተር ኢንጂነር ስለሺ በቀለ ከተመድ የአፍሪካ ኢኮኖሚ ኮሚሽን ዋና ጸሃፊ ከቬራ ሶንግዌ ጋር በመሆን የኮይሻና የጊቤ 3 የሃይል ማመንጫን መጎብኘታቸውን በማህበራዊ ትስስር ገፃቸው አስፍረዋል፡፡
🚧ጊቤ ሶስት ከ3 አመታት በፊት ግንባታው ተጠናቆ በአሁኑ ሰአት 1870 ሜጋ ዋት ሃይል የማመንጨት አቅም ያለው ላይ ሲሆን አሁን ግንባታው 39 በመቶ የደረሰው ጊቤ 4 ወይንም ኮይሻ ሲጠናቀቅ ደግሞ 2160 ሜጋ ዋት የኤሌክትሪክ ሃይል ያመነጫል ሲሉም ጠቅሰዋል፡፡
🚧ይህና የሕዳሴ ግድብ ሲጠናቀቁ አሁን ባለው የኤሌክትሪክ ሃይል ምርት ላይ 170% በማሳደግ በ 2022 ሙሉ በሙሉ ለገራችን ዜጎች ሃይል ለማቅረብ በምናደርገው ጥረት ላይ ትልቁን ሚና እንደሚጫወት ነው የገለጹት::
@etconp
👉Construction Tips
🚧1. What do you know about “TMT”?
➡️Thermo Mechanically Treated or known as TMT is for used construction purposes.
➡️An Engineer usually use TMT bars and sheet because they have high corrosion resistance and high strength compared to normal steels.
🚧2. What is difference between limit state method and working stress method?
➡️Limit state method is a method used in plastic design which the structure is designed to bear the load plastic limit.
➡️While, working stress method is an elastic design method which designed to bear elastic limit.
🚧3. What are the functions of column in a building?
➡️Column is a vertical member in building that has a function to support structural load and transfer it into beams.
➡️Upper columns also has function which is to transfers the load to the lower columns to the ground through footings.
#ConstructionTips
@etconp
🚧1. What do you know about “TMT”?
➡️Thermo Mechanically Treated or known as TMT is for used construction purposes.
➡️An Engineer usually use TMT bars and sheet because they have high corrosion resistance and high strength compared to normal steels.
🚧2. What is difference between limit state method and working stress method?
➡️Limit state method is a method used in plastic design which the structure is designed to bear the load plastic limit.
➡️While, working stress method is an elastic design method which designed to bear elastic limit.
🚧3. What are the functions of column in a building?
➡️Column is a vertical member in building that has a function to support structural load and transfer it into beams.
➡️Upper columns also has function which is to transfers the load to the lower columns to the ground through footings.
#ConstructionTips
@etconp
Ethio Construction Engineering
👉መሰረት /Foundation/ ➡️Foundation ▶️1) ቁፋሮ እና አፈር ሙሌት ⏺መሰረት ሁልጊዜ የተረጋጋ መሬት ላይ ሊቀመጥ ይገባል። ጥሩ አፈር ካልሆነ በተመረጠ እና ከሌላ ቦታ በመጣ አፈር በሚገባ ተጠቅጥቆ እና ተደልድሎ ሊቀመጥ ይገባል። ⏺የተመረጠው አፈር ንብርብር/layer/ በየ 25 ሴ᎐ሜ በሚገባ ሊጠቀጠቅ ወይም ሊደለደል/compact/ ሊደረግ ይገባል። ⏺በሚደለደልበት ወቅት በተወሰነ ረገድ…
👉ከትላንት የቀጠለ
🏷ስለ የ Foundation (መሠረት) ኣይነቶች ትንሽ እንበል...
🚧1)Shallow Foundation
➡️እነዚህን ፋውንዴሽኖች የምንጠቀመው አፈሩ ብዙም ሳይቆፈር በቅርብ ጥልቀት ጠንካራ የአፈር ሁኔታ ካለ ነው፡፡
➡️ለመገንባት ትልልቅ ማሺኖች አያስፈልጉም ብዙ ችሎታም አይጠይቁም::
▶️1.1) Spread/ Pad/Isolated Footing
➡️አንድ ኮለን ብቻ ነው support የሚያደርጉትእንዲሁም የሚመጣውን ፎርስ eccentricity መሰረት በማድረግ circular/ rectangular or square የሆነ ቅርፅ ሊኖራቸው ይችላል፡፡
▶️1.2)Combined Footing
➡️ሁለትና ከዛ በላይ ኮለኖችን በአንድ ፓድ support ለማድረግ ነው የምንጠቀምባቸው፡፡
➡️እነዚህን የምንጠቀመው ሁለት ተቀራራቢ Isolated Footing ካሉ ሁለቱን አንድ ላይ combine በማድረግ ኮንክሪትም ፌሮም ሴቭ ማድረግ እንችላለን፡፡
➡️በተጨማሪም isolated ለመጠቀም property limit ካለ እነዚህን መጠቀም እንችላለን::
➡️2 አይነት Combined Footing አሉፐእነርሱም
▶️1.2.1) Rectangular Combined Footing
➡️ይህንን የምንጠቀመው ሁለቱም ኮለኖች የሚሸከሙት ሎድ ተቀራራቢ ወይም እኩል ከሆከሆነይም ትራፖዞይዳል ለመጠቀም የስፋት ገደብ ካለ ነው።
▶️1.2.2. Trapezoidal Combined Footing
➡️ሁለቱ ኮለኖች የሚሸከሙት ሎድ ልዩነት የተጋነነ ከሆነ ነው።
▶️1.3) Strap/ Cantilever Footing
➡️ሁለት ፓዶችን በቢም በማያያዝ ሎድ ከአንዱ ፓድ ወደሌላው እንዲተላለፍ ማድረግ እንችላለን፡፡
➡️ቢሙ በራሱ ሎድ አይሸከምም ሎድ ያስተላልፋል እንጂ እነዚህን የምንጠቀመው ኮለኖቹ ከ7 ሜትር በላይ ከተራራቁ combined footing ብንጠቀም ኢኮኖሚካል ስለማንሆን ፓዶቹን በቢም በማያያዝ እንደ combined footing ልንጠቀምባቸው እንችላለን፡፡
▶️1.4) Mat/ Raft foundation
➡️እነዚህን የምንጠቀመው መሬቱ የመሸከም አቅሙ ትንሽ ከሆነና spread footing ስንጠቀም የህንጸውን ስፋት ከ50 ፐርሰንት በላይ ከሸፈኑት ነው።
➡️አንዳንዴ ግን spread footing ከ 50 ፐርሰንት በላይ ቢሸፍኑትም ለ spread footing negative reinforcement ስለማንጠቀም ከ Mat ይልቅ ኢኮኖሚካል ሊሆኑ ይችላሉ ምክንያቱም Mat negative & positive reinforcement ይጠቀማሉ፡፡
➡️ማን ኢኮኖሚካል እንደሆነ ቼክ ማድረግ የኢንጅነሩ ድርሻ ነው፡፡
⚡ቀጣይ ደሞ ስለ Deep Foundation እንማማራለን
#Foundation
@etconp
🏷ስለ የ Foundation (መሠረት) ኣይነቶች ትንሽ እንበል...
🚧1)Shallow Foundation
➡️እነዚህን ፋውንዴሽኖች የምንጠቀመው አፈሩ ብዙም ሳይቆፈር በቅርብ ጥልቀት ጠንካራ የአፈር ሁኔታ ካለ ነው፡፡
➡️ለመገንባት ትልልቅ ማሺኖች አያስፈልጉም ብዙ ችሎታም አይጠይቁም::
▶️1.1) Spread/ Pad/Isolated Footing
➡️አንድ ኮለን ብቻ ነው support የሚያደርጉትእንዲሁም የሚመጣውን ፎርስ eccentricity መሰረት በማድረግ circular/ rectangular or square የሆነ ቅርፅ ሊኖራቸው ይችላል፡፡
▶️1.2)Combined Footing
➡️ሁለትና ከዛ በላይ ኮለኖችን በአንድ ፓድ support ለማድረግ ነው የምንጠቀምባቸው፡፡
➡️እነዚህን የምንጠቀመው ሁለት ተቀራራቢ Isolated Footing ካሉ ሁለቱን አንድ ላይ combine በማድረግ ኮንክሪትም ፌሮም ሴቭ ማድረግ እንችላለን፡፡
➡️በተጨማሪም isolated ለመጠቀም property limit ካለ እነዚህን መጠቀም እንችላለን::
➡️2 አይነት Combined Footing አሉፐእነርሱም
▶️1.2.1) Rectangular Combined Footing
➡️ይህንን የምንጠቀመው ሁለቱም ኮለኖች የሚሸከሙት ሎድ ተቀራራቢ ወይም እኩል ከሆከሆነይም ትራፖዞይዳል ለመጠቀም የስፋት ገደብ ካለ ነው።
▶️1.2.2. Trapezoidal Combined Footing
➡️ሁለቱ ኮለኖች የሚሸከሙት ሎድ ልዩነት የተጋነነ ከሆነ ነው።
▶️1.3) Strap/ Cantilever Footing
➡️ሁለት ፓዶችን በቢም በማያያዝ ሎድ ከአንዱ ፓድ ወደሌላው እንዲተላለፍ ማድረግ እንችላለን፡፡
➡️ቢሙ በራሱ ሎድ አይሸከምም ሎድ ያስተላልፋል እንጂ እነዚህን የምንጠቀመው ኮለኖቹ ከ7 ሜትር በላይ ከተራራቁ combined footing ብንጠቀም ኢኮኖሚካል ስለማንሆን ፓዶቹን በቢም በማያያዝ እንደ combined footing ልንጠቀምባቸው እንችላለን፡፡
▶️1.4) Mat/ Raft foundation
➡️እነዚህን የምንጠቀመው መሬቱ የመሸከም አቅሙ ትንሽ ከሆነና spread footing ስንጠቀም የህንጸውን ስፋት ከ50 ፐርሰንት በላይ ከሸፈኑት ነው።
➡️አንዳንዴ ግን spread footing ከ 50 ፐርሰንት በላይ ቢሸፍኑትም ለ spread footing negative reinforcement ስለማንጠቀም ከ Mat ይልቅ ኢኮኖሚካል ሊሆኑ ይችላሉ ምክንያቱም Mat negative & positive reinforcement ይጠቀማሉ፡፡
➡️ማን ኢኮኖሚካል እንደሆነ ቼክ ማድረግ የኢንጅነሩ ድርሻ ነው፡፡
⚡ቀጣይ ደሞ ስለ Deep Foundation እንማማራለን
#Foundation
@etconp
Ethio Construction Engineering
👉ከትላንት የቀጠለ 🏷ስለ የ Foundation (መሠረት) ኣይነቶች ትንሽ እንበል... 🚧1)Shallow Foundation ➡️እነዚህን ፋውንዴሽኖች የምንጠቀመው አፈሩ ብዙም ሳይቆፈር በቅርብ ጥልቀት ጠንካራ የአፈር ሁኔታ ካለ ነው፡፡ ➡️ለመገንባት ትልልቅ ማሺኖች አያስፈልጉም ብዙ ችሎታም አይጠይቁም:: ▶️1.1) Spread/ Pad/Isolated Footing ➡️አንድ ኮለን ብቻ ነው support…
👉Deep Foundation
➡️Most common types are
1. Piles
2. Cofferdams
3. Caisson
1.Pile Foundation
⏺Depending upon their function or use
1. Bearing piles
2. Friction piles
3. Sheet piles
4. Anchor piles
5. Batter piles
6. Fender piles
7. Compaction piles
⏺Depending upon the material used
1. Timber piles
2. Concrete piles
3. Composite piles
4. Steel piles
🏷Concrete piles
▶️Concrete piles may be classified as
1. Pre - cast piles
2. Cast - in - situ piles or Cast in place piles
3. Prestressed concrete piles
*⃣Various types of cast-in situ concrete piles are
1. Simplex pile
2. Franki pile
3. Vibro pile
4. Vibro - expanded pile
5. Raymond pile
6. Mac Arthur pile
🏷Steel piles
*⃣Types of steel piles commonly used are
1. H - piles
2. Pipe - piles
3. Screw piles
4. Disc piles
Sheet piles
*⃣These piles are driven side by side into the ground to form a continuous vertical wall.
🏷Sheet piles can be divided into three categories
1. Straight-web type
2. Shallow or deep arched- web type
3. Z web type
*⃣Depending upon the material used, sheet piles can be divided into
1. Wooden sheet piles
2. Precast concrete sheet piles
3. Prestressed concrete sheet piles
4. Steel sheet piles
🏷Pile driving Piles are driven in the ground by the following method
1. By drop hammer
2. By steam hammer ( single acting or double acting type )
3. By water jets
4. By boring
⏺2.Coffer dams
▶️These are temporary structure constructed in a river or a lake for excluding water from a given site to enable the building operation to be performed on dry surface.
▶️Cofferdams may be divided into
1. Earthen cofferdams
2. Rock - fill cofferdams
3. Single- walled cofferdams
4. Double-walled cofferdams
5. Crib cofferdams
6. Cellular cofferdams ( Circular or diaphragm type)
⏺3.Caissons
▶️A watertight structure made up of wood, steel or RCC constructed for the excavation for foundation in rivers or lakes.
▶️They remain in position and become integral part of the permanent structure.
▶️Caisson may be classified as
1. Open caisson ( open at top and bottom )
2. Box caisson ( closed at bottom and open at top)
3. Pneumatic caisson ( closed at top and open at bottom)
#Foundation
@etconp
➡️Most common types are
1. Piles
2. Cofferdams
3. Caisson
1.Pile Foundation
⏺Depending upon their function or use
1. Bearing piles
2. Friction piles
3. Sheet piles
4. Anchor piles
5. Batter piles
6. Fender piles
7. Compaction piles
⏺Depending upon the material used
1. Timber piles
2. Concrete piles
3. Composite piles
4. Steel piles
🏷Concrete piles
▶️Concrete piles may be classified as
1. Pre - cast piles
2. Cast - in - situ piles or Cast in place piles
3. Prestressed concrete piles
*⃣Various types of cast-in situ concrete piles are
1. Simplex pile
2. Franki pile
3. Vibro pile
4. Vibro - expanded pile
5. Raymond pile
6. Mac Arthur pile
🏷Steel piles
*⃣Types of steel piles commonly used are
1. H - piles
2. Pipe - piles
3. Screw piles
4. Disc piles
Sheet piles
*⃣These piles are driven side by side into the ground to form a continuous vertical wall.
🏷Sheet piles can be divided into three categories
1. Straight-web type
2. Shallow or deep arched- web type
3. Z web type
*⃣Depending upon the material used, sheet piles can be divided into
1. Wooden sheet piles
2. Precast concrete sheet piles
3. Prestressed concrete sheet piles
4. Steel sheet piles
🏷Pile driving Piles are driven in the ground by the following method
1. By drop hammer
2. By steam hammer ( single acting or double acting type )
3. By water jets
4. By boring
⏺2.Coffer dams
▶️These are temporary structure constructed in a river or a lake for excluding water from a given site to enable the building operation to be performed on dry surface.
▶️Cofferdams may be divided into
1. Earthen cofferdams
2. Rock - fill cofferdams
3. Single- walled cofferdams
4. Double-walled cofferdams
5. Crib cofferdams
6. Cellular cofferdams ( Circular or diaphragm type)
⏺3.Caissons
▶️A watertight structure made up of wood, steel or RCC constructed for the excavation for foundation in rivers or lakes.
▶️They remain in position and become integral part of the permanent structure.
▶️Caisson may be classified as
1. Open caisson ( open at top and bottom )
2. Box caisson ( closed at bottom and open at top)
3. Pneumatic caisson ( closed at top and open at bottom)
#Foundation
@etconp
👉DIFFERENCE BETWEEN PERT AND CPM
➡PERT and CPM are most commonly used methods for project management.
➡️In this article, we will discuss the differences between PERT and CPM.
🚧WHAT IS PERT?
➡️PERT or Programme Evaluation and Review
Technique is an event oriented method of network planning. In it, the emphasis is focused on start and completion events rather than on activities.
➡️The activities taking place between events are not specified.
➡️In PERT network, the events fall in logical
sequence But the logic of events may be different
for different planners. Hence PERT network may
vary from planner to planner depending upon their decision as which event to precede or occur
concurrently.
➡️In PERT network the start circle is omitted and only the completed event is recorded.
➡️PERT helps in identifying critical area which threatens the completion of the work.
➡️It provides the means to
determine how resources can be transferred from
one job to another job.
🚧WHAT IS CPM?
➡️CPM is also network comprising events and
activities.
➡️This network is activity based.
➡️The activities are represented by arrowed lines and events by circles.
➡️The activities are connected in logical sequence.
➡️The time allotted to each activity is related to cost.
🚧DIFFERENCE BETWEEN PERT AND CPM
🏷1. PERT is event oriented whereas CPM is activity oriented.
▶️In simple words, in PERT network interest is focused upon start or completion of events and
not on activities themselves.
🏷2. In CPM network no allowance is made for
uncertainties in the duration of time involved
whereas in PERT network uncertainty is considered.
🏷3. In PERT, time is not related to cost whereas in
CPM the object is to develop an optimum time
cost relationship. However, PERT has since been
extended in this direction and the line dividing
PERT/CPM is gradually fading out.
🏷4. In CPM duration of activity is estimated with a
fair degree of accuracy. In PERT duration of
activities are not so accurate and definite.
🏷5. In CPM both time and cost can be controlled
during planning. Pert is basically a tool for
planning
🏷6. PERT is used in research and development
project, basically for non-repetitive type projects.
CPM is widely used in construction projects.
#PERT
#CPM
#ConstructionPlanning
@etconp
➡PERT and CPM are most commonly used methods for project management.
➡️In this article, we will discuss the differences between PERT and CPM.
🚧WHAT IS PERT?
➡️PERT or Programme Evaluation and Review
Technique is an event oriented method of network planning. In it, the emphasis is focused on start and completion events rather than on activities.
➡️The activities taking place between events are not specified.
➡️In PERT network, the events fall in logical
sequence But the logic of events may be different
for different planners. Hence PERT network may
vary from planner to planner depending upon their decision as which event to precede or occur
concurrently.
➡️In PERT network the start circle is omitted and only the completed event is recorded.
➡️PERT helps in identifying critical area which threatens the completion of the work.
➡️It provides the means to
determine how resources can be transferred from
one job to another job.
🚧WHAT IS CPM?
➡️CPM is also network comprising events and
activities.
➡️This network is activity based.
➡️The activities are represented by arrowed lines and events by circles.
➡️The activities are connected in logical sequence.
➡️The time allotted to each activity is related to cost.
🚧DIFFERENCE BETWEEN PERT AND CPM
🏷1. PERT is event oriented whereas CPM is activity oriented.
▶️In simple words, in PERT network interest is focused upon start or completion of events and
not on activities themselves.
🏷2. In CPM network no allowance is made for
uncertainties in the duration of time involved
whereas in PERT network uncertainty is considered.
🏷3. In PERT, time is not related to cost whereas in
CPM the object is to develop an optimum time
cost relationship. However, PERT has since been
extended in this direction and the line dividing
PERT/CPM is gradually fading out.
🏷4. In CPM duration of activity is estimated with a
fair degree of accuracy. In PERT duration of
activities are not so accurate and definite.
🏷5. In CPM both time and cost can be controlled
during planning. Pert is basically a tool for
planning
🏷6. PERT is used in research and development
project, basically for non-repetitive type projects.
CPM is widely used in construction projects.
#PERT
#CPM
#ConstructionPlanning
@etconp
Ethio Construction Engineering
👉DIFFERENCE BETWEEN PERT AND CPM ➡PERT and CPM are most commonly used methods for project management. ➡️In this article, we will discuss the differences between PERT and CPM. 🚧WHAT IS PERT? ➡️PERT or Programme Evaluation and Review Technique is an event…
👉PERT (Project/Programme Evaluation and Review Technique)
➡️Event oriented
➡️Probabilistic approach
➡️3 time estimates
(optimistic, pessimistic and most likely)
➡️Follows Beta distribution curve
➡️Time is only controlling factor
➡️Critical events may be +ve, -ve or zero
➡️Recommended for research, development and new projects.
👉CPM (Critical Path Method)
🚧Activity oriented
🚧Deterministic approach
🚧Only 1 time estimate
🚧Normal distribution
🚧Time and cost both are controlling factors
🚧Critical events must have zero slack
🚧Recommended for repetitive nature of work.
👉Errors in Network
(2 Types)
▶️Constructional Error
▶️Conceptual Error
🏷Constructional Error
(2 Types)
⏺Looping error ( Diagram form a loop )
⏺Dangling Error ( One or more activities have no effect on project time)
🏷Conceptual Error
(1 Type)
*⃣Wagon Wheel Error ( Logical error is present )
#PERT
#CPM
#ConstructionPlanning
@etconp
➡️Event oriented
➡️Probabilistic approach
➡️3 time estimates
(optimistic, pessimistic and most likely)
➡️Follows Beta distribution curve
➡️Time is only controlling factor
➡️Critical events may be +ve, -ve or zero
➡️Recommended for research, development and new projects.
👉CPM (Critical Path Method)
🚧Activity oriented
🚧Deterministic approach
🚧Only 1 time estimate
🚧Normal distribution
🚧Time and cost both are controlling factors
🚧Critical events must have zero slack
🚧Recommended for repetitive nature of work.
👉Errors in Network
(2 Types)
▶️Constructional Error
▶️Conceptual Error
🏷Constructional Error
(2 Types)
⏺Looping error ( Diagram form a loop )
⏺Dangling Error ( One or more activities have no effect on project time)
🏷Conceptual Error
(1 Type)
*⃣Wagon Wheel Error ( Logical error is present )
#PERT
#CPM
#ConstructionPlanning
@etconp